- 2076 Asoj · 9 marks
Irrigation channel earthwork, bed 5 m, 1 in 3000
Short answer
Total depth D = 1.6 m. Bed falls 0.10 m per 300 m. At sections 0 and 300 full cutting occurs, sections 600 and 900 are part cutting/part banking. Earthwork in cutting = 8,831.25 m³, banking = 1,828.50 m³, total = 10,659.75 m³.
Calculate the quantity of earthwork of an irrigation channel with the following data: Bed width of channel = 5 m; Top width of both banks = 2 m; Longitudinal slope of bed = 1 in 3000; Side slopes in cutting and filling = 1½:1 (H:V); Fully supply depth = 1 m; Free board = 0.60 m; R.L. of bed at 0 m = 1395.50 m. Ground level along the alignment are as given below:
| R.L. of Ground | 1397.50 | 1397.00 | 1396.50 | 1395.70 |
|---|---|---|---|---|
| Distance | 0 | 300 | 600 | 900 |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of each bank m; side slope for cutting and banking (inner and outer).
- Bed RL 1395.50 m at 0, falling 1 in 3000: 1395.50, 1395.40, 1395.30, 1395.20 m at 0, 300, 600, 900 m.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0 | 1,397.500 | 1,395.500 | 2.000 | full cutting | 16.000 | 0.000 |
| 300 | 1,397.000 | 1,395.400 | 1.600 | full cutting () | 11.840 | 0.000 |
| 600 | 1,396.500 | 1,395.300 | 1.200 | part cutting, part banking | 8.160 | 2.080 |
| 900 | 1,395.700 | 1,395.200 | 0.500 | part cutting, part banking | 2.875 | 8.030 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0 – 300 | 300.0 | 4,176.00 | 0.00 |
| 300 – 600 | 300.0 | 3,000.00 | 312.00 |
| 600 – 900 | 300.0 | 1,655.25 | 1,516.50 |
| Total | 8,831.25 | 1,828.50 |
Answer: Earthwork in cutting = 8,831.25 m³; earthwork in banking = 1,828.50 m³; total = 10,659.75 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Channel earthwork with drop at 0+090 · Estimating and Costing, chapter 6
- Irrigation canal earthwork, 0-600 m · Estimating and Costing, chapter 6
- Channel fully in banking, 0.5-1.5 km · Estimating and Costing, chapter 6
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Balancing depth: bed width 25 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Stable depth and bed width: Q 5, d50 3 cm · Irrigation and Drainage Engineering, chapter 4