Canals are classified by alignment: watershed canals run along ridges, commanding both sides with minimal cross-drainage; contour canals follow contours, irrigating one side with many cross-drainage works; side-slope canals run perpendicular to contours, with limited command and few cross-drainage works.
Describe with sketch the possible alignments of an irrigation canal (classification of canals based on alignment).
Canals are classified by alignment according to the ground they follow.
1. Watershed (ridge) canal
Aligned along the ridge line between two drainage basins. Water can flow by gravity to both sides, there is no cross-drainage work, and the whole area can be commanded.
ridge
fields /\ fields
____ / \ ____
command canal command
2. Contour canal
Runs along a contour line with a very small slope; used in hilly areas. It irrigates only the land on its lower side. It meets streams, so it needs cross-drainage works and is liable to landslides.
hill (higher side)
===== canal along contour ======>
irrigated area on one side only
3. Side-slope canal
Runs roughly at right angles to the contours, on the side slope of the ground, between a watershed and a drainage line. It meets no cross-drainage, but is liable to be damaged by runoff from the hill side, so it is protected by catch drains.
ridge
\ canal (perpendicular to contours)
\ -->
\
drainage line
Comparison
| Type | Command | Cross-drainage works |
|---|---|---|
| Watershed | Both sides, largest | Almost none |
| Contour | One side | Many |
| Side slope | Limited | Few |
In plains the main canal is generally a watershed canal; in hills contour or side-slope canals are used.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Alignment factors and canal types · Irrigation and Drainage Engineering, chapter 3
- Short note: Design of hilly irrigation canals · Irrigation and Drainage Engineering, chapter 3
- Factors in deciding canal alignment · Irrigation and Drainage Engineering, chapter 3
- Types of lining in irrigation canals · Irrigation and Drainage Engineering, chapter 4
- Components of canal irrigation system · Irrigation and Drainage Engineering, chapter 3 · asked 7×
- Alluvial and non-alluvial canals · Irrigation and Drainage Engineering, chapter 3 · asked 2×
- Geological parameters for canal alignment · Engineering Geology II, chapter 4
- Irrigation canal earthwork with vertical drop · Estimating and Costing, chapter 6
- Irrigation canal earthwork, 0-600 m · Estimating and Costing, chapter 6
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
All Irrigation and Drainage Engineering chapter 3 questions →