Irrigation channel earthwork, bed 5 m, 1 in 3000

Short answer

Total depth D = 1.6 m. Bed falls 0.10 m per 300 m. At sections 0 and 300 full cutting occurs, sections 600 and 900 are part cutting/part banking. Earthwork in cutting = 8,831.25 m³, banking = 1,828.50 m³, total = 10,659.75 m³.

Calculate the quantity of earthwork of an irrigation channel with the following data: Bed width of channel = 5 m; Top width of both banks = 2 m; Longitudinal slope of bed = 1 in 3000; Side slopes in cutting and filling = 1½:1 (H:V); Fully supply depth = 1 m; Free board = 0.60 m; R.L. of bed at 0 m = 1395.50 m. Ground level along the alignment are as given below:

R.L. of Ground1397.501397.001396.501395.70
Distance0300600900

Given data and assumptions

  • Bed width 55 m; FSD 11 m; free board 0.60.6 m, so D=1.6D = 1.6 m; top width of each bank 22 m; side slope 1.5:11.5:1 for cutting and banking (inner and outer).
  • Bed RL 1395.50 m at 0, falling 1 in 3000: 1395.50, 1395.40, 1395.30, 1395.20 m at 0, 300, 600, 900 m.

Method

Total depth of canal section D=FSD+free board=1.00+0.60=1.60D = \text{FSD} + \text{free board} = 1.00 + 0.60 = 1.60 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
01,397.5001,395.5002.000full cutting16.0000.000
3001,397.0001,395.4001.600full cutting (e=De = D)11.8400.000
6001,396.5001,395.3001.200part cutting, part banking8.1602.080
9001,395.7001,395.2000.500part cutting, part banking2.8758.030

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0 – 300300.04,176.000.00
300 – 600300.03,000.00312.00
600 – 900300.01,655.251,516.50
Total8,831.251,828.50

Answer: Earthwork in cutting = 8,831.25 m³; earthwork in banking = 1,828.50 m³; total = 10,659.75 m³.