- 2079 Chaitra · 5 marks
Factors in deciding canal alignment
Short answer
Canal alignment follows the highest ground (ridge) for maximum command area by gravity. It minimizes earthwork by staying near balancing depth, avoids costly cross-drainage works, and selects stable geology. Alignment uses gentle curves, avoids villages and fertile land, reduces land acquisition costs, and provides required head with few drops.
What factors do you consider while deciding a canal alignment?
The alignment should give the maximum command at minimum cost and be safe. The factors are:
- Command: keep the canal on the highest ground (watershed/ridge) so that gravity irrigation covers the largest area, with the full supply level above the field levels.
- Topography and contours: avoid unnecessary deep cuttings and high fillings; follow the ground slope as far as possible; keep near the balancing depth for economy of earthwork.
- Cross-drainage works: keep the number of drainage crossings (aqueducts, culverts) to a minimum, as each is costly.
- Geology and soil: avoid rocky, sandy, porous or landslide-prone areas, and saline or swampy ground.
- Straight and smooth alignment: avoid sharp bends (use curves of radius at least 5 times the bed width), and avoid cutting through villages and fertile land.
- Land acquisition and existing structures: avoid roads, houses and religious places, to keep compensation low.
- Head and drops: the length and bed slope should provide the needed head with the fewest falls.
- Command and field boundaries: align along property boundaries; avoid splitting farms.
- Future extension and drainage: allow for extension and avoid waterlogging.
- Accessibility for construction and O&M, and nearness of construction material (borrow area).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Alignment factors and canal types · Irrigation and Drainage Engineering, chapter 3
- Why a canal fall; site selection factors · Irrigation and Drainage Engineering, chapter 7
- Canal in alluvium, Q 64, d 0.5 mm · Irrigation and Drainage Engineering, chapter 4
- Possible alignments of an irrigation canal · Irrigation and Drainage Engineering, chapter 3 · asked 5×
- Factors while routing signal traces on PCB · Instrumentation II, chapter 8 · asked 4×
- Material handling and factors to consider · Construction Management, chapter 6
- Geological parameters for canal alignment · Engineering Geology II, chapter 4
- Factors controlling highway alignment · Transportation Engineering I, chapter 2 · asked 12×
All Irrigation and Drainage Engineering chapter 3 questions →