Skip to main content

Chapter 6 · 20 hours

Detailed Estimate

IOE past exam questions

Past questions and answers

80 questions set from this chapter, 1 of them more than once; 1 is most repeated (set, or a close variant set, in 3 or more exams). Most repeated first.

  • Most repeated · 3 of 22 exams
  • 2067 Asar (old course) · 7 marks

Find out the quantity of earthwork of a portion of road to be constructed with the following data: Formation width of the road throughout = 10 m. Side slope in banking (2:1) and side slope in cutting (1:1). Downward grade 1 in 120 from distance 90 m to 120 m. While it remains in level from distance 120 m to 180 m and has again upward grade 1 in 90 from distance 180 m to 210 m. The formation level at distance 180 m = 1197.50 m. The ground levels are as under:
R.L. of ground1198.651196.401199.301200.401198.10
Distance (m)90120150180210

Similar questions: Road earthwork, grades 1 in 120 and 1 in 90 (0-120) (2068 Baisakh (old course)) · Road earthwork, formation level at 150 m (2067 Poush (old course))

Answer

Given data and assumptions

  • Formation width 1010 m throughout; banking slope 2:12:1, cutting slope 1:11:1; ground level across the road.
  • Formation level at 180 m is 1197.50 m; level from 120 m to 180 m; falling 1 in 120 from 90 to 120 m, so level at 90 m = 1197.50 + 30/120 = 1197.75 m; rising 1 in 90 from 180 to 210 m, so level at 210 m = 1197.833 m.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+0901,198.6501,197.750cutting 0.900
0+1201,196.4001,197.500filling 1.100
0+1501,199.3001,197.500cutting 1.800
0+1801,200.4001,197.500cutting 2.900
0+2101,198.1001,197.833cutting 0.267

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+090cut 0.909.8100.000
0+120fill 1.100.00013.420
0+150cut 1.8021.2400.000
0+180cut 2.9037.4100.000
0+210cut 0.272.7380.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+090 – 0+12030.066.22110.71
0+120 – 0+15030.0197.7576.36
0+150 – 0+18030.0879.750.00
0+180 – 0+21030.0602.220.00
Total120.01,745.94187.07

Answer: Earthwork in cutting = 1,745.94 m³; earthwork in filling = 187.07 m³.

  • Asked 2 times
  • 2075 Chaitra · 5+2 marks
  • 2070 Chaitra · 5+3 marks

Find out the quantities of the following items of work of a T-beam decking of a bridge with 6 m span and 45 cm bearing at ends. i) RCC work (1:2:4) excluding steel ii) Cement concrete (1:2:4) in wearing coat [Figure: RCC T-beam decking cross-section. Overall width 7.7 m, 7 m roadway, 20×20 cm kerb on each side, 10 cm wearing coat of C.C., 20 cm slab, three ribs each 35 cm wide with 225 cm clear between ribs, rib depth below slab 75 cm (107.5 cm projections at the edges), 15×15 cm fillets, 15×15 cm RCC railing posts 120 cm high at 136 cm c/c, 40 mm dia G.I. pipe 4 nos., railing height 120 cm.]

Answer

Assumptions from the figure

  • Length of decking =6.00+2×0.45=6.90= 6.00 + 2 \times 0.45 = 6.90 m (clear span plus bearing at both ends).
  • Overhang of slab beyond outer ribs =(7.70−3×0.35−2×2.25)/2=1.075= (7.70 - 3 \times 0.35 - 2 \times 2.25)/2 = 1.075 m (matches the 107.5 cm in the figure).
  • Fillets are taken as triangles of 15 × 15 cm at both sides of each rib (6 in total). The railing posts are at 1.36 m c/c: with 6.90 m length this gives 6 posts per side, 12 in all.
  • The 20 cm slab is taken from the figure; the kerb is 20 × 20 cm above the slab, and the wearing coat (10 cm) is laid between the kerbs over the 7.0 m roadway.

(i) RCC work (1:2:4), excluding steel

MemberWorkingVolume (m³)
Slab7.70×6.90×0.207.70 \times 6.90 \times 0.2010.626
Ribs (3)3×0.35×0.75×6.903 \times 0.35 \times 0.75 \times 6.905.434
Fillets (6, 15 × 15 cm triangular)6×12×0.15×0.15×6.906 \times \tfrac12 \times 0.15 \times 0.15 \times 6.900.466
Kerbs (2)2×0.20×0.20×6.902 \times 0.20 \times 0.20 \times 6.900.552
Railing posts (12 nos, 15 × 15 × 120 cm)12×0.15×0.15×1.2012 \times 0.15 \times 0.15 \times 1.200.324
Total RCC (1:2:4)17.402

(ii) Cement concrete (1:2:4) in wearing coat

V=7.00×6.90×0.10=4.830V = 7.00 \times 6.90 \times 0.10 = 4.830 m³

Answer: RCC = 17.402 m³; wearing coat = 4.830 m³.

Materials for information (1:2:4, dry factor 1.54): RCC needs 110.3 bags cement, 7.66 m³ sand, 15.31 m³ aggregate; wearing coat needs 30.6 bags, 2.13 m³, 4.25 m³.

  • 2081 Bhadra · 8 marks

Data for a hill road portion is given below. Calculate the volume of earthwork.
ChainageDepth of Cutting (m)Height of banking (m)Transverse Slope of Ground
0+020 m0.6-10:1
0+070 m0.7-15:1
0+140 m-0.812:1
Width in cutting = 8 m, Formation width in banking = 10 m, Side slope in cutting = 1.5:1 (H:V), Side slope in banking = 2:1 (H:V).

Similar questions: Hill road earthwork, 0 m to 90 m, 10/8 m widths (2080 Bhadra)

Answer

Given data and assumptions

  • Formation width: cutting 88 m, banking 1010 m; side slopes: cutting 1.5:11.5:1, banking 2:12:1 (H:V).
  • Sections at 0+020, 0+070 and 0+140 m, so the distances are 50 m and 70 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+020cut 0.605.7080.000
0+070cut 0.706.5070.000
0+140fill 0.800.0009.902

Working for one section:

Take chainage 0+020: centre cutting depth h=0.60h = 0.60 m, n=10n = 10, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =1.000= 1.000 m, at the downhill edge =0.200= 0.200 m.
  • Toe of the side slope on the uphill side at x=5.765x = 5.765 m from the centre line (ground above formation by 1.176 m); downhill toe at x=4.261x = 4.261 m (ground above formation by 0.174 m).
  • Area from the co-ordinates of the polygon: cutting =5.708= 5.708 m², filling =0.000= 0.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+020 – 0+07050.0305.380.00
0+070 – 0+14070.0227.74346.58
Total120.0533.12346.58

Answer: Earthwork in cutting = 533.12 m³; earthwork in filling = 346.58 m³.

  • 2080 Bhadra · 8 marks

Calculate the volume of earthwork of a portion of hill road from the given data: Top formation width in cutting = 8 m, top formation width in banking = 10 m, side slope in cutting and banking are 1.5:1 and 2:1 (H:V), respectively.
DistanceHeight of FillingDepth of CuttingTransverse Slope of Ground (H:V)
0 m-0.6010:1
30 m-0.7015:1
60 m0.80-12:1
90 m0.85-10:1

Similar questions: Hill road earthwork, 0+020 to 0+140 (2081 Bhadra)

Answer

Given data and assumptions

  • Formation width: cutting 88 m, banking 1010 m; side slopes: cutting 1.5:11.5:1, banking 2:12:1 (H:V).
  • Sections 30 m apart. Cutting at 0 m and 30 m, filling at 60 m and 90 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.605.7080.000
0+030cut 0.706.5070.000
0+060fill 0.800.0009.902
0+090fill 0.850.00010.880

Working for one section:

Take chainage 0+090: centre filling height h=0.85h = 0.85 m, n=10n = 10, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =−0.350= -0.350 m, at the downhill edge =−1.350= -1.350 m.
  • Toe of the side slope on the uphill side at x=5.583x = 5.583 m from the centre line (ground below formation by 0.292 m); downhill toe at x=8.375x = 8.375 m (ground below formation by 1.688 m).
  • Area from the co-ordinates of the polygon: cutting =0.000= 0.000 m², filling =10.880= 10.880 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0183.230.00
0+030 – 0+06030.097.60148.53
0+060 – 0+09030.00.00311.74
Total90.0280.83460.27

Answer: Earthwork in cutting = 280.83 m³; earthwork in filling = 460.27 m³.

  • 2068 Baisakh (old course) · 8 marks

Estimate the quantity of earthwork of a portion of road from the following data: Formation width of the road = 10 m. Side slope in banking = 2:1 (H:V), side slope in cutting = 1:1. Downward grade 1 in 120 from distance 0 m to 30 m while it remains in level from distance 30 m to 90 m and has again upward grade 1 in 90 from distance 90 to 120 m. The formation level at distance 60 m = 1197.50 m. The ground levels of the centre line of the road are as under:
R.L. of ground1198.651196.401199.301200.401198.10
Distance in m0306090120

Similar questions: Road earthwork, grades from 90 m to 210 m (s) (2067 Asar (old course))

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; banking slope 2:12:1, cutting slope 1:11:1. Ground is level across the road.
  • Formation levels: 1197.50 m at 60 m; level from 30 m to 90 m; falling 1 in 120 from 0 to 30 m, so the level at 0 m is 1197.50 + 30/120 = 1197.75 m; rising 1 in 90 from 90 to 120 m, so the level at 120 m is 1197.50 + 30/90 = 1197.833 m.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+0001,198.6501,197.750cutting 0.900
0+0301,196.4001,197.500filling 1.100
0+0601,199.3001,197.500cutting 1.800
0+0901,200.4001,197.500cutting 2.900
0+1201,198.1001,197.833cutting 0.267

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.909.8100.000
0+030fill 1.100.00013.420
0+060cut 1.8021.2400.000
0+090cut 2.9037.4100.000
0+120cut 0.272.7380.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.066.22110.71
0+030 – 0+06030.0197.7576.36
0+060 – 0+09030.0879.750.00
0+090 – 0+12030.0602.220.00
Total120.01,745.94187.07

Answer: Earthwork in cutting = 1,745.94 m³; earthwork in filling = 187.07 m³.

  • 2067 Asar (old course) · 7 marks

Estimate the quantity of earthwork in cutting and filling from the following data for a portion of road. Formation width = 10 m, side slope in banking = 2:1, side slope in cutting = 1:1.
ChainageDepth of cutting (m)Height of filling (m)Cross slope of ground
00.60—10:1
200.30—8:1
400.50—12:1
60—0.3510:1
80—0.7012:1

Similar questions: Road earthwork, 80 m length (v) (2065 Shrawan (old course))

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in banking 2:12:1, in cutting 1:11:1.
  • Sections 20 m apart; cutting up to 40 m and filling at 60 m and 80 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.606.6770.000
0+020cut 0.303.9110.563
0+040cut 0.505.4620.000
0+060fill 0.350.1254.516
0+080fill 0.700.0008.565

Working for one section:

Take chainage 0+020: centre cutting depth h=0.30h = 0.30 m, n=8n = 8, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.925= 0.925 m, at the downhill edge =−0.325= -0.325 m.
  • Toe of the side slope on the uphill side at x=6.057x = 6.057 m from the centre line (ground above formation by 1.057 m); downhill toe at x=5.867x = 5.867 m (ground below formation by 0.433 m).
  • Area from the co-ordinates of the polygon: cutting =3.911= 3.911 m², filling =0.563= 0.563 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+02020.0105.885.63
0+020 – 0+04020.093.735.63
0+040 – 0+06020.055.8745.16
0+060 – 0+08020.01.25130.81
Total80.0256.73187.23

Answer: Earthwork in cutting = 256.73 m³; earthwork in filling = 187.23 m³.

  • 2067 Poush (old course) · 10 marks

Find out the quantity of earth work of a portion of road to be constructed with the following data: Formation width of the road = 10 m. Side slopes in banking and cutting = (2:1) and (1:1). Downward grade 1 in 120 from distance 90 to 120 m while it remains in level from distance 120 to 180 m and again upward grade 1 in 90 from distance 180 to 210 m. The formation level at distance 150 m = 1197.50.
R.L. of ground1198.651196.401199.301200.401198.10
Distance (m)90120150190210

Similar questions: Road earthwork, grades from 90 m to 210 m (s) (2067 Asar (old course))

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; banking slope 2:12:1, cutting slope 1:11:1. Ground is level across the road. Stations are at 90, 120, 150, 190 and 210 m (spacing 30, 30, 40, 20 m).
  • Formation level at 150 m is 1197.50 m; level from 120 m to 180 m; falling 1 in 120 from 90 to 120 m, so level at 90 m = 1197.75 m; rising 1 in 90 from 180 m, so level at 190 m = 1197.50 + 10/90 = 1197.611 m and at 210 m = 1197.833 m.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+0901,198.6501,197.750cutting 0.900
0+1201,196.4001,197.500filling 1.100
0+1501,199.3001,197.500cutting 1.800
0+1901,200.4001,197.611cutting 2.789
0+2101,198.1001,197.833cutting 0.267

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+090cut 0.909.8100.000
0+120fill 1.100.00013.420
0+150cut 1.8021.2400.000
0+190cut 2.7935.6670.000
0+210cut 0.272.7380.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+090 – 0+12030.066.22110.71
0+120 – 0+15030.0197.7576.36
0+150 – 0+19040.01,138.140.00
0+190 – 0+21020.0384.050.00
Total120.01,786.15187.07

Answer: Earthwork in cutting = 1,786.15 m³; earthwork in filling = 187.07 m³.

  • 2065 Shrawan (old course) · 10 marks

Estimate the quantity of earthwork in cutting and filling from the following data for a portion of road 80 m length. Formation width = 10 m. Side slopes in banking 2:1. Side slopes in cutting 1:1.
ChainageDepth of cutting at centre lineHeight of bankingCross slope of ground
0 m0.60—10:1
20 m0.70—12:1
40 m0.50—15:1
60 m0.3012:1
80 m0.7010:1

Similar questions: Road earthwork, chainage 0-80 (s) (2067 Asar (old course))

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in banking 2:12:1, in cutting 1:11:1.
  • Sections 20 m apart: cutting at 0, 20, 40 m and filling at 60, 80 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.606.6770.000
0+020cut 0.707.7170.000
0+040cut 0.505.3850.000
0+060fill 0.300.0893.698
0+080fill 0.700.0008.833

Working for one section:

Take chainage 0+020: centre cutting depth h=0.70h = 0.70 m, n=12n = 12, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =1.117= 1.117 m, at the downhill edge =0.283= 0.283 m.
  • Toe of the side slope on the uphill side at x=6.218x = 6.218 m from the centre line (ground above formation by 1.218 m); downhill toe at x=5.262x = 5.262 m (ground above formation by 0.262 m).
  • Area from the co-ordinates of the polygon: cutting =7.717= 7.717 m², filling =0.000= 0.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+02020.0143.940.00
0+020 – 0+04020.0131.020.00
0+040 – 0+06020.054.7436.98
0+060 – 0+08020.00.89125.31
Total80.0330.59162.29

Answer: Earthwork in cutting = 330.59 m³; earthwork in filling = 162.29 m³.

  • 2080 Baisakh · 12 marks

Calculate the quantity of earthwork and area of permanent land required for the land acquisition purpose for a portion of a channel from following data: Bed width = 4 m; Free board = 45 cm; Side slope in cutting = 1:1; Side slope in banking = 1.5:1; Full supply depth = 1 m; Top width of bank = 3 m left and 1.5 m right.
Chainage90120150180210220
RL Ground109.8109.7109.55109.30109.15109.10
RL Bed109.52Bed slope 1:300 rising

Similar questions: Channel earthwork and land area, 50 cm fall (2078 Bhadra)

Answer

Given data and assumptions

  • Bed width 44 m; FSD 11 m; free board 0.450.45 m, so D=1.45D = 1.45 m; top width of bank 33 m (left) and 1.51.5 m (right).
  • Side slope in cutting 1:11:1, in banking 1.5:11.5:1 (inner and outer faces of banks).
  • Bed level 109.52 m at chainage 90, rising at 1 in 300 with chainage (assumed direction): 109.52, 109.62, 109.72, 109.82, 109.92, 109.953 m.

Method

Total depth of canal section D=FSD+free board=1.00+0.45=1.45D = \text{FSD} + \text{free board} = 1.00 + 0.45 = 1.45 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+090109.800109.5200.280part cutting, part banking1.1989.372
0+120109.700109.6200.080part cutting, part banking0.32611.796
0+150109.550109.720-0.170full banking0.00015.800
0+180109.300109.820-0.520full banking0.00022.182
0+210109.150109.920-0.770full banking0.00026.966
0+220109.100109.953-0.853full banking0.00028.602

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+090 – 0+12030.022.87317.51
0+120 – 0+15030.04.90413.93
0+150 – 0+18030.00.00569.73
0+180 – 0+21030.00.00737.22
0+210 – 0+22010.00.00277.84
Total27.772,316.23

Permanent land

Width of land at a section = distance between the outer toes of the banks (banking) or canal top width plus the two bank/berm widths (cutting).

StationLand width (m)
0+09016.080
0+12016.880
0+15017.710
0+18018.760
0+21019.510
0+22019.760

Area of land == mean width × length, summed over the reaches =2,330.70= 2,330.70 m² =0.2331= 0.2331 ha.

Answer: Earthwork in cutting = 27.77 m³; earthwork in banking = 2,316.23 m³; total = 2,344.00 m³. Permanent land = 2,330.70 m².

  • 2078 Bhadra · 10 marks

Calculate the quantity of earthwork and area of permanent land required for the land acquisition purpose for a portion of a channel from following data: Bed width = 4 m; Free board = 45 cm; Side slope in cutting = 1:1; Side slope in banking = 1.5:1; Full supply depth = 1 m; Top width of bank = 3 m left and 1.5 m right. There is 50 cm fall at chainage 800 m.
Chainage80085090095010001050
RL ground109.8109.7109.55109.30109.25109.15
RL Bed109.52Bed slope 1:250

Similar questions: Channel earthwork and land area, bed 4 m (2080 Baisakh)

Answer

Given data and assumptions

  • Bed width 44 m; FSD 11 m; free board 0.450.45 m, so D=1.45D = 1.45 m; top width of bank 33 m (left) and 1.51.5 m (right).
  • Side slope in cutting 1:11:1, in banking 1.5:11.5:1 (inner and outer faces of banks).
  • The printed bed level 109.52 m at chainage 800 is the level just upstream of the 0.50 m fall; the reach considered starts after the fall, so bed at 800 is 109.02 m, rising 1 in 250 with chainage (same direction as the companion problem): 109.02, 109.22, 109.42, 109.62, 109.82, 110.02 m.

Method

Total depth of canal section D=FSD+free board=1.00+0.45=1.45D = \text{FSD} + \text{free board} = 1.00 + 0.45 = 1.45 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+800109.800109.0200.780part cutting, part banking3.7284.362
0+850109.700109.2200.480part cutting, part banking2.1507.188
0+900109.550109.4200.130part cutting, part banking0.53711.167
0+950109.300109.620-0.320full banking0.00018.490
1+000109.250109.820-0.570full banking0.00023.124
1+050109.150110.020-0.870full banking0.00028.932

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+800 – 0+85050.0146.97288.73
0+850 – 0+90050.067.18458.87
0+900 – 0+95050.013.42741.43
0+950 – 1+00050.00.001,040.35
1+000 – 1+05050.00.001,301.39
Total227.583,830.78

Permanent land

Width of land at a section = distance between the outer toes of the banks (banking) or canal top width plus the two bank/berm widths (cutting).

StationLand width (m)
0+80014.080
0+85015.280
0+90016.680
0+95018.160
1+00018.910
1+05019.810

Area of land == mean width × length, summed over the reaches =4,298.75= 4,298.75 m² =0.4299= 0.4299 ha.

Answer: Earthwork in cutting = 227.58 m³; earthwork in banking = 3,830.78 m³; total = 4,058.36 m³. Permanent land = 4,298.75 m².

  • 2065 Shrawan (old course) · 15 marks

Estimate the quantities of the following items of work from the accompanying drawing. (Aqueduct) a) Earthwork in excavation b) Cement concrete in foundation c) Brick work d) RCC work [Drawing not included in the scanned paper]

Similar questions: Earthwork, concrete, brick, RCC from drawing (2067 Asar (old course))

Answer

A drawing is not given, so the method is shown on an assumed small aqueduct: a single-span RCC trough carrying an irrigation canal over a drain, resting on two brick abutments with four wing walls. All quantities are by the centre-line / length × breadth × depth method.

Assumed data

  • Trough: clear span 6.0 m, bearing 0.3 m each end (length 6.6 m), internal width 2.0 m, depth 1.2 m, walls 0.20 m, bottom slab 0.25 m, so outside width 2.4 m.
  • Abutments (2 nos.): length 3.4 m, thickness 0.9 m, height 2.5 m above PCC, in 1:6 brickwork; PCC 1:3:6 bed 4.0 m × 1.5 m × 0.30 m.
  • Wing walls (4 nos.): 2.0 m long, mean thickness 0.45 m, mean height 2.0 m; PCC 2.0 m × 0.9 m × 0.30 m.
  • Abutment pit depth 1.5 m with 0.3 m working space on each side; wing-wall trench 1.2 m wide, 1.2 m deep.

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Abutment pits (2 nos., working space 0.3 m)24.6002.1001.50028.980
Wing-wall trenches (4 nos.)42.0001.2001.20011.520
Total40.500

b) Cement concrete in foundation (1:3:6)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Abutment PCC 1:3:6, 0.30 m thick24.0001.5000.3003.600
Wing-wall PCC 1:3:642.0000.9000.3002.160
Total5.760

c) Brick work (1:6 cement sand mortar)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Abutment wall, 1:6 brick23.4000.9002.50015.300
Wing walls (mean thickness 0.45, mean height 2.0)42.0000.4502.0007.200
Total22.500

d) RCC work (trough, M20)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trough bottom slab16.6002.4000.2503.960
Trough side walls26.6000.2001.2003.168
Total7.128

Reinforcement is then taken separately (about 80–100 kg per m³ of trough concrete as a check).

Answer: Excavation = 40.50 m³; PCC = 5.76 m³; brickwork = 22.50 m³; RCC = 7.13 m³ (for the assumed dimensions; substitute the dimensions of the actual drawing in the same format).

Quantities are taken in the usual order: length × breadth × height/depth, in cubic metres (m³) or square metres (m²), with deductions entered as negatives. Rates are not asked; when costing, apply the current District Rate and DUDBC rate-analysis norms of the district.

  • 2067 Asar (old course) · 14 marks

Estimate the quantities of the following items of work from the accompanying drawing. a) Earthwork in excavation b) Cement concrete c) 1st class brick work d) RCC work [Drawing not included in the scanned paper]

Similar questions: Aqueduct: excavation, concrete, brick, RCC (2065 Shrawan (old course))

Answer

No drawing is given. The method is therefore shown on an assumed one-room building with RCC flat roof, using the centre-line method.

Assumed data

  • Room 4.5 m × 3.5 m clear; walls 0.23 m (first class brick in 1:6 cement mortar); centre-line length = 2(4.5 + 3.5 + 2 × 0.23) = 16.92 m.
  • Trench 0.90 m wide, 1.00 m deep; PCC 1:3:6, 0.20 m thick; two brick footing steps (0.69 m and 0.46 m wide, 0.15 m each); plinth 0.45 m above GL; ceiling height 3.0 m.
  • One door 1.0 × 2.1 m and two windows 1.2 × 1.2 m; RCC lintels 0.23 × 0.15 m with 0.2 m bearing each side; roof slab 125 mm; floor PCC 100 mm.
  • Wall height from last footing to plinth top = 1.00 − 0.20 − 0.30 + 0.45 = 0.95 m.

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)116.9200.9001.00015.228
Total15.228

b) Cement concrete

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC bed under walls116.9200.9000.2003.046
Floor PCC 1:4:8, 100 mm (room)14.5003.5000.1001.575
Total4.621

c) First class brick work (foundation, plinth and superstructure)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)116.9200.6900.1501.751
Brick footing step 2 (0.46 m wide)116.9200.4600.1501.167
Wall up to plinth116.9200.2300.9503.697
Wall above plinth, full length116.9200.2303.00011.675
Deduct door 1.00×2.10-11.0000.2302.100-0.483
Deduct window 1.20×1.20-21.2000.2301.200-0.662
Deduct lintel bearing, 1.00 m opening-11.4000.2300.150-0.048
Deduct lintel bearing, 1.20 m opening-21.6000.2300.150-0.110
Total16.986

(Lintel bearing is deducted because it is measured under RCC.)

d) RCC work

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Roof slab, 125 mm (outer size of walls)14.9603.9600.1252.455
Lintel over door11.4000.2300.1500.048
Lintels over windows21.6000.2300.1500.110
Total2.614

Answer: Excavation = 15.23 m³; cement concrete = 4.62 m³; brickwork = 16.99 m³; RCC = 2.61 m³ (assumed dimensions; follow the same sequence for the actual drawing).

Quantities are taken in the usual order: length × breadth × height/depth, in cubic metres (m³) or square metres (m²), with deductions entered as negatives. Rates are not asked; when costing, apply the current District Rate and DUDBC rate-analysis norms of the district.

  • 2081 Baisakh · 8 marks

Work out quantity of well foundation of bridge foundation. The well is to be circular of 2 m internal diameter with 300 mm thick masonry wall in 1:6 cement sand mortar. The well is founded in strata 14.00 m thick. Water table remains at 3.80 m depth. Well curb at bottom is RCC with M25 grade concrete mix and is 400 mm deep. The well rises 60 cm above ground level. Top of well is to sealed with 0.45 m thick (1:4:8) cement concrete as well cover. Estimate quantities for the following works. a) Earthwork in excavation b) Sinking of well c) Brick masonry work in (1:6) cement sand mortar d) PCC for RCC in curb

Similar questions: Well foundation: sinking, brick, sand filling, PCC (2079 Bhadra)

Answer

Data. Internal dia = 2.0 m; masonry wall 0.30 m, so outer dia = 2.0 + 2 × 0.30 = 2.60 m. Founding depth below GL = 14.0 m (including the 0.4 m curb); water table at 3.8 m; well rises 0.6 m above GL.

  • Outer cross-section Ao=π4(2.60)2=5.309A_o=\frac{\pi}{4}(2.60)^2=5.309 m²
  • Annular area of steining =π4(2.602−22)=2.168=\frac{\pi}{4}(2.60^2-2^2)=2.168 m²

a) Earthwork in excavation (above water table)

Dry excavation from GL to 3.8 m: 5.309 × 3.8 = 20.18 m³.

b) Sinking of well (below water table)

The remaining depth 14.0 − 3.8 = 10.2 m is sunk by dredging under water: 5.309 × 10.2 = 54.15 m³. (If a single item is wanted, total = 74.33 m³.)

c) Brick masonry (1:6) in steining

Height of steining = 14.0 − 0.4 (curb) + 0.6 (above GL) = 14.20 m.

Volume = 2.168 × 14.20 = 30.78 m³.

d) PCC (M25) for RCC curb

Curb ring area is the same, depth 0.4 m: 2.168 × 0.4 = 0.867 m³ (reinforcement is measured separately in kg).

The 0.45 m well cover (1:4:8) is not asked here; it is π/4 × 2.0² × 0.45 = 1.41 m³.

Answer: Excavation 20.18 m³; sinking 54.15 m³; brickwork 30.78 m³; curb concrete 0.867 m³.

  • 2079 Bhadra · 4×2 marks

Work out quantity of well foundation for bridge. The well is to be circular of 2 m internal diameter with 300 mm thick masonry wall in 1:6 cement sand mortar. The well is founded in strata 14.00 m thick. Water table remains at 3.80 m depth. Well curb at bottom is RCC with M25 grade concrete mix and is 400 mm deep. The well rises 60 cm above ground level. Top of well is to be sealed with 0.45 m thick (1:4:8) cement concrete as well cover. Estimate quantities for the following works. a) Sinking of well. b) Brick masonry work in (1:6) cement sand mortar. c) Sand filling. d) PCC for RCC in well cover.

Similar questions: Well foundation: excavation, sinking, brick, PCC curb (2081 Baisakh)

Answer

Data. Internal dia 2.0 m; wall 0.30 m, so outer dia = 2.60 m. Depth of well below GL = 14.0 m (curb included); well rises 0.6 m above GL; curb 0.4 m; cover 0.45 m thick placed inside the top of the bore.

  • Outer area Ao=5.309A_o=5.309 m²; inner area Ai=π4×22=3.142A_i=\frac{\pi}{4}\times 2^2=3.142 m²; ring area 2.1682.168 m².

a) Sinking of well

Ao×14.0=5.309×14=A_o\times 14.0 = 5.309\times 14 = 74.33 m³ (of this, 3.8 m is above the water table: 20.18 m³ and 54.15 m³ below it, which is priced separately if required).

b) Brick masonry (1:6)

Height = 14.0 − 0.4 + 0.6 = 14.20 m; volume = 2.168 × 14.20 = 30.78 m³.

c) Sand filling

Filling goes from the top of the curb to the underside of the cover: height = 14.0 + 0.6 − 0.4 − 0.45 = 13.75 m; volume = 3.142 × 13.75 = 43.20 m³.

d) PCC (1:4:8) in well cover

Volume = Ai×0.45=3.142×0.45=A_i\times 0.45=3.142\times 0.45= 1.414 m³.

Answer: Sinking 74.33 m³; brickwork 30.78 m³; sand filling 43.20 m³; well cover concrete 1.414 m³.

  • 2075 Chaitra · 7 marks

Workout the quantity of well foundation of a bridge. The well is to be circular of 5 m internal diameter with 800 mm wall in 1:6 cement and sand mortar. The well is to be founded on strata 15 m below bed of river which is dry during winter. Bottom of the well is to be plugged with 1.5 m thick cement concrete 1:4:8 and the top to be sealed with 1 m thick cement concrete 1:2:4 and central portion is to be sand filled.

Similar questions: Well foundation, 4.5 m internal diameter (2071 Chaitra)

Answer

Data. Internal dia 5.0 m, wall 0.80 m, so outer dia = 5.0 + 2 × 0.8 = 6.60 m. Founding depth = 15.0 m below river bed (dry river, so no water-table complication). Assumptions: the top of the well is at river-bed level and the steining includes the curb (a separate RCC curb would be deducted from the brickwork).

  • Ao=π4(6.60)2=34.212A_o=\frac{\pi}{4}(6.60)^2=34.212 m²; Ai=π4(5)2=19.635A_i=\frac{\pi}{4}(5)^2=19.635 m²; ring area =14.577=14.577 m².
ItemWorkingQuantity
Excavation / sinking34.212 × 15.0513.18 m³
Brick masonry 1:6 in steining14.577 × 15.0218.65 m³
Bottom plug, CC 1:4:819.635 × 1.529.45 m³
Top seal, CC 1:2:419.635 × 1.019.63 m³
Sand filling (15.0 − 1.5 − 1.0 = 12.50 m)19.635 × 12.50245.44 m³

Answer: Excavation 513.18 m³; brickwork 218.65 m³; bottom plug 29.45 m³ (1:4:8); top seal 19.63 m³ (1:2:4); sand filling 245.44 m³.

  • 2071 Chaitra · 9 marks

Workout the quantity of well foundation of a bridge. The well is to be circular of 4.5 meter internal diameter with 800 mm wall in 1:6 cement and sand mortar. The well to be founded on strata 15 meter below bed of river which is dry during the hot weather. Bottom of the well to be plugged with 1.0 meter thick cement concrete 1:4:8 and the top to be sealed with 0.75 meter thick cement concrete 1:4:8 and central portion is to be sand filled.

Similar questions: Well foundation, 5 m internal diameter (2075 Chaitra)

Answer

Data. Internal dia 4.5 m, wall 0.80 m, so outer dia = 4.5 + 2 × 0.8 = 6.10 m. Founding depth 15.0 m below river bed (dry). Assumptions: top of the well at bed level and the steining includes the curb.

  • Ao=π4(6.10)2=29.225A_o=\frac{\pi}{4}(6.10)^2=29.225 m²; Ai=π4(4.5)2=15.904A_i=\frac{\pi}{4}(4.5)^2=15.904 m²; ring area =13.320=13.320 m².
ItemWorkingQuantity
Excavation / sinking29.225 × 15.0438.37 m³
Brick masonry 1:6 in steining13.320 × 15.0199.81 m³
Bottom plug, CC 1:4:8 (1.0 m)15.904 × 1.015.90 m³
Top seal, CC 1:4:8 (0.75 m)15.904 × 0.7511.93 m³
Sand filling (15.0 − 1.0 − 0.75 = 13.25 m)15.904 × 13.25210.73 m³

Total 1:4:8 concrete = 27.83 m³.

Answer: Excavation 438.37 m³; brickwork 199.81 m³; CC 1:4:8 = 27.83 m³ (bottom 15.90 + top 11.93); sand filling 210.73 m³.

  • 2076 Chaitra · 8 marks

Estimate the quantities of a T-beam decking of a single span bridge which has 6 m clear span and bearing on either side is 45 cm, from the accompanying bridge drawing. (Reinforcement: beam 2½%, slab and posts 1%.) [Figure: RCC T-beam decking cross-section. Overall width 7.7 m, 7 m roadway, 20×20 cm kerb on each side, 10 cm wearing coat of C.C., 20 cm slab, three ribs each 35 cm wide with 225 cm clear between ribs, rib depth below slab 75 cm (107.5 cm projections at the edges), 15×15 cm fillets, 15×15 cm RCC railing posts 120 cm high at 136 cm c/c, 40 mm dia G.I. pipe 4 nos., railing height 120 cm.]

Answer

Assumptions from the drawing

  • Length of decking =6.00+2×0.45=6.90= 6.00 + 2 \times 0.45 = 6.90 m (clear span plus bearing at both ends).
  • Overhang of slab beyond outer ribs =(7.70−3×0.35−2×2.25)/2=1.075= (7.70 - 3 \times 0.35 - 2 \times 2.25)/2 = 1.075 m (matches the 107.5 cm in the figure).
  • Fillets are taken as triangles of 15 × 15 cm at both sides of each rib (6 in total). The railing posts are at 1.36 m c/c: with 6.90 m length this gives 6 posts per side, 12 in all.
  • The 20 cm slab is taken from the figure; the kerb is 20 × 20 cm above the slab, and the wearing coat (10 cm) is laid between the kerbs over the 7.0 m roadway.
  • Reinforcement as given: beams (ribs and fillets) 2.5%, slab and kerbs 1%, posts 1% of the volume of concrete; density of steel 7850 kg/m³.
  • The railing has 4 lines of 40 mm G.I. pipe on each side, running the full length of the decking (assumption; the figure shows "4 nos").

Quantities

MemberWorkingVolume (m³)
Slab7.70×6.90×0.207.70 \times 6.90 \times 0.2010.626
Ribs (3)3×0.35×0.75×6.903 \times 0.35 \times 0.75 \times 6.905.434
Fillets (6, 15 × 15 cm triangular)6×12×0.15×0.15×6.906 \times \tfrac12 \times 0.15 \times 0.15 \times 6.900.466
Kerbs (2)2×0.20×0.20×6.902 \times 0.20 \times 0.20 \times 6.900.552
Railing posts (12 nos, 15 × 15 × 120 cm)12×0.15×0.15×1.2012 \times 0.15 \times 0.15 \times 1.200.324
Total RCC (1:2:4)17.402
ItemWorkingQuantity
Wearing coat C.C. (1:2:4)7.00×6.90×0.107.00 \times 6.90 \times 0.104.830 m³
Steel in beams(5.434+0.466)×0.025×7850(5.434 + 0.466) \times 0.025 \times 78501,157.8 kg
Steel in slab and kerbs(10.626+0.552)×0.01×7850(10.626 + 0.552) \times 0.01 \times 7850877.5 kg
Steel in posts0.324×0.01×78500.324 \times 0.01 \times 785025.4 kg
Total steel2,060.7 kg
G.I. pipe 40 mm dia.4×2×6.904 \times 2 \times 6.9055.2 m

Answer: RCC (1:2:4) = 17.402 m³; wearing coat = 4.830 m³; reinforcement = 2,060.7 kg; 40 mm G.I. pipe = 55.2 m.

  • 2080 Baisakh · 4+3 marks

From the given figure of RCC T-beam decking of one span of 6 m, of which the section is given, calculate the following items of works: a) PCC for RCC work b) Reinforcement quantities for all RCC members. [Figure: RCC T-beam decking cross-section. Overall width 7.7 m, 7 m roadway, 20×20 cm kerb on each side, 10 cm wearing coat of C.C., 20 cm slab, three ribs each 35 cm wide with 225 cm clear between ribs, rib depth below slab 75 cm (107.5 cm projections at the edges), 15×15 cm fillets, 15×15 cm RCC railing posts 120 cm high at 136 cm c/c, 40 mm dia G.I. pipe 4 nos., railing height 120 cm.]

Answer

Assumptions from the figure

  • Length of decking =6.00+2×0.45=6.90= 6.00 + 2 \times 0.45 = 6.90 m (clear span plus bearing at both ends).
  • Overhang of slab beyond outer ribs =(7.70−3×0.35−2×2.25)/2=1.075= (7.70 - 3 \times 0.35 - 2 \times 2.25)/2 = 1.075 m (matches the 107.5 cm in the figure).
  • Fillets are taken as triangles of 15 × 15 cm at both sides of each rib (6 in total). The railing posts are at 1.36 m c/c: with 6.90 m length this gives 6 posts per side, 12 in all.
  • The 20 cm slab is taken from the figure; the kerb is 20 × 20 cm above the slab, and the wearing coat (10 cm) is laid between the kerbs over the 7.0 m roadway.
  • Percentage of steel is not stated; the usual values for T-beam decking are taken: beams 2.5%, slab and kerbs 1%, posts 1%. Density of steel 7850 kg/m³.

(a) Concrete for the RCC work (1:2:4)

MemberWorkingVolume (m³)
Slab7.70×6.90×0.207.70 \times 6.90 \times 0.2010.626
Ribs (3)3×0.35×0.75×6.903 \times 0.35 \times 0.75 \times 6.905.434
Fillets (6, 15 × 15 cm triangular)6×12×0.15×0.15×6.906 \times \tfrac12 \times 0.15 \times 0.15 \times 6.900.466
Kerbs (2)2×0.20×0.20×6.902 \times 0.20 \times 0.20 \times 6.900.552
Railing posts (12 nos, 15 × 15 × 120 cm)12×0.15×0.15×1.2012 \times 0.15 \times 0.15 \times 1.200.324
Total RCC (1:2:4)17.402

(b) Reinforcement

MemberConcrete (m³)% steelSteel (kg)
Ribs and fillets5.8992.51,157.8
Slab and kerbs11.1781.0877.5
Posts0.3241.025.4
Total2,060.7

Answer: concrete in RCC members = 17.402 m³; reinforcement = 2,060.7 kg (2.061 tonne).

  • 2082 Bhadra

A road is to be constructed in hill areas with formation width of 8 m. Side slope in banking is 2:1 and side slope in cutting is 1.5:1. Calculate the quantities of earthwork from the following data:
ChainageDepth of cutting at centre of roadHeight of filling at centre of roadCross slope of ground
1300.7 m-12:1
1600.5 m-15:1
1900.4 m-12:1
220-0.7 m10:1
250-0.6 m15:1
280-0.8 m12:1

Answer

Given data and assumptions

  • Formation width B=8B = 8 m in both cutting and filling; side slope in cutting 1.5:11.5:1, in filling 2:12:1 (H:V).
  • Chainages are 30 m apart; cross slopes are taken as n:1n:1 (H:V), e.g. 12:1 means 12 horizontal to 1 vertical.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+130cut 0.706.6050.000
0+160cut 0.504.5270.000
0+190cut 0.403.6640.000
0+220fill 0.700.0007.188
0+250fill 0.600.0005.765
0+280fill 0.800.0008.128

Working for one section:

Take chainage 0+220: centre filling height h=0.70h = 0.70 m, n=10n = 10, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =−0.300= -0.300 m, at the downhill edge =−1.100= -1.100 m.
  • Toe of the side slope on the uphill side at x=4.500x = 4.500 m from the centre line (ground below formation by 0.250 m); downhill toe at x=6.750x = 6.750 m (ground below formation by 1.375 m).
  • Area from the co-ordinates of the polygon: cutting =0.000= 0.000 m², filling =7.188= 7.188 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+130 – 0+16030.0166.980.00
0+160 – 0+19030.0122.860.00
0+190 – 0+22030.054.96107.81
0+220 – 0+25030.00.00194.28
0+250 – 0+28030.00.00208.39
Total150.0344.80510.49

Answer: Earthwork in cutting = 344.80 m³; earthwork in filling = 510.49 m³.

  • 2082 Baisakh · 6 marks

Calculate earthwork for the following section of road from the given data. i) Formation width = 8 m, ii) Side slope in filling and cutting = 2:1 and 1½:1 respectively.
Distance (m)0100200300400500600
RL of GL99.510099.8101.6102.3101.1103
RL of FL1001:200 (upward)1:400 (downward)

Answer

Given data and assumptions

  • Formation width B=8B = 8 m; side slope in filling 2:12:1, in cutting 1.5:11.5:1 (H:V). Ground is taken as level across the road (no cross slope given).
  • Formation level at 0 m is 100.00 m. The gradient is read as 1 in 200 upward from 0 to 300 m and 1 in 400 downward from 300 m to 600 m (the printed table shows only the two gradients).

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+00099.500100.000filling 0.500
0+100100.000100.500filling 0.500
0+20099.800101.000filling 1.200
0+300101.600101.500cutting 0.100
0+400102.300101.250cutting 1.050
0+500101.100101.000cutting 0.100
0+600103.000100.750cutting 2.250

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000fill 0.500.0004.500
0+100fill 0.500.0004.500
0+200fill 1.200.00012.480
0+300cut 0.100.8150.000
0+400cut 1.0510.0540.000
0+500cut 0.100.8150.000
0+600cut 2.2525.5940.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+100100.00.00450.00
0+100 – 0+200100.00.00849.00
0+200 – 0+300100.03.13576.00
0+300 – 0+400100.0543.440.00
0+400 – 0+500100.0543.440.00
0+500 – 0+600100.01,320.440.00
Total600.02,410.451,875.00

Answer: Earthwork in cutting = 2,410.45 m³; earthwork in filling = 1,875.00 m³.

  • 2081 Baisakh · 8 marks

Estimate for the construction of highway for one km length. Cut slope be 1.5:1 and fill slope be 2:1, mid depth of cutting be 0.35 m for two lane road and ground slope be 9:1. The pavement thickness be wearing coat, base course and sub-base over the subgrade 50 mm, 250 mm and 350 mm respectively.

Answer

Given data and assumptions

  • Two-lane road: carriageway 7.07.0 m with 1.51.5 m shoulders on both sides (Nepal Road Standard 2070), so formation width B=10.0B = 10.0 m. The earthwork is taken to subgrade (formation) level.
  • Cut slope 1.5:11.5:1, fill slope 2:12:1, ground cross slope 9:19:1, centre depth of cutting h=0.35h = 0.35 m at every section, so the section is uniform along the 1 km.
  • Wearing coat and base course 7.0 m wide; sub-base spread over the full formation width of 10 m.

Earthwork (side-hill section)

At the up-hill edge the ground is 0.35+5/9=0.9060.35 + 5/9 = 0.906 m above formation (cutting), and at the down-hill edge it is 0.35−5/9=−0.2060.35 - 5/9 = -0.206 m (so that side falls below formation and needs filling). The ground cuts the formation level at 9×0.35=3.159 \times 0.35 = 3.15 m from the centre line.

  • Up-hill toe: xu=6.630x_u = 6.630 m from the centre line, ground 1.0871.087 m above formation
  • Down-hill toe (filling slope): xd=5.529x_d = 5.529 m, ground 0.2640.264 m below formation
  • Area of cutting =4.428= 4.428 m²; area of filling =0.244= 0.244 m² (from the co-ordinates of the section).
Vcut=4.428×1000=4,428.2 m3Vfill=0.244×1000=244.5 m3\begin{aligned} V_{cut} &= 4.428 \times 1000 = 4,428.2\ \text{m}^3\\ V_{fill} &= 0.244 \times 1000 = 244.5\ \text{m}^3 \end{aligned}

Pavement quantities for 1 km

LayerWorkingVolume (m³)
Wearing coat 50 mm7.0×0.05×10007.0 \times 0.05 \times 1000350.0
Base course 250 mm7.0×0.25×10007.0 \times 0.25 \times 10001,750.0
Sub-base 350 mm10.0×0.35×100010.0 \times 0.35 \times 10003,500.0

Answer: cutting = 4,428.2 m³, filling = 244.5 m³ per km; wearing coat 350 m³, base 1,750 m³, sub-base 3,500 m³. The cost follows by multiplying each quantity by its rate (District Rate) and adding overhead, profit and VAT.

  • 2080 Bhadra · 2 marks

Draw a balanced canal section.

Answer

A balanced section is a canal section partly in cutting and partly in banking in which the earth excavated from the bed is exactly enough to build the banks, so there is no surplus spoil and no earth is borrowed. The depth of cutting at which this happens is the balancing depth.

 bank top ______                    ______
         /      \                  /      \
        /  bank  \  F.S.L ~~~~~~~/  bank  \
 G.L ===/          \            /          \===
                    \          /
                     \________/
                      bed width b

Condition: area of cutting below ground = area of the two banks above ground.

(b+s d) d=2 (t+s hb) hb,hb=D−d(b + s\,d)\,d = 2\,(t + s\,h_b)\,h_b,\qquad h_b = D - d

where dd is the depth of cutting, DD = full supply depth + free board, tt = top width of one bank and ss the side slope.

Example (assumed b=5b = 5 m, s=1.5s = 1.5, t=2t = 2 m, D=1.6D = 1.6 m): solving gives d=0.810d = 0.810 m, cutting area =5.033= 5.033 m² and bank area =5.033= 5.033 m² (equal).

  • 2079 Bhadra · 2 marks

Briefly explain the method of quantity estimate for road construction.

Answer

Quantities of road earthwork are found from the longitudinal section and cross-sections.

  1. Take cross-sections at regular intervals (e.g. 10–30 m, closer on curves) and at points where the ground changes.
  2. Find the depth of cutting or height of filling at the centre line from the ground level and formation level; the formation level follows the design gradients.
  3. For each section calculate the area of cutting and filling from the formation width and side slopes (A=(B+sh)hA = (B + s h)h for level ground; side-hill formulae when the ground has a cross slope).
  4. Find the volume between consecutive sections by the mean sectional area method (V=A1+A22×LV = \tfrac{A_1 + A_2}{2} \times L), or the prismoidal formula for greater accuracy.
  5. Add the quantities of pavement layers (area × thickness), drains, culverts and protection works, and put everything in a bill of quantities.
  • 2079 Bhadra · 10 marks

Workout the quantities of earthwork in embankment and cutting based on the data provided below. Formation width of road: Dedicated four lane width based on NRS-1070. Side slope in embankment and excavation is 1:2 and 1:1.5 respectively.
Chainage0+0000+0300+0600+0900+1200+1500+180
RL of GL (m)152.00152.35152.60152.80153.00152.65152.20
RL of FL (m)151.80 / 152.45 (as printed)153
Cross slopePlainPlain1:121:101:111:111:13
Gradient of road1:200 rising (up to 0+090)1:300 rising (0+090 onwards)

Answer

Given data and assumptions

  • Formation width of a dedicated four-lane road (NRS 2070): four lanes of 3.5 m, a 1.5 m median and two shoulders of 2.5 m give about 21.0 m; B=21B = 21 m is used (check with the standard in use).
  • Side slope in embankment 2:12:1 and in excavation 1.5:11.5:1 (the question writes 1:2 and 1:1.5, i.e. 1 vertical to 2 and 1.5 horizontal). Cross slopes: "plain" is taken as level ground.
  • The printed formation levels are unclear. Formation level at 0+000 is taken as 152.00 m, rising 1 in 200 up to 0+090 (152.45 m, as printed) and then 1 in 300 to 0+180 (152.75 m).

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+000152.000152.0000.000
0+030152.350152.150cutting 0.200
0+060152.600152.300cutting 0.300
0+090152.800152.450cutting 0.350
0+120153.000152.550cutting 0.450
0+150152.650152.6500.000
0+180152.200152.750filling 0.550

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+0000.000.0000.000
0+030cut 0.204.2600.000
0+060cut 0.309.4672.381
0+090cut 0.3511.5293.062
0+120cut 0.4512.5631.711
0+1500.005.8036.125
0+180fill 0.550.48814.160

Working for one section:

Take chainage 0+060: centre cutting depth h=0.30h = 0.30 m, n=12n = 12, B=21.0B = 21.0 m.

  • Ground height above formation at the uphill edge =1.175= 1.175 m, at the downhill edge =−0.575= -0.575 m.
  • Toe of the side slope on the uphill side at x=12.514x = 12.514 m from the centre line (ground above formation by 1.343 m); downhill toe at x=11.880x = 11.880 m (ground below formation by 0.690 m).
  • Area from the co-ordinates of the polygon: cutting =9.467= 9.467 m², filling =2.381= 2.381 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.063.900.00
0+030 – 0+06030.0205.9135.71
0+060 – 0+09030.0314.9581.64
0+090 – 0+12030.0361.3971.61
0+120 – 0+15030.0275.49117.54
0+150 – 0+18030.094.36304.28
Total180.01,315.99610.78

Answer: Earthwork in cutting = 1,315.99 m³; earthwork in filling = 610.78 m³.

  • 2076 Chaitra · 10 marks

Estimate quantities of earthwork of a portion of road from the following data: (i) Formation width of road is 10 m. (ii) Side slope in cutting and filling (1:1) and (2:1) (H:V) respectively.
Distance0306090120150180
R.L. of ground102.60103.00102.65102.20101.50101.20100.65
R.L. of formation101102.15
GradientRising gradient 1 in 200Falling gradient 1 in 120

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in filling 2:12:1. Ground is level across the road.
  • Formation level at 0 m is 101.00 m, rising 1 in 200 up to 120 m (101.60 m) and falling 1 in 120 from 120 m to 180 m (101.10 m). The printed 102.15 at 120 m does not fit a 1 in 200 gradient, so the stated gradients are used.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+000102.600101.000cutting 1.600
0+030103.000101.150cutting 1.850
0+060102.650101.300cutting 1.350
0+090102.200101.450cutting 0.750
0+120101.500101.600filling 0.100
0+150101.200101.350filling 0.150
0+180100.650101.100filling 0.450

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 1.6018.5600.000
0+030cut 1.8521.9220.000
0+060cut 1.3515.3230.000
0+090cut 0.758.0620.000
0+120fill 0.100.0001.020
0+150fill 0.150.0001.545
0+180fill 0.450.0004.905

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0607.240.00
0+030 – 0+06030.0558.680.00
0+060 – 0+09030.0350.780.00
0+090 – 0+12030.0106.711.80
0+120 – 0+15030.00.0038.47
0+150 – 0+18030.00.0096.75
Total180.01,623.40137.02

Answer: Earthwork in cutting = 1,623.40 m³; earthwork in filling = 137.02 m³.

  • 2076 Asoj · 9 marks

A road is to be constructed in hilly area with formation width of 10 m, side slopes in banking and cutting (2:1) and (1:1). The height of banking or depth of cutting at the centre line of the road are given below. The cross slopes of ground are also given at different sections. Calculate the quantities of earthwork.
DistanceCuttingFillingCross slope of ground
00.50--12:1
500.60--10:1
100--0.4015:1
150--0.6012:1

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in banking 2:12:1 (H:V).
  • Sections 50 m apart; cutting at 0 and 50 m, filling at 100 and 150 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.505.4620.000
0+050cut 0.606.6770.000
0+100fill 0.400.0004.624
0+150fill 0.600.0007.269

Working for one section:

Take chainage 0+000: centre cutting depth h=0.50h = 0.50 m, n=12n = 12, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.917= 0.917 m, at the downhill edge =0.083= 0.083 m.
  • Toe of the side slope on the uphill side at x=6.000x = 6.000 m from the centre line (ground above formation by 1.000 m); downhill toe at x=5.077x = 5.077 m (ground above formation by 0.077 m).
  • Area from the co-ordinates of the polygon: cutting =5.462= 5.462 m², filling =0.000= 0.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+05050.0303.460.00
0+050 – 0+10050.0166.92115.61
0+100 – 0+15050.00.00297.34
Total150.0470.38412.95

Answer: Earthwork in cutting = 470.38 m³; earthwork in filling = 412.95 m³.

  • 2075 Chaitra · 10 marks

Estimate the quantity of earthwork of a hill road when the formation width in cutting is 4 m and side slope is 2:1. The formation width in banking is 6 m and side slope 3:1. The ground and formation level at the centre of road and also the transverse slopes of ground surface are as below:
Chainage (m)050100150200250
RL of GL (m)1150.001150.601151.501150.801151.501152.00
RL of FL (m)1149.201150.001150.801151.601151.501153.20
Cross slope (m)1:101:11:141:1201:10

Answer

Given data and assumptions

  • Formation width: cutting 44 m with side slope 2:12:1; banking 66 m with side slope 3:13:1 (H:V). Sections are 50 m apart.
  • Centre height = GL − FL: 0.80, 0.60, 0.70 (cutting), −0.80 (filling), 0.00, −1.20 (filling).
  • Cross slope printed as 1:1 at 50 m is steeper than the 2:1 cut slope (the cut face would never meet the ground), so it is taken as 1:10; at 200 m the cross slope is 0 (level ground) and the centre height is zero.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.804.7500.000
0+050cut 0.603.3330.000
0+100cut 0.703.9000.000
0+150fill 0.800.0007.368
0+2000.000.0000.000
0+250fill 1.200.00012.956

Working for one section:

Take chainage 0+050: centre cutting depth h=0.60h = 0.60 m, n=10n = 10, B=4.0B = 4.0 m.

  • Ground height above formation at the uphill edge =0.800= 0.800 m, at the downhill edge =0.400= 0.400 m.
  • Toe of the side slope on the uphill side at x=4.000x = 4.000 m from the centre line (ground above formation by 1.000 m); downhill toe at x=2.667x = 2.667 m (ground above formation by 0.333 m).
  • Area from the co-ordinates of the polygon: cutting =3.333= 3.333 m², filling =0.000= 0.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+05050.0202.080.00
0+050 – 0+10050.0180.840.00
0+100 – 0+15050.097.51184.20
0+150 – 0+20050.00.00184.20
0+200 – 0+25050.00.00323.90
Total250.0480.44692.30

Answer: Earthwork in cutting = 480.44 m³; earthwork in filling = 692.30 m³.

  • 2075 Asoj · 12 marks

Find the quantity of earth work of a hill road from the following data. Formation width is 10 m, side slope in filling and cutting 2:1 and 1½:1 respectively.
Chainage (m)0100200300400500600
RL of Ground (m)1115.201116.101116.851118.001118.251118.101117.75
Formation: RL at chainage 0 is 1116.5 m, upward gradient 1 in 200 up to chainage 300 m. Downward gradient 1 in 400 from chainage 300 m onwards.

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in filling 2:12:1, in cutting 1.5:11.5:1. No cross slope is given, so the ground is level across the road.
  • Formation level 1116.50 m at 0, rising 1 in 200 up to 300 m (1118.00 m) and then falling 1 in 400.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+0001,115.2001,116.500filling 1.300
0+1001,116.1001,117.000filling 0.900
0+2001,116.8501,117.500filling 0.650
0+3001,118.0001,118.0000.000
0+4001,118.2501,117.750cutting 0.500
0+5001,118.1001,117.500cutting 0.600
0+6001,117.7501,117.250cutting 0.500

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000fill 1.300.00016.380
0+100fill 0.900.00010.620
0+200fill 0.650.0007.345
0+3000.000.0000.000
0+400cut 0.505.3750.000
0+500cut 0.606.5400.000
0+600cut 0.505.3750.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+100100.00.001,350.00
0+100 – 0+200100.00.00898.25
0+200 – 0+300100.00.00367.25
0+300 – 0+400100.0268.750.00
0+400 – 0+500100.0595.750.00
0+500 – 0+600100.0595.750.00
Total600.01,460.252,615.50

Answer: Earthwork in cutting = 1,460.25 m³; earthwork in filling = 2,615.50 m³.

  • 2074 Chaitra · 10 marks

Calculate the quantity of earthwork for a portion of hill road from following data: Formation width = 10 m in banking and 8 m in cutting, side slope in cutting = 1:1, side slope in filling = 2:1.
ChainageCut depthFill heightTransverse slope
0+0600.5-10:1
0+0900.6-15:1
0+120-0.712:1

Answer

Given data and assumptions

  • Formation width: cutting 88 m, banking 1010 m; side slope in cutting 1:11:1, in filling 2:12:1.
  • Sections 30 m apart; cutting at 0+060 and 0+090, filling at 0+120.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+060cut 0.504.4550.000
0+090cut 0.605.2540.000
0+120fill 0.700.0008.565

Working for one section:

Take chainage 0+060: centre cutting depth h=0.50h = 0.50 m, n=10n = 10, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =0.900= 0.900 m, at the downhill edge =0.100= 0.100 m.
  • Toe of the side slope on the uphill side at x=5.000x = 5.000 m from the centre line (ground above formation by 1.000 m); downhill toe at x=4.091x = 4.091 m (ground above formation by 0.091 m).
  • Area from the co-ordinates of the polygon: cutting =4.455= 4.455 m², filling =0.000= 0.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+060 – 0+09030.0145.640.00
0+090 – 0+12030.078.82128.48
Total60.0224.45128.48

Answer: Earthwork in cutting = 224.45 m³; earthwork in filling = 128.48 m³.

  • 2074 Asoj · 10 marks

Calculate the quantities of earthwork of a hill road in side long ground from 0 m to 400 m partly in cutting and partly in filling with the following data: width of road = 10 m, side slope in cutting and filling = (1:1) and (2:1). The road has a downward gradient of 1 in 200. The cross slope of ground = 1 in 5. Formation level at 0 m = 1203.50 m.
Ground level1202.501201.971202.351199.661200.50
Distance0100200300400

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in filling 2:12:1; cross slope of ground 11 in 55 (n=5n = 5) throughout.
  • Formation level at 0 m is 1203.50 m and falls 1 in 200, so it is 1203.50, 1203.00, 1202.50, 1202.00, 1201.50 m at 0, 100, 200, 300, 400 m.
  • Ground levels are at the centre line.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+0001,202.5001,203.500filling 1.000
0+1001,201.9701,203.000filling 1.030
0+2001,202.3501,202.500filling 0.150
0+3001,199.6601,202.000filling 2.340
0+4001,200.5001,201.500filling 1.000

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000fill 1.000.00016.667
0+100fill 1.030.00017.169
0+200fill 0.152.2585.510
0+300fill 2.340.00043.275
0+400fill 1.000.00016.667

Working for one section:

Take chainage 0+000: centre filling height h=1.00h = 1.00 m, n=5n = 5, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.000= 0.000 m, at the downhill edge =−2.000= -2.000 m.
  • Toe of the side slope on the uphill side at x=5.000x = 5.000 m from the centre line (ground above formation by 0.000 m); downhill toe at x=11.667x = 11.667 m (ground below formation by 3.333 m).
  • Area from the co-ordinates of the polygon: cutting =0.000= 0.000 m², filling =16.667= 16.667 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+100100.00.001,691.77
0+100 – 0+200100.0112.891,133.96
0+200 – 0+300100.0112.892,439.28
0+300 – 0+400100.00.002,997.10
Total400.0225.788,262.11

Answer: Earthwork in cutting = 225.78 m³; earthwork in filling = 8,262.11 m³.

  • 2073 Shrawan · 16 marks

Prepare an estimate of earthwork for a road portion from the following data: Formation width = 8 m in cutting and 10 m in banking. Side slope in cutting = 1:1, side slope in banking = 2:1 (H:V).
RD0306090120
RLS of ground507.0507.95507.30506.90506.50
Formation level507.0 and upward gradient @ 1 in 150
Cross slope of ground1:101:121:101:121:10

Answer

Given data and assumptions

  • Formation width 88 m in cutting and 1010 m in banking; side slope in cutting 1:11:1, in banking 2:12:1 (H:V).
  • Formation level 507.00 m at RD 0, rising 1 in 150: 507.00, 507.20, 507.40, 507.60, 507.80 m. The section at RD 0 has zero centre height and is taken with the cutting width of 8 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+000507.000507.0000.000
0+030507.950507.200cutting 0.750
0+060507.300507.400filling 0.100
0+090506.900507.600filling 0.700
0+120506.500507.800filling 1.300

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+0000.000.8891.000
0+030cut 0.756.7200.000
0+060fill 0.100.8892.250
0+090fill 0.700.0008.565
0+120fill 1.300.00017.583

Working for one section:

Take chainage 0+000: centre cutting depth h=0.00h = 0.00 m, n=10n = 10, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =0.400= 0.400 m, at the downhill edge =−0.400= -0.400 m.
  • Toe of the side slope on the uphill side at x=4.444x = 4.444 m from the centre line (ground above formation by 0.444 m); downhill toe at x=5.000x = 5.000 m (ground below formation by 0.500 m).
  • Area from the co-ordinates of the polygon: cutting =0.889= 0.889 m², filling =1.000= 1.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0114.1415.00
0+030 – 0+06030.0114.1433.75
0+060 – 0+09030.013.33162.23
0+090 – 0+12030.00.00392.23
Total120.0241.61603.20

Answer: Earthwork in cutting = 241.61 m³; earthwork in filling = 603.20 m³.

  • 2071 Chaitra · 12 marks

Calculate the quantities of earthwork of a portion of hill road from the following data: Formation width = 8 m, side slope in cutting and filling = (1:1) and (2:1).
DistanceDepth of cutDepth of fillCross slope of ground
0 m0.30-10:1
30 m0.20-15:1
60 m-0.5012:1
90 m-0.708:1

Answer

Given data and assumptions

  • Formation width B=8B = 8 m; side slope in cutting 1:11:1, in filling 2:12:1.
  • Sections 30 m apart. Some of the cutting sections (small centre depth, steep cross slope) are partly in filling on the low side, and are calculated that way.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.302.7220.063
0+030cut 0.201.7500.038
0+060fill 0.500.0004.857
0+090fill 0.700.0007.552

Working for one section:

Take chainage 0+000: centre cutting depth h=0.30h = 0.30 m, n=10n = 10, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =0.700= 0.700 m, at the downhill edge =−0.100= -0.100 m.
  • Toe of the side slope on the uphill side at x=4.778x = 4.778 m from the centre line (ground above formation by 0.778 m); downhill toe at x=4.250x = 4.250 m (ground below formation by 0.125 m).
  • Area from the co-ordinates of the polygon: cutting =2.722= 2.722 m², filling =0.063= 0.063 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.067.081.51
0+030 – 0+06030.026.2573.43
0+060 – 0+09030.00.00186.14
Total90.093.33261.09

Answer: Earthwork in cutting = 93.33 m³; earthwork in filling = 261.09 m³.

  • 2070 Chaitra · 10 marks

Estimate the quantities of earthwork for a portion of a hilly road from following data: Formation width = 10 m. Side slopes in cutting = 1:1 and in banking = 2:1 (H:V), length of chain = 30 m.
Chainage12131415
Depth of cut0.40.2--
Ht. of banking--0.30.5
Transverse slope of ground1:101:121:101:8

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in banking 2:12:1. The length of one chain is 30 m, so the sections are 30 m apart (chainage numbers 12, 13, 14, 15 are chain numbers).

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
12cut 0.404.5000.062
13cut 0.202.4890.338
14fill 0.300.2224.000
15fill 0.500.0716.750

Working for one section:

Take chainage 12: centre cutting depth h=0.40h = 0.40 m, n=10n = 10, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.900= 0.900 m, at the downhill edge =−0.100= -0.100 m.
  • Toe of the side slope on the uphill side at x=6.000x = 6.000 m from the centre line (ground above formation by 1.000 m); downhill toe at x=5.250x = 5.250 m (ground below formation by 0.125 m).
  • Area from the co-ordinates of the polygon: cutting =4.500= 4.500 m², filling =0.062= 0.062 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
12 – 1330.0104.846.01
13 – 1430.040.6765.07
14 – 1530.04.40161.25
Total90.0149.91232.33

Answer: Earthwork in cutting = 149.91 m³; earthwork in filling = 232.33 m³.

  • 2068 Baisakh (old course) · 10 marks

Work out the quantity of earth work in cutting and filling of a portion of a hill road as per data given below: Cross slope = 1 in 5, formation width = 8 m, side slope in cutting = 1:1, side slope in filling = 2:1.
R.L. of formation699.20702.20704.20
R.L. of ground698.80700.00706.20
Distance (m)03060

Answer

Given data and assumptions

  • Formation width B=8B = 8 m; side slope in cutting 1:11:1, in filling 2:12:1; ground cross slope 11 in 55.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+000698.800699.200filling 0.400
0+030700.000702.200filling 2.200
0+060706.200704.200cutting 2.000

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000fill 0.400.5006.000
0+030fill 2.200.00034.000
0+060cut 2.0021.5000.000

Working for one section:

Take chainage 0+000: centre filling height h=0.40h = 0.40 m, n=5n = 5, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =0.400= 0.400 m, at the downhill edge =−1.200= -1.200 m.
  • Toe of the side slope on the uphill side at x=4.500x = 4.500 m from the centre line (ground above formation by 0.500 m); downhill toe at x=8.000x = 8.000 m (ground below formation by 2.000 m).
  • Area from the co-ordinates of the polygon: cutting =0.500= 0.500 m², filling =6.000= 6.000 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.07.50600.00
0+030 – 0+06030.0322.50510.00
Total60.0330.001,110.00

Answer: Earthwork in cutting = 330.00 m³; earthwork in filling = 1,110.00 m³.

  • 2067 Poush (old course) · 10 marks

Calculate the quantity of earthwork in cutting and filling in a portion of a hill road from km 8.50 to km 9.00 having cross slope (transverse slope) of ground 1 in 5 with the following data. Formation width of road = 8 m. Side slope in cutting = (1:1). Side slope in filling = (2:1). Depth of cut at centre line at km 8.50 = 40 cm. Depth of cut at centre line at km 9.00 = 80 cm.

Answer

Given data and assumptions

  • Formation width B=8B = 8 m; side slope in cutting 1:11:1, in filling 2:12:1; cross slope of ground 11 in 55 (n=5n = 5).
  • Centre depth of cutting: 0.40 m at km 8.50 and 0.80 m at km 9.00; the length is 500 m. With only two sections, the mean-area method is used.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
km 8.50cut 0.404.5000.667
km 9.00cut 0.808.0000.000

Working for one section:

Take chainage km 8.50: centre cutting depth h=0.40h = 0.40 m, n=5n = 5, B=8.0B = 8.0 m.

  • Ground height above formation at the uphill edge =1.200= 1.200 m, at the downhill edge =−0.400= -0.400 m.
  • Toe of the side slope on the uphill side at x=5.500x = 5.500 m from the centre line (ground above formation by 1.500 m); downhill toe at x=5.333x = 5.333 m (ground below formation by 0.667 m).
  • Area from the co-ordinates of the polygon: cutting =4.500= 4.500 m², filling =0.667= 0.667 m².

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
km 8.50 – km 9.00500.03,125.00166.67
Total500.03,125.00166.67

Answer: Earthwork in cutting = 3,125.00 m³; earthwork in filling = 166.67 m³.

  • 2066 Bhadra (old course) · 5 marks

Estimate the quantity of earth work for a portion of road, when formation width is 10 m. Side slope in cutting and filling are 1:1 and 2:1 respectively.
Distance0 m30 m60 m90 m
R.L.G100 m110 m111 m112 m
R.L.F100 m, upward grade (1:100)
(as printed; the ground level row is hard to read)

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slopes: cutting 1:11:1, filling 2:12:1. Ground is level across the road.
  • Ground levels are read as printed (100, 110, 111, 112 m at 0, 30, 60, 90 m, the scan is hard to read) and formation level starts at 100.00 m, rising 1 in 100.

Method

Level (plain-ground) sections are used. With centre height hh, formation width BB and side slope s:1s:1:

A=(B+s h) hA = (B + s\,h)\,h

Volume between two sections = mean area × distance; where a section changes from cutting to filling, the length of each part is found by proportion of the depths and the volume of each part = ½ × end area × length.

ChainageGL (m)FL (m)Depth of cutting / height of filling (m)
0+000100.000100.0000.000
0+030110.000100.300cutting 9.700
0+060111.000100.600cutting 10.400
0+090112.000100.900cutting 11.100

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+0000.000.0000.000
0+030cut 9.70191.0900.000
0+060cut 10.40212.1600.000
0+090cut 11.10234.2100.000

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.02,866.350.00
0+030 – 0+06030.06,048.750.00
0+060 – 0+09030.06,695.550.00
Total90.015,610.650.00

Answer: Earthwork in cutting = 15,610.65 m³; earthwork in filling = 0.00 m³.

  • 2066 Bhadra (old course) · 6 marks

Find out the quantity of a hill road when the following data are given: formation width is 10 m. Side slope in cutting and filling are (1:1 and 2:1) respectively.
ChainageDepth of cutting at centre lineCross slope of ground
00.5 m10:1
300.30 m12:1
601.00 m10:1
Draw cross section at each point.

Answer

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in filling 2:12:1 (H:V); distance between sections 30 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.505.5560.000
0+030cut 0.303.3620.098
0+060cut 1.0011.3640.000

Working for one section:

Take chainage 0+030: centre cutting depth h=0.30h = 0.30 m, n=12n = 12, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.717= 0.717 m, at the downhill edge =−0.117= -0.117 m.
  • Toe of the side slope on the uphill side at x=5.782x = 5.782 m from the centre line (ground above formation by 0.782 m); downhill toe at x=5.280x = 5.280 m (ground below formation by 0.140 m).
  • Area from the co-ordinates of the polygon: cutting =3.362= 3.362 m², filling =0.098= 0.098 m².

Cross-sections (vertical scale exaggerated)

Chainage 0+000 (centre cutting 0.50 m, cross slope 10:1; area of cutting 5.556 m², filling 0.000 m²)

...
  ##.....
   ##   ........
    #          .......
    ##               ........
     #                      .......
      #                           ........
      ##########################################
                                               ...

(. ground line, # formation and side slopes)

Chainage 0+030 (centre cutting 0.30 m, cross slope 12:1; area of cutting 3.362 m², filling 0.098 m²)

..
 .##.....
   #    .......
    #         ........
    #                ........
     #                      ........
     ##########################################
                                         .....##.
                                                ..

(. ground line, # formation and side slopes)

Chainage 0+060 (centre cutting 1.00 m, cross slope 10:1; area of cutting 11.364 m², filling 0.000 m²)

..#.
  ##........
   ##      ..........
    ##              .........
     ##                      .........
      ##                             ..........
       #                                      ##..
       ##                                    ##
        ######################################

(. ground line, # formation and side slopes)

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0133.761.47
0+030 – 0+06030.0220.881.47
Total60.0354.642.94

Answer: Earthwork in cutting = 354.64 m³; earthwork in filling = 2.94 m³.

  • 2082 Bhadra · 7 marks

Estimate earthwork for an irrigation canal with following data: Bed width of canal = 5 m; F.S.L = 1 m (full supply depth) and free board = 0.5 m. Top width of both banks = 2 m. Outer bank side slope = 1:1 (H:V) and canal section slope = 2:1 (H:V). Canal bed is proposed at uniform gradient of 1 in 5,000. A vertical drop of 0.5 m is to be provided at 0+400 m chainage.
Chainage (m)R.L of Ground (m)R.L of Canal Bed (m)
0+000129.24
0+200129.00130.96
0+400129.20
0+600129.12

Answer

Given data and assumptions

  • Bed width b=5b = 5 m; FSD =1= 1 m; free board =0.5= 0.5 m, so D=1.5D = 1.5 m; top width of each bank 22 m.
  • Canal side slope 2:12:1 (inner slope of banks) and outer bank slope 1:11:1 (H:V).
  • Bed RL falls 1 in 5000 in the direction of chainage: bed at 0+200 is 130.96 m, so it is 131.00 m at 0+000 and 130.92 m at 0+400. The drop of 0.5 m at 0+400 lowers the bed to 130.42 m, then 130.38 m at 0+600.
  • The bed is above the ground everywhere, so the canal is wholly in embankment.

Method

Total depth of canal section D=FSD+free board=1.00+0.50=1.50D = \text{FSD} + \text{free board} = 1.00 + 0.50 = 1.50 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+000129.240131.000-1.760full banking0.00047.528
0+200129.000130.960-1.960full banking0.00051.872
0+400 (before drop)129.200130.920-1.720full banking0.00046.668
0+400 (after drop)129.200130.420-1.220full banking0.00036.198
0+600129.120130.380-1.260full banking0.00037.018

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+000 – 0+200200.00.009,939.92
0+200 – 0+400 (before drop)200.00.009,854.00
0+400 (after drop) – 0+600200.00.007,321.60
Total0.0027,115.52

Answer: Earthwork in cutting = 0.00 m³; earthwork in banking = 27,115.52 m³; total = 27,115.52 m³.

  • 2082 Baisakh · 8 marks

Calculate the quantities of earthwork from the following data for channel section from chainage 0+500 to 1+500 m. Bed width = 5 m, side slope in cutting 1H:1V, side slope in banking 1.5H:1V, top width of both banks = 2.5 m, full supply depth = 1.5 m and free board = 0.5 m.
ChainageRL of Bed (m)RL of ground (m)
0+5001000.501001.80
0+10001000.00999.50
0+1500999.50997.50

Answer

Given data and assumptions

  • Bed width 55 m; FSD 1.51.5 m; free board 0.50.5 m, so D=2.0D = 2.0 m; top width of each bank 2.52.5 m.
  • Side slope in cutting 1:11:1; side slope of banks (inner and outer) 1.5:11.5:1 (H:V).
  • Chainages 0+500, 1+000 and 1+500 are 500 m apart.

Method

Total depth of canal section D=FSD+free board=1.50+0.50=2.00D = \text{FSD} + \text{free board} = 1.50 + 0.50 = 2.00 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+5001,001.8001,000.5001.300part cutting, part banking8.1904.970
1+000999.5001,000.000-0.500full banking0.00033.375
1+500997.500999.500-2.000full banking0.00072.000

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+500 – 1+000500.02,047.509,586.25
1+000 – 1+500500.00.0026,343.75
Total2,047.5035,930.00

Answer: Earthwork in cutting = 2,047.50 m³; earthwork in banking = 35,930.00 m³; total = 37,977.50 m³.

  • 2080 Bhadra · 8 marks

Calculate the quantity of the earthwork of a channel with the following data: Bed width = 6 m, free board = 50 cm, slope of cutting 1:1, side slope of banking 1.5:1, full supply depth is 2 m, width of the banks is 1.5 m. There is vertical drop of 0.5 m at ground surface at chainage 0+090. The longitudinal slope of canal is 1 in 600.
ChainageGround Level (m)Bed Level (m)
0+000225.3224.00
0+030225.2
0+060225.1
0+090225.2 / 224.7 (as printed, before and after drop)
0+120224.8

Answer

Given data and assumptions

  • Bed width 66 m; FSD 22 m; free board 0.50.5 m, so D=2.5D = 2.5 m; width (top) of each bank 1.51.5 m.
  • Side slope in cutting 1:11:1; banks 1.5:11.5:1 on both faces.
  • Bed falls 1 in 600: 30 m gives 0.05 m, so the bed is 224.00, 223.95, 223.90, 223.85 m up to the drop at 0+090. The 0.5 m drop gives 223.35 m after the drop, and 223.30 m at 0+120. Ground level at 0+090 is 225.2 m before and 224.7 m after the drop.

Method

Total depth of canal section D=FSD+free board=2.00+0.50=2.50D = \text{FSD} + \text{free board} = 2.00 + 0.50 = 2.50 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+000225.300224.0001.300part cutting, part banking9.4907.920
0+030225.200223.9501.250part cutting, part banking9.0628.438
0+060225.100223.9001.200part cutting, part banking8.6408.970
0+090 (before drop)225.200223.8501.350part cutting, part banking9.9227.418
0+090 (after drop)224.700223.3501.350part cutting, part banking9.9227.418
0+120224.800223.3001.500part cutting, part banking11.2506.000

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+000 – 0+03030.0278.29245.36
0+030 – 0+06030.0265.54261.11
0+060 – 0+090 (before drop)30.0278.44245.81
0+090 (after drop) – 0+12030.0317.59201.26
Total1,139.85953.55

Answer: Earthwork in cutting = 1,139.85 m³; earthwork in banking = 953.55 m³; total = 2,093.40 m³.

  • 2076 Chaitra · 10 marks

Workout the quantity of a portion of channel fully in banking with the following data:
DistanceR.L. of Ground levelProposed bed level
5001314.751316.00
10001314.90
15001314.20
The bed width of channel is 4.50 m. The bed slope is 1 in 5000. The full supply depth is 1.50 m and free board is 0.50 m. The top width of both side banks is 2.50 m in each bank. The side slope of banks is (1.5:1).

Answer

Given data and assumptions

  • Bed width 4.54.5 m; FSD 1.51.5 m; free board 0.50.5 m, so D=2.0D = 2.0 m; top width of each bank 2.52.5 m; side slope of banks 1.5:11.5:1 (inner and outer).
  • Bed falls 1 in 5000: 0.10 m per 500 m, so bed = 1316.00, 1315.90, 1315.80 m at 500, 1000, 1500 m. The canal is wholly in banking.

Method

Total depth of canal section D=FSD+free board=1.50+0.50=2.00D = \text{FSD} + \text{free board} = 1.50 + 0.50 = 2.00 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
5001,314.7501,316.000-1.250full banking0.00051.219
10001,314.9001,315.900-1.000full banking0.00045.000
15001,314.2001,315.800-1.600full banking0.00060.240

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
500 – 1000500.00.0024,054.69
1000 – 1500500.00.0026,310.00
Total0.0050,364.69

Answer: Earthwork in cutting = 0.00 m³; earthwork in banking = 50,364.69 m³; total = 50,364.69 m³.

  • 2076 Asoj · 9 marks

Calculate the quantity of earthwork of an irrigation channel with the following data: Bed width of channel = 5 m; Top width of both banks = 2 m; Longitudinal slope of bed = 1 in 3000; Side slopes in cutting and filling = 1½:1 (H:V); Fully supply depth = 1 m; Free board = 0.60 m; R.L. of bed at 0 m = 1395.50 m. Ground level along the alignment are as given below:
R.L. of Ground1397.501397.001396.501395.70
Distance0300600900

Answer

Given data and assumptions

  • Bed width 55 m; FSD 11 m; free board 0.60.6 m, so D=1.6D = 1.6 m; top width of each bank 22 m; side slope 1.5:11.5:1 for cutting and banking (inner and outer).
  • Bed RL 1395.50 m at 0, falling 1 in 3000: 1395.50, 1395.40, 1395.30, 1395.20 m at 0, 300, 600, 900 m.

Method

Total depth of canal section D=FSD+free board=1.00+0.60=1.60D = \text{FSD} + \text{free board} = 1.00 + 0.60 = 1.60 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
01,397.5001,395.5002.000full cutting16.0000.000
3001,397.0001,395.4001.600part cutting, part banking11.8400.000
6001,396.5001,395.3001.200part cutting, part banking8.1602.080
9001,395.7001,395.2000.500part cutting, part banking2.8758.030

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0 – 300300.04,176.000.00
300 – 600300.03,000.00312.00
600 – 900300.01,655.251,516.50
Total8,831.251,828.50

Answer: Earthwork in cutting = 8,831.25 m³; earthwork in banking = 1,828.50 m³; total = 10,659.75 m³.

  • 2075 Chaitra · 6 marks

Calculate the quantity of earthwork of an irrigation canal with the following data. Bed width = 5 m, freeboard = 0.6 m, fully supply depth = 1 m, top width of both the bank = 2 m, side slope in cutting = 1:1, side slope in banking = 1½:1.
Distance (m)0300600 m
Ground level (m)325.24324.80324.43
Proposed bed level (m)324.001 in 3000 downward

Answer

Given data and assumptions

  • Bed width 55 m; FSD 11 m; free board 0.60.6 m, so D=1.6D = 1.6 m; top width of each bank 22 m; side slope in cutting 1:11:1 and in banking 1.5:11.5:1 (inner and outer faces of banks).
  • Bed RL 324.00 m at 0, falling 1 in 3000: 324.00, 323.90, 323.80 m at 0, 300, 600 m. (No drop is mentioned in the data.)

Method

Total depth of canal section D=FSD+free board=1.00+0.60=1.60D = \text{FSD} + \text{free board} = 1.00 + 0.60 = 1.60 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0325.240324.0001.240part cutting, part banking7.7381.829
300324.800323.9000.900part cutting, part banking5.3104.270
600324.430323.8000.630part cutting, part banking3.5476.703

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0 – 300300.01,957.14914.82
300 – 600300.01,328.541,645.90
Total3,285.682,560.72

Answer: Earthwork in cutting = 3,285.68 m³; earthwork in banking = 2,560.72 m³; total = 5,846.40 m³.

  • 2075 Asoj · 6 marks

Find the quantity of earth work of irrigation canal using prismoidal method from the following data:
Distance (m)050100150200
RL of Ground (m)100.00101.00101.0099.00100.00
RL of Formation (m)99.5099.0089.5089.0088.50
Formation bottom width of canal is 6 meter and side slope 1:1. (RL of formation at 100 m and 150 m as printed.)

Answer

Given data and assumptions

  • Bottom width b=6b = 6 m; side slope 1:11:1; the canal is in cutting at every station. Depth dd = GL − formation level.
  • The printed formation levels at 100 m, 150 m and 200 m (89.50, 89.00, 88.50) are not consistent with the first two (99.50, 99.00); the pattern of 0.5 m fall per 50 m is continued: 99.50, 99.00, 98.50, 98.00, 97.50 m.

Sectional areas

A=(b+s d) d=(6+d) dA = (b + s\,d)\,d = (6 + d)\,d

Distance (m)GL (m)Formation RL (m)Depth dd (m)Area (m²)
0100.0099.500.503.250
50101.0099.002.0016.000
100101.0098.502.5021.250
15099.0098.001.007.000
200100.0097.502.5021.250

Volume by the prismoidal rule

There are 5 sections (4 equal intervals of h=50h = 50 m, an even number), so Simpson's rule applies:

V=h3[A0+4(A1+A3)+2A2+A4]=503[3.250+4(16.000+7.000)+2(21.250)+21.250]\begin{aligned} V &= \frac{h}{3}\left[A_0 + 4(A_1 + A_3) + 2A_2 + A_4\right]\\ &= \frac{50}{3}\left[3.250 + 4(16.000 + 7.000) + 2(21.250) + 21.250\right] \end{aligned}

Answer: volume of earthwork (prismoidal rule) = 2,650.00 m³. (For comparison, the mean-area method gives 2,825.00 m³.)

  • 2070 Chaitra · 10 marks

Calculate the quantity of earth work for a portion of channel with the following data: Bed width = 3 m; Free Board = 0.44 m; Side slope for digging = 1:1; Side slope for banking = 1:1½ (V:H); Fully supply depth = 1 m; Top width of bank = 1.5 m.
Chainage0306090120150
RL of GL225.24224.8224.43224.12224.5224.98
Proposed level224.00223.94223.88223.82223.76223.7
Also draw a typical X-section.

Answer

Given data and assumptions

  • Bed width 33 m; FSD 11 m; free board 0.440.44 m, so D=1.44D = 1.44 m; top width of each bank 1.51.5 m.
  • Side slope for digging 1:11:1; for banking 1 V : 1½ H, i.e. 1.5:11.5:1 (H:V) on inner and outer faces of the banks.

Method

Total depth of canal section D=FSD+free board=1.00+0.44=1.44D = \text{FSD} + \text{free board} = 1.00 + 0.44 = 1.44 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Typical cross-section (part cutting, part banking)

 1.5 m   FB 0.44   FSD 1.0 m
 ____                              ____
/    \  1.5:1             1.5:1   /    \
      \_____ G.L. ____  ________/
 bank    \   1:1       1:1   /    bank
          \______________/
              b = 3 m

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0225.240224.0001.240part cutting, part banking5.2580.720
30224.800223.9400.860part cutting, part banking3.3202.749
60224.430223.8800.550part cutting, part banking1.9535.046
90224.120223.8200.300part cutting, part banking0.9907.319
120224.500223.7600.740part cutting, part banking2.7683.570
150224.980223.7001.280part cutting, part banking5.4780.557

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0 – 3030.0128.6652.04
30 – 6030.079.08116.93
60 – 9030.044.14185.48
90 – 12030.056.36163.33
120 – 15030.0123.6961.90
Total431.93579.68

Answer: Earthwork in cutting = 431.93 m³; earthwork in banking = 579.68 m³; total = 1,011.61 m³.

  • 2082 Bhadra

Calculate quantities for the following items of works for an underground RCC water tank given below: a) First class brickwork in 1:4 c/s mortar b) Steel reinforcement in top RCC cover slab [Figure a: Underground RCC water tank. Plan: outer 300 cm wide, brick wall 23 cm thick with 12 cm and 35 cm offsets/projections, inner opening 200 cm × 100 cm, 200 cm. Section A-A: overall 276 cm wide, top RCC cover slab 20 cm thick with 10 mm dia all-bent-up bars and 10 mm dia main bars @ 15 cm c/c, 10 mm dia distribution bars @ 15 cm c/c, internal height 60 cm + 137 cm + 60 cm as marked, brickwork (1:4) 23 cm at top and 35 cm at base, M20 RCC floor, PCC (1:3:6) and flat brick soling below. Figure dimensions are hard to read in the scan.]

Answer

Assumptions (figure dimensions are hard to read)

  • Clear internal size of tank 2.00×1.002.00 \times 1.00 m; internal clear height 1.371.37 m.
  • Brick wall (1:4): bottom part 0.350.35 m thick and 0.600.60 m high (12 cm offset on the outer face), top part 0.230.23 m thick and 0.770.77 m high; total 1.371.37 m.
  • Top cover slab: 2020 cm thick RCC, resting on the 23 cm wall at both ends, so its size is (2.00+2×0.23)×(1.00+2×0.23)=2.46×1.46(2.00 + 2 \times 0.23) \times (1.00 + 2 \times 0.23) = 2.46 \times 1.46 m. Clear cover 2525 mm.
  • 10 mm bars at 15 cm c/c in both directions; main bars in the short direction, alternate bars cranked up; distribution bars in the long direction; hooks 9d=0.099d = 0.09 m at each end of main and distribution bars; crank extra =0.42×(0.20−2×0.025−0.010)=0.059= 0.42 \times (0.20 - 2 \times 0.025 - 0.010) = 0.059 m at each of the two cranks.

(a) Brickwork in 1:4 mortar (centre-line method)

PartCentre-line length (m)Thickness (m)Height (m)Volume (m³)
Lower wall2 [(2.00+0.35)+(1.00+0.35)]=7.402\,[(2.00+0.35)+(1.00+0.35)] = 7.400.350.601.554
Upper wall2 [(2.00+0.23)+(1.00+0.23)]=6.922\,[(2.00+0.23)+(1.00+0.23)] = 6.920.230.771.226
Total2.780

(b) Steel in the top cover slab

  • Number of main bars =1+(2.46−0.05)/0.15=17= 1 + (2.46 - 0.05)/0.15 = 17; of these 8 are cranked and 9 are straight.
  • Straight main bar length =1.46−0.05+2×0.09=1.590= 1.46 - 0.05 + 2 \times 0.09 = 1.590 m; cranked bar =1.590+2×0.059=1.708= 1.590 + 2 \times 0.059 = 1.708 m.
  • Number of distribution bars =1+(1.46−0.05)/0.15=10= 1 + (1.46 - 0.05)/0.15 = 10, each =2.46−0.05+2×0.09=2.590= 2.46 - 0.05 + 2 \times 0.09 = 2.590 m.
  • Weight per metre of 10 mm bar =d2/162=100/162=0.617= d^2/162 = 100/162 = 0.617 kg/m.
BarsNumberLength each (m)Total length (m)Weight (kg)
Main, straight91.59014.318.83
Main, cranked81.70813.668.43
Distribution102.59025.9015.99
Total33.25

Answer: brickwork = 2.780 m³; steel in top slab = 33.3 kg.

  • 2082 Baisakh · 3×3 marks

Prepare detailed estimate for the following items of works for an underground RCC water tank given in Figure 1. i) Brickwork ii) PCC for RCC works iii) Steel reinforcement in RCC works (assume 1% steel) [Figure 1 not included in the scanned paper]

Answer

Figure 1 is not available, so the working is shown on assumed dimensions; the method is the same for any drawing.

Assumed dimensions

  • Clear internal size 3.00×2.003.00 \times 2.00 m, clear depth 1.501.50 m.
  • Brick walls 0.230.23 m thick in 1:4 mortar, 1.501.50 m high, resting on a 0.150.15 m RCC floor.
  • RCC floor 0.150.15 m thick and top cover slab 0.120.12 m thick, both of outer size (3.00+0.46)×(2.00+0.46)=3.46×2.46(3.00 + 0.46) \times (2.00 + 0.46) = 3.46 \times 2.46 m; a 0.60×0.600.60 \times 0.60 m manhole opening in the cover.
  • Steel 1%1\% of the volume of RCC; density 78507850 kg/m³.

i) Brickwork (centre-line method)

Centre-line length =2 [(3.00+0.23)+(2.00+0.23)]=10.92= 2\,[(3.00 + 0.23) + (2.00 + 0.23)] = 10.92 m

V=10.92×0.23×1.50=3.767V = 10.92 \times 0.23 \times 1.50 = 3.767 m³

ii) PCC (concrete) for the RCC works

MemberWorkingVolume (m³)
Floor slab3.46×2.46×0.153.46 \times 2.46 \times 0.151.277
Top slab3.46×2.46×0.123.46 \times 2.46 \times 0.121.021
Deduct manhole0.60×0.60×0.120.60 \times 0.60 \times 0.12−0.043
Total2.255

iii) Steel reinforcement

W=1%×2.255×7850=177.0W = 1\% \times 2.255 \times 7850 = 177.0 kg

Answer (for the assumed figure): brickwork = 3.767 m³; concrete in RCC = 2.255 m³; steel = 177.0 kg.

  • 2080 Bhadra · 4+3+1 marks

Drawing of an Underground RCC water tank is given below (Fig. 1). Prepare detailed estimate for the following items of works: i) Brickwork (1:4) ii) PCC for M20 RCC work iii) Steel reinforcement for M20 RCC work (assuming 1% steel) [Figure 1: plan 3000 mm × 2300 mm outside; brick wall 230 mm thick at top stepping to 380 mm at base with 150 mm offset; clear inside 1990 mm × 1290 mm; M20 RCC walls/floor 125 mm; 125 mm thick M25 RCC slab at top; section: 800 mm and 475 mm wall heights, overall 1450 mm, clear height 1150 mm; brickwork (1:4); PCC (1:3:6) base with flat brick soling. All dimensions in mm.]

Answer

Reading of Fig. 1

  • Outside size at base 3.00×2.303.00 \times 2.30 m; clear inside 1.99×1.291.99 \times 1.29 m. Wall at the base is 0.380.38 m of brick plus 0.1250.125 m of M20 RCC, so 1.99+2×(0.38+0.125)=3.001.99 + 2 \times (0.38 + 0.125) = 3.00 m and 1.29+2×0.505=2.301.29 + 2 \times 0.505 = 2.30 m (check).
  • Brick wall: 0.380.38 m thick for the lower 0.4750.475 m, stepping in by 0.150.15 m on the outer face to 0.230.23 m for the upper 0.800.80 m (total brick height 1.2751.275 m = clear height 1.151.15 m + floor 0.1250.125 m).
  • Inside the brick: 125 mm M20 RCC lining wall, 1.151.15 m high, and 125 mm M20 RCC floor. Top slab 125 mm M25 RCC (not part of the M20 quantity).

i) Brickwork (1:4), centre-line method

PartCentre-line length (m)Thickness (m)Height (m)Volume (m³)
Lower2 [(3.00−0.38)+(2.30−0.38)]=9.082\,[(3.00-0.38)+(2.30-0.38)] = 9.080.380.4751.639
Upper2 [(3.00−0.53)+(2.30−0.53)]=8.482\,[(3.00-0.53)+(2.30-0.53)] = 8.480.230.8001.560
Total3.199

The upper wall's outer face is set in by 0.150.15 m on each side, so its centre-line rectangle is (3.00−0.30−0.23)×(2.30−0.30−0.23)=2.47×1.77(3.00 - 0.30 - 0.23) \times (2.30 - 0.30 - 0.23) = 2.47 \times 1.77 m.

ii) Concrete for M20 RCC work

MemberWorkingVolume (m³)
Floor(1.99+0.25)(1.29+0.25)×0.125(1.99 + 0.25)(1.29 + 0.25) \times 0.1250.431
Lining wall2 [(1.99+0.125)+(1.29+0.125)]×0.125×1.15=7.06×0.125×1.152\,[(1.99+0.125)+(1.29+0.125)] \times 0.125 \times 1.15 = 7.06 \times 0.125 \times 1.151.015
Total M201.446

(For information, the M25 top slab is 2.70×2.00×0.125=0.6752.70 \times 2.00 \times 0.125 = 0.675 m³.)

iii) Steel in M20 RCC (1%)

W=0.01×1.446×7850=113.5W = 0.01 \times 1.446 \times 7850 = 113.5 kg

Answer: brickwork (1:4) = 3.199 m³; M20 concrete = 1.446 m³; steel = 113.5 kg.

  • 2079 Bhadra · 2+4+2 marks

The plan and section of the under-ground water tank which is fully constructed below the ground level. Find the quantities of a) Earthwork in excavation for construction. b) Brickwork in 1:6 cement sand mortar. c) Plastering work for inner part of tank. [Figure: Underground water tank. Top plan: outer 550 cm × 250 cm plus 30 cm wall all round (30 | 550 | 30 and 30 | 250 | 30). Sectional elevation: wall stepped with offsets of 30, 40, 50, 60 and 70 cm widths in 40 cm high steps, total height 190 cm, base footing 85 cm wide with 30 cm thick lime concrete, 3 cm thick C.C. flooring, outer plaster 1.2 cm thick 1:6 C:S, inner plaster 1.5 cm thick 1:4 C:S.]

Answer

Reading of the figure and assumptions

  • Clear internal plan 5.50×2.505.50 \times 2.50 m. The wall is stepped on the outside only, inside face vertical. Widths 0.30,0.40,0.50,0.60,0.700.30, 0.40, 0.50, 0.60, 0.70 m; heights 0.300.30 m for the top step and 0.400.40 m for each of the other four (total wall height 1.901.90 m).
  • Base footing: lime concrete 0.300.30 m thick, 0.850.85 m wide (0.075 m projection on each face of the 0.70 m base). The tank is fully below ground, so the top of the wall is at ground level and excavation depth is 1.90+0.30=2.201.90 + 0.30 = 2.20 m.
  • Floor: 3 cm C.C. flooring on the lime concrete; inner plaster 1.5 cm in 1:4 from floor to top of wall.

a) Earthwork in excavation

Footing outer size: length =5.50+2×(0.70+0.075)=7.05= 5.50 + 2 \times (0.70 + 0.075) = 7.05 m; width =2.50+2×0.775=4.05= 2.50 + 2 \times 0.775 = 4.05 m.

V=7.05×4.05×2.20=62.82V = 7.05 \times 4.05 \times 2.20 = 62.82 m³ (no working space or side slope allowed).

b) Brickwork in 1:6 mortar (centre-line method for each step)

Thickness (m)Height (m)Centre-line length (m)Volume (m³)
0.300.302 [(5.50+0.30)+(2.50+0.30)]=17.202\,[(5.50+0.30)+(2.50+0.30)] = 17.201.548
0.400.402 [(5.50+0.40)+(2.50+0.40)]=17.602\,[(5.50+0.40)+(2.50+0.40)] = 17.602.816
0.500.402 [(5.50+0.50)+(2.50+0.50)]=18.002\,[(5.50+0.50)+(2.50+0.50)] = 18.003.600
0.600.402 [(5.50+0.60)+(2.50+0.60)]=18.402\,[(5.50+0.60)+(2.50+0.60)] = 18.404.416
0.700.402 [(5.50+0.70)+(2.50+0.70)]=18.802\,[(5.50+0.70)+(2.50+0.70)] = 18.805.264
Total17.644

c) Inner plaster 1.5 cm (1:4)

  • Inner perimeter =2 (5.50+2.50)=16.00= 2\,(5.50 + 2.50) = 16.00 m; plastered height =1.90−0.03=1.87= 1.90 - 0.03 = 1.87 m (above the floor).
  • Area =16.00×1.87=29.92= 16.00 \times 1.87 = 29.92 m²
  • Wet mortar =29.92×0.015=0.4488= 29.92 \times 0.015 = 0.4488 m³; dry =1.27×0.4488=0.5700= 1.27 \times 0.4488 = 0.5700 m³; cement =0.1140= 0.1140 m³ =3.28= 3.28 bags; sand =0.4560= 0.4560 m³

Answer: excavation = 62.82 m³; brickwork = 17.644 m³; inner plaster = 29.92 m² (3.28 bags cement, 0.456 m³ sand).

  • 2082 Bhadra

Prepare a detailed estimate for the following items of works for a RCC slab culvert given below (Fig. b): a) First class brickwork in foundation b) Wearing coat in road of P.C.C (1:2:4) c) 100 mm dia. GI pipe in railing works d) Steel reinforcement in RCC slab (assume 1.5% steel) [Figure b: slab culvert. Plan: 75 cm | 280 cm | 75 cm, culvert length 430 cm, abutment lengths 140 cm, 160 cm, 140 cm, 15 cm offsets, 95 cm and 45 cm sections; slab 400 cm × 25 cm with 20 cm kerb; elevation: 100 mm dia GI railing pipe, 30 × 30 cm concrete posts @ 100 cm c/c, 15 cm wearing coat, 100 cm and 30 cm heights; sectional elevation: road level and bed level, 15 cm wearing coat, 440 cm, 160 cm, 70 cm, 30 cm, 95 cm, 85 cm, 140 cm, 40 cm, 30 cm. Details hard to read in the scan.]

Answer

Reading of the figure (dimensions are hard to read, these values are assumed)

  • Clear span 2.802.80 m with 0.750.75 m bearing on each abutment: length of culvert (along the stream) =0.75+2.80+0.75=4.30= 0.75 + 2.80 + 0.75 = 4.30 m.
  • Abutment length (across the road) =1.40+1.60+1.40=4.40= 1.40 + 1.60 + 1.40 = 4.40 m. Slab 4.004.00 m wide and 0.250.25 m thick with 0.200.20 m kerbs, so roadway between kerbs =4.00−0.40=3.60= 4.00 - 0.40 = 3.60 m.
  • Brickwork foundation of each abutment in two steps: 0.950.95 m wide ×\times 0.400.40 m high (lower) and 0.750.75 m wide ×\times 0.850.85 m high (upper).
  • Wearing coat 0.150.15 m; railing: one line of 100 mm GI pipe on each side along the culvert length.

a) First class brickwork in foundation

V=2×4.40×(0.95×0.40+0.75×0.85)=8.954V = 2 \times 4.40 \times (0.95 \times 0.40 + 0.75 \times 0.85) = 8.954 m³

b) Wearing coat, PCC (1:2:4)

V=3.60×4.30×0.15=2.322V = 3.60 \times 4.30 \times 0.15 = 2.322 m³ (area 15.48 m²)

c) 100 mm GI pipe in railing

Length =2×4.30=8.60= 2 \times 4.30 = 8.60 m

d) Steel in RCC slab (1.5%)

Concrete in slab =4.00×4.30×0.25=4.300= 4.00 \times 4.30 \times 0.25 = 4.300 m³; steel =0.015×4.300×7850=506.3= 0.015 \times 4.300 \times 7850 = 506.3 kg

Answer: brickwork = 8.954 m³; wearing coat = 2.322 m³; GI pipe = 8.60 m; steel = 506.3 kg.

  • 2076 Asoj · 10 marks

Estimate the quantities of the following items of work from the accompanying RCC Slab Culvert drawings: a) Earthwork in excavation in foundation b) PCC (1:3:6) in foundation c) PCC (1:2:4) for RCC slab [Drawing not included in the scanned paper]

Answer

The drawing is not available, so the method is shown on a stated set of dimensions; the same steps are used for any slab culvert.

Assumed dimensions

  • Clear span 3.003.00 m, bearing of slab 0.400.40 m on each abutment; slab thickness 0.300.30 m.
  • Width of culvert (along the road) 4.804.80 m (4.00 m roadway + 2 kerbs of 0.40 m).
  • Each abutment foundation: PCC (1:3:6) 1.401.40 m wide ×\times 0.300.30 m thick ×\times 4.804.80 m long, with the bottom of excavation 1.501.50 m below the ground.

a) Earthwork in excavation

V=2×1.40×4.80×1.50=20.16V = 2 \times 1.40 \times 4.80 \times 1.50 = 20.16 m³

b) PCC (1:3:6) in foundation

V=2×1.40×4.80×0.30=4.032V = 2 \times 1.40 \times 4.80 \times 0.30 = 4.032 m³

c) PCC (1:2:4) for RCC slab

Slab length =3.00+2×0.40=3.80= 3.00 + 2 \times 0.40 = 3.80 m; V=3.80×4.80×0.30=5.472V = 3.80 \times 4.80 \times 0.30 = 5.472 m³

Answer (for the assumed drawing): excavation = 20.16 m³; PCC 1:3:6 = 4.032 m³; concrete 1:2:4 in slab = 5.472 m³. For the actual drawing, substitute its dimensions in the same expressions.

  • 2075 Asoj · 4+6 marks

Workout quantity of (i) earth work excavation and (ii) brick work of slab culvert. (Fig. 2) [Figure 2: slab culvert. Sectional elevation: 300 thick RCC slab, 100 thick wearing coat, 200 thick kerb, bed/ground level, PCC (1:3:6) foundation; dimensions 590, 710, 1010, 1410 mm, clear span 2000, 295, 300, 150, 280, 230, 350. Sectional plan: 5000 total length, 2000 width, 590 abutment width. Cross-section: 5000 roadway width. Dimensions in mm, hard to read in the scan.]

Answer

Reading of Fig. 2 (dimensions are hard to read; stated values are assumed where unclear)

  • Culvert width (along the road) 5.005.00 m; clear span 2.002.00 m.
  • Each abutment: brick shaft 0.590.59 m thick ×\times 1.001.00 m high; first offset 0.710.71 m ×\times 0.300.30 m; second offset 1.011.01 m ×\times 0.300.30 m; PCC (1:3:6) bed 1.411.41 m wide ×\times 0.300.30 m thick.
  • Ground level at the top of the first offset, so excavation depth to the bottom of PCC is 0.30+0.30+0.30=0.900.30 + 0.30 + 0.30 = 0.90 m.

(i) Earthwork in excavation

V=2×1.41×5.00×0.90=12.69V = 2 \times 1.41 \times 5.00 \times 0.90 = 12.69 m³

(ii) Brickwork

PartWorkingArea of section (m²)
Shaft0.59×1.000.59 \times 1.000.5900
Offset 10.71×0.300.71 \times 0.300.2130
Offset 21.01×0.301.01 \times 0.300.3030
Total1.1060

V=2×5.00×1.1060=11.060V = 2 \times 5.00 \times 1.1060 = 11.060 m³

Answer: excavation = 12.69 m³; brickwork = 11.060 m³.

  • 2074 Asoj · 12 marks

Estimate the quantities of the following items of work from the accompanying RCC slab culvert drawings: a) Earthwork in excavation in foundation b) PCC (1:3:6) in foundation c) Brick work in (1:4) cement mortar d) PCC (1:2:4) for RCC slab [Figure: R.C.C. slab culvert 1.50 m span with standard modular bricks. Overall length 4.90 m, 4.00 m roadway, 10 cm c.c. wearing coat, slab with 20 mm dia bars @ 30 cm c/c (alternate bent up), distribution bars 10 mm dia @ 25 cm c/c, 15 cm cover; abutment 1.20 m clear span, 40 cm wall, 70 cm, 30 cm footing, C.C. 1:3:6 foundation 30 cm thick, earth slope 1:1, 60 cm curb/kerb, 1.30 m, 1.00 m height; plan 4.80 m, 1.50 m, 1.20 m. Details hard to read in the scan.]

Answer

Reading of the drawing (some dimensions are hard to read; assumed values are stated)

  • Roadway 4.004.00 m + two kerbs of 0.450.45 m: width of culvert 4.904.90 m = length of abutment.
  • Clear span between abutments 1.201.20 m, bearing 0.150.15 m each side, so slab span 1.501.50 m; slab thickness 0.200.20 m (assumed).
  • Abutment: brick shaft 0.400.40 m thick ×\times 1.001.00 m high on a brick footing 0.700.70 m wide ×\times 0.300.30 m high; PCC (1:3:6) bed 1.001.00 m wide ×\times 0.300.30 m thick; bottom of PCC 0.600.60 m below ground (footing + PCC).

a) Earthwork in excavation

V=2×1.00×4.90×0.60=5.880V = 2 \times 1.00 \times 4.90 \times 0.60 = 5.880 m³

b) PCC (1:3:6) in foundation

V=2×1.00×4.90×0.30=2.940V = 2 \times 1.00 \times 4.90 \times 0.30 = 2.940 m³

c) Brickwork in 1:4 mortar

Area of one abutment section =0.70×0.30+0.40×1.00=0.61= 0.70 \times 0.30 + 0.40 \times 1.00 = 0.61 m²

V=2×4.90×0.61=5.978V = 2 \times 4.90 \times 0.61 = 5.978 m³

d) PCC (1:2:4) for RCC slab

V=4.90×1.50×0.20=1.470V = 4.90 \times 1.50 \times 0.20 = 1.470 m³

Answer: excavation = 5.880 m³; PCC (1:3:6) = 2.940 m³; brickwork = 5.978 m³; slab concrete (1:2:4) = 1.470 m³.

  • 2066 Bhadra (old course) · 14 marks

Estimate the quantities of the following items of work from the accompanying drawing. a) Earthwork in excavation b) Cement concrete in foundation c) Brick work d) RCC work [Figure: RCC slab culvert; roadway 4 m, overall length 530 cm, 8 cm C.C. wearing coat, 22 cm thick road metal, slab 30 cm with 10 mm dia @ 22 c/c and 16 mm dia @ 10 c/c bars (alternate bars cranked), wall 50 cm × 90 cm, footing 80 cm × 30 cm, 45 degree earth slope, 150 cm, 140 cm, 120 cm, 500 cm length, 15 cm offsets. All dimensions in centimetres.]

Answer

Reading of the drawing (dimensions in the scan are hard to read; assumed values are stated)

  • Overall length of culvert across the road 5.305.30 m (4.00 m roadway plus kerbs). Clear span 1.501.50 m.
  • Abutment: wall 0.500.50 m thick ×\times 0.900.90 m high; C.C. foundation (1:3:6 assumed) 0.800.80 m wide ×\times 0.300.30 m thick; excavation to 0.700.70 m depth (0.30 m C.C. plus 0.40 m below bed level).
  • Slab 0.300.30 m thick resting 0.300.30 m on each abutment (span 1.50+2×0.30=2.101.50 + 2 \times 0.30 = 2.10 m). The wearing coat and road metal are not asked.

a) Earthwork in excavation

V=2×0.80×5.30×0.70=5.936V = 2 \times 0.80 \times 5.30 \times 0.70 = 5.936 m³

b) Cement concrete in foundation

V=2×0.80×0.30×5.30=2.544V = 2 \times 0.80 \times 0.30 \times 5.30 = 2.544 m³

c) Brickwork

V=2×0.50×0.90×5.30=4.770V = 2 \times 0.50 \times 0.90 \times 5.30 = 4.770 m³

d) RCC work (slab)

V=5.30×2.10×0.30=3.339V = 5.30 \times 2.10 \times 0.30 = 3.339 m³

Answer: excavation = 5.936 m³; C.C. foundation = 2.544 m³; brickwork = 4.770 m³; RCC slab = 3.339 m³.

  • 2081 Bhadra · 3+4+3 marks

Determine the following quantities from drawing of septic tank. i) Earthwork in excavation ii) Brickwork in (1:6) cement sand mortar iii) PCC in foundation (1:3:6) [Drawing not included in the scanned paper]

Answer

A drawing is not given, so a typical two-chamber septic tank is assumed. Excavation is taken for the plan of the PCC plus working space; brickwork by the centre-line method; PCC over the full footprint.

Assumed data

  • Internal size 3.0 m × 1.2 m, liquid depth 1.5 m; outer walls 230 mm in 1:6 mortar from top of PCC to 0.30 m above GL (height 1.80 m); a 115 mm partition wall (3.0 m internal length is shared by two chambers) rising 1.5 m.
  • PCC 1:3:6, 150 mm thick, projecting 150 mm beyond outer wall faces; working space 150 mm more on each side.
  • Outside size of tank = 3.46 × 1.66 m; PCC size = 3.76 × 1.96 m; excavation size = 4.06 × 2.26 m; depth of excavation = 0.15 + 1.5 = 1.65 m.
  • Centre-line length of walls = 2[(3.0 + 0.23) + (1.2 + 0.23)] = 9.32 m.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Pit for tank14.0602.2601.65015.140
Total15.140

ii) Brickwork in 1:6 cement sand mortar

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Outer walls, 230 mm (centre-line)19.3200.2301.8003.858
Partition wall, 115 mm (to 1.5 m)11.2000.1151.5000.207
Total4.065

Small openings (inlet, outlet, manhole recess) are ignored in a first estimate, which slightly overstates the brickwork.

iii) PCC in foundation (1:3:6)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC 1:3:6 bed under tank13.7601.9600.1501.105
Total1.105

Answer: Excavation = 15.14 m³; brickwork 1:6 = 4.07 m³; PCC 1:3:6 = 1.11 m³ (assumed dimensions).

  • 2080 Baisakh · 4+2+2 marks

Prepare a detailed estimate of the following items from the septic tank with soak pit from the given fig 1. a) Earth work in excavation for soak pit b) Cement concrete flooring for septic tank c) Cement plaster (1:3) of 20 mm for septic tank floor Dimensions of septic tank: width = 750 mm, length = 1500 mm. Soak pit is of 1000 mm diameter. [Figure 1: septic tank with soak pit; 100 dia vent pipe, 450 dia manhole cover with frame, 100 thk R.C.C. slab, 375 mm brick walls, 125 mm walls, 250 mm offsets, heights 300, 850, 1200, 150, 100 mm; soak pit with stone/brick aggregate filling, 250 mm thick outer casing with coarse sand, overflow outlet, depth 1200 mm and 700 mm.]

Answer

Items are taken from the dimensions stated: tank 1500 mm × 750 mm (internal), soak pit 1000 mm diameter.

Assumptions (from the figure)

  • Soak pit: 1000 mm diameter (internal) with a 250 mm coarse sand/aggregate casing around it, so the excavated diameter = 1.0 + 2 × 0.25 = 1.50 m.
  • Depth of soak pit = 1.2 m (the 1200 mm marked); the 700 mm dimension is the filling/cover zone inside this depth.
  • Floor of septic tank: cement concrete 150 mm thick over the internal area (the 150 mm marked).

a) Earthwork in excavation for soak pit

V=π4D2 h=π4×(1.50)2×1.20=2.121 m3V=\frac{\pi}{4}D^2\,h=\frac{\pi}{4}\times(1.50)^2\times 1.20=2.121\ \text{m}^3

b) Cement concrete flooring of septic tank

Volume = length × width × thickness = 1.5 × 0.75 × 0.15 = 0.169 m³.

c) Cement plaster (1:3), 20 mm, on septic tank floor

Area = 1.5 × 0.75 = 1.125 m². Mortar volume = 1.125 × 0.020 = 0.0225 m³.

Answer: Excavation for soak pit = 2.12 m³; floor concrete = 0.169 m³; floor plaster = 1.125 m².

  • 2074 Chaitra · 5 marks

Workout quantity of brickwork of a septic tank. [Figure: Septic tank. Plan: internal 2000 mm × 1000 mm, wall 230 mm, 450 mm and 50 mm (baffle) marked. Section: wall 230 mm at top stepping to 350 mm, 150 mm offset, total internal depth 1800 mm, 350 mm cover zone, 75 th RCC precast cover, 50 th RCC baffle, 150 mm base slab with 1:20 slope, inlet/outlet 150 mm, 300 mm.]

Answer

Brickwork volume of the septic tank walls is found by the centre-line method, treating the 350 mm lower wall and 230 mm upper wall separately.

Assumptions (from the figure)

  • Internal plan 2000 mm × 1000 mm; total internal depth 1800 mm. The wall is 350 mm thick for the lower 0.9 m and steps to 230 mm for the upper 0.9 m (the 120 mm difference is the offset on the inside/outside).
  • The 75 mm precast RCC cover and 50 mm RCC baffle are RCC items, not brickwork; the 150 mm base slab is concrete. Small inlet/outlet openings (150 mm) are ignored.

Centre-line lengths

  • Lower wall: 2[(2.0 + 0.35) + (1.0 + 0.35)] = 2(2.35 + 1.35) = 7.40 m
  • Upper wall: 2[(2.0 + 0.23) + (1.0 + 0.23)] = 2(2.23 + 1.23) = 6.92 m

Calculation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Lower wall 350 mm (centre-line)17.4000.3500.9002.331
Upper wall 230 mm (centre-line)16.9200.2300.9001.432
Total3.763

Answer: Brickwork in the septic tank = 3.76 m³.

  • 2081 Bhadra · 4 marks

A well foundation for pier of a bridge is to be constructed. It has 7 meters internal diameter and 15 metres depth from river bed level to top of well curb. Well steining of 1 meter thickness is to be constructed up to 7.5 metres depth and remaining of 2 m thickness with M20 RCC. There are two plugs of M20 concrete at top and middle of 1 m thickness. Find out i) Quantity of PCC for M20 RCC works ii) Steel reinforcement for M20 RCC work well steining (1.5% of PCC by volume)

Answer

Meaning of the data. Well steining is 1.0 m thick for the top 7.5 m of the 15 m depth and 2.0 m thick for the remaining 7.5 m (M20 RCC). Two 1.0 m thick M20 plugs are placed at the top and middle of the well.

i) Quantity of concrete in the steining

Annular volume = π4(Do2−Di2)×h\frac{\pi}{4}(D_o^2-D_i^2)\times h, with Di=7D_i = 7 m.

  • Upper steining (t=1t=1 m, Do=9D_o=9 m): π4(81−49)×7.5=188.496\frac{\pi}{4}(81-49)\times 7.5 = 188.496 m³
  • Lower steining (t=2t=2 m, Do=11D_o=11 m): π4(121−49)×7.5=424.115\frac{\pi}{4}(121-49)\times 7.5 = 424.115 m³

Total M20 concrete in steining = 188.496 + 424.115 = 612.61 m³.

Plugs (2 nos., 1.0 m thick, 7 m dia): 2×π4×72×1.0=76.972\times\frac{\pi}{4}\times 7^2\times 1.0 = 76.97 m³ of M20 plain concrete.

ii) Steel reinforcement in steining (1.5 % by volume)

Volume of steel = 0.015 × 612.611 = 9.189 m³.

Weight = 9.189 × 7850 kg/m³ = 72135 kg = 72.13 tonnes.

Answer: Steining concrete = 612.61 m³ (plus 76.97 m³ in plugs); steel = 72.13 t.

  • 2081 Baisakh · 6+2 marks

From the drawing attached of the brick masonry pier (Fig. 2), calculate the total quantity of brick work and also the pointing work. [Figure 2 not included in the scanned paper]

Answer

The pier drawing is not available, so the method is shown for an assumed stepped brick pier: two footing steps, a square shaft and a projecting cap. Brickwork is the sum of the volumes of each prism; pointing is the exposed surface area only.

Assumed data

  • Footing step 1: 1.50 m × 1.50 m × 0.30 m; step 2: 1.20 m × 1.20 m × 0.30 m (both below ground, so not pointed).
  • Shaft: 0.90 m × 0.90 m × 2.40 m high; cap: 1.05 m × 1.05 m × 0.15 m. Brick in 1:6 cement mortar.

Brickwork

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Footing step 1: 1.50 × 1.50 × 0.3011.5001.5000.3000.675
Footing step 2: 1.20 × 1.20 × 0.3011.2001.2000.3000.432
Pier shaft 0.90 × 0.90 × 2.4010.9000.9002.4001.944
Cap course 1.05 × 1.05 × 0.1511.0501.0500.1500.165
Total3.216

Pointing (exposed faces above ground)

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Shaft, 4 faces40.9002.400–8.640
Cap, 4 vertical faces41.0500.150–0.630
Cap overhang underside (1.05² − 0.90²)10.292––0.292
Cap top surface11.0501.050–1.103
Total10.665

Answer: Brickwork = 3.216 m³; pointing = 10.67 m² (assumed dimensions; for the actual figure take each step as length × breadth × height and each exposed face once).

  • 2078 Bhadra · 3+5 marks

From the attached drawing (figure 2) of RCC column, estimate the following items. (i) RCC 1:2:4 in column (ii) Steel reinforcement work excluding formwork [Figure 2: Column footing 1.5 m × 1.5 m in plan, RCC 1:2:4, 20 cm thick at edge (sloping up to column) with 10 cm PCC 1:3:6 below; column 30 cm × 30 cm, 3.50 m above GL and 70 cm below GL; footing reinforcement 12 mm main bars @ 10 cm c/c and 10 mm distribution bars @ 10 cm c/c; column reinforcement 4–16 mm dia and 4–12 mm dia vertical bars; 6 mm dia stirrups @ 15 cm c/c; anchorage/development 45 times bar dia.]

Answer

The footing thickness at the column face is not given, so 0.45 m is assumed (0.20 m at the edge, sloping up 0.25 m to the column). Footing 1.5 m × 1.5 m is 0.70 m below GL (bottom of the RCC footing), column 0.30 × 0.30 m rises 3.50 m above GL.

i) RCC 1:2:4

Column (above footing top, height = 0.70 − 0.45 + 3.50 = 3.75 m):

0.30 × 0.30 × 3.75 = 0.337 m³

Footing (a slab plus a sloping pyramid frustum):

  • Edge slab: 1.5 × 1.5 × 0.20 = 0.450 m³
  • Frustum (prismoidal formula, h=0.25h=0.25 m, A1=2.25A_1=2.25, A2=0.09A_2=0.09): 0.253(2.25+0.09+2.25×0.09)=0.2325\frac{0.25}{3}\left(2.25+0.09+\sqrt{2.25\times0.09}\right)=0.2325 m³
  • Footing total = 0.682 m³

Total RCC 1:2:4 (footing + column) = 0.337 + 0.682 = 1.020 m³. (PCC 1:3:6, 10 cm under footing = 1.5 × 1.5 × 0.10 = 0.225 m³.)

ii) Steel reinforcement (formwork excluded)

Cover 50 mm in footing, 25 mm in column; weight per metre = d2/162d^2/162 kg (d in mm).

BarWorkingLength (m)Weight (kg)
12 mm main, 15 bars15 × (1.5 − 0.10)21.0018.67
10 mm distribution, 15 bars15 × 1.4021.0012.96
16 mm vertical, 4 bars4 × (4.20 − 0.05 + 45 × 0.016)19.4830.78
12 mm vertical, 4 bars4 × (4.20 − 0.05 + 45 × 0.012)18.7616.68
6 mm stirrups, 29 nos.29 × (4 × 0.25 + 2 × 10 × 0.006)32.487.22
Total86.31

Number of stirrups = (4.20 − 0.10)/0.15 + 1 rounded up = 29. Bars per layer in the footing = 1.40/0.10 + 1 = 15. (Column bars carry a 45d development length at the top and no extra hook at the bottom; bend allowances are ignored.)

Answer: RCC 1:2:4 = 1.02 m³ (column 0.337 m³, footing 0.682 m³); steel ≈ 86.3 kg.

  • 2082 Bhadra

Prepare detailed estimate for the following items of works for one-roomed building: (Use fig.c) a) Earthwork in excavation. b) 12 mm thick plaster work inside and outside the building. c) Door and windows frame and shutters. [Figure c: One-roomed building. Ground floor plan: external length 4200 mm and width 3000 mm (plus 1200 projection), wall 230 mm thick, offsets 2000, 2000, 470, 600, 470, 230 mm, door D1 1000 × 2100 mm, windows W1 600 × 1000 mm, 4000 mm and 1400 mm room dimensions. Section X-X: height 2650 mm, plinth 450 mm, 300 × 300 mm plinth tie-beam, M20 RCC slab 125 mm with 600 mm projection, brickwork (1:6) above plinth, stone masonry in foundation, PCC (1:2:4) 75 mm with brick soling and compacted earth, foundation width 600/400/300 mm. All dimensions in mm; details approximate.]

Answer

The figure is approximate, so the following reading is used: building 4.2 m × 3.0 m outside, walls 0.23 m; one door D1 1.0 × 2.1 m; two windows W1 0.6 × 1.0 m (number assumed); inside height 2.65 m; plinth 0.45 m; RCC slab 125 mm. The 1200 mm projection is taken as a slab canopy and is not walled.

Centre-line length = 2[(4.2 − 0.23) + (3.0 − 0.23)] = 13.48 m.

a) Earthwork in excavation

Foundation (stone masonry, widths 600/400/300 mm) needs a trench 0.60 m wide; assumed depth 0.90 m (75 mm soling, 75 mm PCC 1:2:4, masonry above).

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, centre-line113.4800.6000.9007.279
Total7.279

b) 12 mm plaster, inside and outside

Inside perimeter = 2(3.74 + 2.54) = 12.56 m; outside perimeter = 2(4.2 + 3.0) = 14.40 m. Outside height taken from GL to top of slab edge = 0.45 + 2.65 + 0.125 = 3.225 m.

Inside:

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside wall112.5602.650–33.284
Deduct door-11.0002.100–-2.100
Deduct windows-20.6001.000–-1.200
Add reveals, door (3 sides × 0.23)11.196––1.196
Add reveals, windows20.736––1.472
Total32.652

Outside:

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Outside wall (plinth + wall + slab edge)114.4003.225–46.440
Deduct door-11.0002.100–-2.100
Deduct windows-20.6001.000–-1.200
Total43.140

Total plaster = 32.65 + 43.14 = 75.79 m².

c) Doors and windows

Frame section assumed 100 × 75 mm.

ItemWorkingQuantity
Door frame (2 × 2.1 + 1.0)5.2 × 0.10 × 0.0750.0390 m³
Window frames, 2 nos. (2 × 1.0 + 2 × 0.6)2 × 3.2 × 0.10 × 0.0750.0480 m³
Door shutter1.0 × 2.12.10 m²
Window shutters2 × 0.6 × 1.01.20 m²

Answer: Excavation = 7.28 m³; plaster = 75.79 m²; frames = 0.087 m³ of timber; shutters = 3.30 m².

  • 2082 Baisakh · 3+4+3+3 marks

From the attached plan and section (Figure 2) of single room building, estimate the quantities. i) Earthwork in excavation ii) Brickwork in 1:6 c/s mortar up to plinth level iii) 12.5 mm thick plastering in room and ceiling iv) Door window shutter (assume door window frame is 0.1 m × 0.1 m) [Figure 2 not included in the scanned paper]

Answer

No figure is available, so a single room is assumed: 4.0 m × 3.0 m clear, walls 230 mm, centre-line length = 2(4.0 + 3.0 + 2 × 0.23) = 14.92 m.

Assumed data

  • Trench 0.90 m wide × 1.00 m deep; PCC 200 mm; two brick footing steps (0.69 m and 0.46 m wide, 150 mm high each); plinth 0.45 m above GL.
  • Wall (0.23 m) from top of last step to plinth top = 1.00 − 0.20 − 0.30 + 0.45 = 0.95 m.
  • Ceiling height 3.0 m; one door 1.0 × 2.1 m, two windows 1.2 × 1.2 m.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)114.9200.9001.00013.428
Total13.428

ii) Brickwork in 1:6 c/s mortar up to plinth level

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)114.9200.6900.1501.544
Brick footing step 2 (0.46 m wide)114.9200.4600.1501.029
Wall up to plinth114.9200.2300.9503.260
Total5.834

iii) 12.5 mm plastering in room and ceiling

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside walls, 2(4.0+3.0) × 3.0114.0003.000–42.000
Deduct door-11.0002.100–-2.100
Deduct windows-21.2001.200–-2.880
Ceiling 4.0 × 3.014.0003.000–12.000
Total49.020

iv) Door and window shutters

Frame 0.1 m × 0.1 m, so the shutter is smaller than the opening by one frame width at each vertical side and the head.

  • Door shutter = (1.0 − 2 × 0.1) × (2.1 − 0.1) = 0.80 × 2.00 = 1.60 m²
  • Window shutters = 2 × (1.2 − 0.2) × (1.2 − 0.2) = 2 × 1.00 = 2.00 m²
  • Total shutter area = 3.60 m²

Answer: Excavation 13.43 m³; brickwork to plinth 5.83 m³; plastering 49.02 m²; shutters 3.60 m² (assumed dimensions).

  • 2081 Bhadra · 4+3+3 marks

From the attached plan and section of single room building, estimate the quantities. i) Brickwork in foundation up to plinth with 1:6 cement mortar. ii) 2 cm DPC at plinth level. iii) Brickwork in superstructure in cement mortar. [Drawing not included in the scanned paper]

Answer

No drawing is available, so a typical single room is assumed. The standard method is the centre-line method.

Assumed data

  • Room 4.0 m × 3.5 m clear, 230 mm walls; centre-line length = 2(4.0 + 3.5 + 0.46) = 15.92 m.
  • Foundation: trench 0.90 m × 1.00 m, PCC 200 mm, two brick steps 0.69 and 0.46 m wide (150 mm each), 230 mm wall up to plinth top (0.45 m above GL); wall height from last step = 0.95 m.
  • Superstructure height 3.0 m; D 1.0 × 2.1 m (1 no.); W 1.2 × 1.2 m (2 nos.); lintel 150 mm deep with 200 mm bearing each side.

i) Brickwork in foundation up to plinth, 1:6

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)115.9200.6900.1501.648
Brick footing step 2 (0.46 m wide)115.9200.4600.1501.098
Wall up to plinth115.9200.2300.9503.479
Total6.225

ii) 2 cm DPC at plinth level

DPC (cement concrete 1:2:4 with waterproofing) is measured in m² = wall length × wall width, not carried across door openings.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
DPC 20 mm, wall length115.9200.230–3.662
Deduct door opening-11.0000.230–-0.230
Total3.432

iii) Brickwork in superstructure

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall above plinth, full length115.9200.2303.00010.985
Deduct door 1.00×2.10-11.0000.2302.100-0.483
Deduct window 1.20×1.20-21.2000.2301.200-0.662
Deduct lintel bearing, 1.00 m opening-11.4000.2300.150-0.048
Deduct lintel bearing, 1.20 m opening-21.6000.2300.150-0.110
Total9.681

Answer: Foundation and plinth brickwork 6.22 m³; DPC 3.43 m²; superstructure brickwork 9.68 m³ (assumed dimensions).

  • 2081 Baisakh · 4×4 marks

Calculate the quantities from the given building drawings: Fig. 1(a, b) a) Earthwork in excavation b) Crushed rubble stone masonry c) 1st class brick work in super structure d) 12 mm plastering work 1:4 for inner wall Following are the double room building estimation specifications:
  • In foundation cement concrete M25 is used.
  • CRS wall is used in the foundation for the base of the brick wall.
  • Plinth beam size is 400 mm × 600 mm in cement concrete M25.
  • Damp-proof course 25 mm thick is applied.
  • In superstructure 1st class brickwork is in 1:4 cement mortar and thickness 300 mm.
  • Doors D, size 1.2 m × 2.1 m
  • Windows W, size 1 m × 1.5 m
  • Shelves S-1 m × 1.5 m [Fig. 1(a, b) not included in the scanned paper]

Answer

Fig. 1 is not available, so an assumed double-room building is used with the given specifications.

Assumed data

  • Two rooms side by side, each 4.0 m × 3.5 m clear; all walls 300 mm (as stated). Outside size = (2 × 4.0 + 3 × 0.3) × (3.5 + 2 × 0.3) = 8.90 × 4.10 m.
  • Centre-line length of outer walls = 2[(8.90 − 0.3) + (4.10 − 0.3)] = 24.80 m; partition (clear) = 3.5 m; total wall length = 28.30 m.
  • Foundation: trench 1.10 m wide, 1.20 m deep; CC M25 bed 0.30 m; CRS wall 0.50 m wide, 0.75 m high from top of bed to bottom of plinth beam (0.15 m below GL); plinth beam 400 × 600 mm (not asked).
  • Superstructure 3.0 m high above plinth beam; D 1.2 × 2.1 (2 nos.), W 1.0 × 1.5 (3 nos.), shelf recess S 1.0 × 1.5 × 0.15 m deep (2 nos.). Plaster 12 mm 1:4.

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, outer + partition128.3001.1001.20037.356
Total37.356

b) Crushed rubble stone masonry

ItemNo.L (m)B (m)H/D (m)Qty (m³)
CRS masonry 0.50 m wide × 0.75 m high128.3000.5000.75010.612
Total10.612

(For reference, M25 concrete bed = 9.34 m³.)

c) 1st class brick work in superstructure (1:4)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.30 × 3.0 above plinth beam128.3000.3003.00025.470
Deduct doors D 1.2 × 2.1 (2 nos.)-21.2000.3002.100-1.512
Deduct windows W 1.0 × 1.5 (3 nos.)-31.0000.3001.500-1.350
Deduct shelves S 1.0 × 1.5 × 0.15 recess (2 nos.)-21.0000.1501.500-0.450
Deduct lintel bearings (doors)-21.6000.3000.150-0.144
Deduct lintel bearings (windows & shelves)-51.4000.3000.150-0.315
Total21.699

d) 12 mm plastering, 1:4, inner wall

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside walls, both rooms 2 × 2(4.0+3.5) × 3.0130.0003.000–90.000
Deduct doors (each door once inside per room)-21.2002.100–-5.040
Deduct windows-31.0001.500–-4.500
Total80.460

Answer: Excavation 37.36 m³; CRS 10.61 m³; brickwork 21.70 m³; plaster 80.46 m² (assumed layout).

  • 2080 Bhadra · 3+4+3 marks

Prepare detailed estimate for the following items of works for RCC frame structured building (Fig. 2.) i) Earthwork in excavation in foundation ii) Brickwork in 1:4 c/s mortar up to plinth level iii) 1:4 (c/s) mortar inside the room [Figure 2: two-room building. Overall 7000 mm × 4700 mm outer; Room 1 3180 × 3040 mm, Room 2 3130 × 3040 mm, verandah 7000 × 1200 mm. Openings: D1 1000 × 2100 mm, W1 1500 × 1350 mm, W2 1000 × 1350 mm. Plinth tie-beam 300 × 300 mm; superstructure wall thickness 230 mm (same section for exterior and partition walls). Section A-A: height 2850 mm, M20 RCC slab 125 mm with 600 mm projection, brickwork 1:6 in superstructure, 1:4 brickwork in plinth (450 mm), foundation with 75 mm PCC, brick soling, compacted earth, PCC (1:2:4); footing widths 600/400/300 mm; heights 300/150/350/150 mm. All dimensions in mm, not to scale.]

Answer

Reading of the figure

Outer building = 7000 × 4700 mm including the 1200 mm verandah, so the rooms (and walls) occupy 7000 × 3500 mm (3040 + 2 × 230 = 3500; 3180 + 3130 + 3 × 230 = 7000). Walls are 230 mm. The verandah is open and not walled. Assumptions: one door D1 in each room, W1 in Room 1, W2 in Room 2.

Foundation: concrete 0.60 m wide × 0.30 m thick, brick step 0.40 m × 0.15 m, 230 mm wall; trench depth taken as 0.30 + 0.15 + 0.35 = 0.80 m; plinth 0.45 m above GL; 300 × 300 RCC tie beam at the top of plinth.

Centre-line length of outer walls = 2[(7.0 − 0.23) + (3.5 − 0.23)] = 20.08 m; partition (clear) = 3.04 m; total = 23.12 m.

i) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, outer walls120.0800.6000.8009.638
Trench, partition13.0400.6000.8001.459
Total11.098

ii) Brickwork in 1:4 c/s mortar up to plinth level

Wall height = 0.35 (below GL) + 0.45 (plinth) − 0.30 (tie beam) = 0.50 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick step 0.40 × 0.15123.1200.4000.1501.387
Wall 0.23 up to plinth tie beam123.1200.2300.5002.659
Deduct door sill width (D1 ×2)-21.0000.2300.500-0.230
Total3.816

iii) 1:4 cement-sand plaster inside the rooms (12 mm assumed)

Clear height 2.85 m.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Room 1 walls112.4402.850–35.454
Room 2 walls112.3402.850–35.169
Deduct D1 1.0 × 2.1 (2 nos.)-21.0002.100–-4.200
Deduct W1 1.5 × 1.35-11.5001.350–-2.025
Deduct W2 1.0 × 1.35-11.0001.350–-1.350
Total63.048

Mortar volume at 12 mm = 63.05 × 0.012 = 0.757 m³.

Answer: Excavation 11.10 m³; brickwork to plinth 3.82 m³; inside plaster 63.05 m².

  • 2080 Baisakh · 3+2+4+3 marks

Prepare detailed estimate of the following items of works from the given building drawing attached fig 3. a) Earth work in excavation in foundation b) Plain cement concrete (1:3:6) in foundation. c) Brickwork in 1:6 C.S. in super structure wall. d) Wood work for door and window frame. [Fig 3: plan, overall length 7250 mm (1265 + 1200 + 2300 + 1200 + 1265), width 3730 mm with internal 3500 mm, 230 mm walls, internal clear 3270 mm each room, partition with door P1, door D 1200 × 2100, D1 1000 × 2100, window W 1500 × 1200, W1 1200 × 1200 (as printed '15400×1200'). Section X-X: 600 mm roof projection, 18 mm screed over 2 layers of tarfelt, roof slab, window 3270 wide, sill/lintel levels 2100 and 2400, DPC, plinth with 3 cm cement sand (1:1) pointing over 36 cement concrete (1:2:4), 75 thick brick bats soling, 150 sand filling, foundation PCC (1:3:6) 770 mm wide with 150/250/150 mm layers.]

Answer

Reading of the drawing

Two rooms of 3.27 m × 3.27 m clear side by side, 230 mm walls (3 × 0.23 + 2 × 3.27 = 7.23 m; 3.27 + 2 × 0.23 = 3.73 m). Centre-line length of outer walls = 2[(7.23 − 0.23) + (3.73 − 0.23)] = 21.00 m; central partition = 3.27 m; total = 24.27 m.

Foundation profile assumed from the section: PCC 1:3:6, 0.77 m wide × 0.15 m; brick step 0.69 m × 0.25 m; step 0.46 m × 0.15 m; 230 mm wall, trench depth 0.80 m; plinth 0.45 m above GL. Wall height above plinth (floor to slab soffit) = 2.4 m. Openings assumed: D 1.2 × 2.1 (1 no.), D1 1.0 × 2.1 (1 no., partition), W 1.5 × 1.2 (2 nos.), W1 1.2 × 1.2 (1 no.).

a) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench (centre-line)124.2700.7700.80014.950
Total14.950

b) PCC (1:3:6) in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC 1:3:6, 0.77 wide124.2700.7700.1502.803
Total2.803

c) Brickwork in 1:6 c.s. in superstructure wall

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.23 × 2.4 above plinth124.2700.2302.40013.397
Deduct D 1.2×2.1-11.2000.2302.100-0.580
Deduct D1 1.0×2.1-11.0000.2302.100-0.483
Deduct W 1.5×1.2-21.5000.2301.200-0.828
Deduct W1 1.2×1.2-11.2000.2301.200-0.331
Total11.175

d) Wood work for door and window frames

Frame section assumed 100 × 75 mm (doors have no sill member).

FrameNo.L (m)B (m)H/D (m)Qty (m³)
Frame D (2×2.1 + 1×1.2)15.4000.1000.0750.0405
Frame D1 (2×2.1 + 1×1.0)15.2000.1000.0750.0390
Frame W (2×1.2 + 2×1.5)25.4000.1000.0750.0810
Frame W1 (2×1.2 + 2×1.2)14.8000.1000.0750.0360
Total0.1965

Answer: Excavation 14.95 m³; PCC 2.803 m³; superstructure brickwork 11.18 m³; frame timber 0.197 m³.

  • 2079 Bhadra · 3+4+3 marks

Find the following quantities for the following items of works from the attached building drawing. The building is a load bearing structure with 23 cm wall all around. A non-load bearing wall of thickness 11 cm divides the living room and the bathroom. The half brick thick wall is not connected to the foundation. a) Earthwork in excavation in foundation b) First class brick work in cement sand mortar (1:4) in super structure. c) 12 mm thick cement plaster in 1:4 c/s mortar in inner (opening schedule door: 2 nos 1.2 × 2.1 m, window 3 nos 1 × 1.1 m) [Building drawing not included in the scanned paper]

Answer

No drawing is given, so a layout consistent with the data is assumed: the building is 5.0 m × 3.0 m clear inside (outside 5.46 × 3.46 m), 230 mm load-bearing walls all around; the 110 mm half-brick partition divides a living room (3.5 × 3.0 m) from a bathroom (1.5 × 3.0 m). The partition is not connected to the foundation, so it has no trench.

Assumed data

  • Centre-line length of 230 mm walls = 2[(5.0 + 0.23) + (3.0 + 0.23)] = 16.92 m.
  • Trench 0.90 m wide × 1.00 m deep; superstructure height 3.0 m (plinth to slab soffit).
  • Openings: 2 doors 1.2 × 2.1 m (one external, one in the partition), 3 windows 1.0 × 1.1 m (external).

a) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench for 230 mm walls only116.9200.9001.00015.228
Total15.228

b) First class brickwork in 1:4 c/s mortar, superstructure

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Outer wall 0.23 × 3.0116.9200.2303.00011.675
Partition 0.11 (clear 3.0 × 3.0)13.0000.1103.0000.990
Deduct external door 1.2×2.1-11.2000.2302.100-0.580
Deduct partition door 1.2×2.1-11.2000.1102.100-0.277
Deduct windows 1.0×1.1 (3 nos.)-31.0000.2301.100-0.759
Total11.049

c) 12 mm thick 1:4 inner plaster

Inner faces only (rooms, including both faces of the partition):

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Living room 3.5 × 3.0 inside perimeter113.0003.000–39.000
Bathroom 1.5 × 3.0 inside perimeter19.0003.000–27.000
Deduct external door (living room face)-11.2002.100–-2.520
Deduct partition door (both faces)-21.2002.100–-5.040
Deduct windows (3 nos.)-31.0001.100–-3.300
Total55.140

Answer: Excavation 15.23 m³; superstructure brickwork 11.05 m³; inner plaster 55.14 m² (assumed layout).

  • 2078 Bhadra · 5 marks

Prepare detailed estimate of the item of work from the building drawing (figure 1) attached herewith: a) Earthwork in excavation in foundation b) PCC (1:3:6) in foundation c) Brick work in 1:6 cement sand mortar up to Plinth d) Plastering work 1:4 for the ceiling. [Figure 1: Plan 7900 mm overall length × 5400 mm; two rooms 3450 × 3300 mm and 3400 × 4600 mm; front verandah/open portion 1300 mm; external bays 900, 2400, 1300, 2400, 900 mm; internal partition wall 250 mm; external wall 400 mm (as marked 400); door D 900 × 2100, window W 2400 × 1500. Sections of 0.25 m wall and 0.40 m wall: foundation PCC (1:3:6) with flat brick soling, brickwork in (1:6) CM, 1:1 cement pointing, 100 thick PCC (1:3:6), 150 stone soling, rammed earth, P.C.C. (1:2:4) for RCC roof; wall height 3000 mm, sill 1500/2100 mm. Details approximate.]

Answer

Reading of the figure

Overall 7.9 m × 5.4 m: 0.40 + 3.45 + 0.25 + 3.40 + 0.40 = 7.90 m and 0.40 + 4.60 + 0.40 = 5.40 m. Room 1 (3.45 × 3.30 m) has the 1.30 m open verandah in front; Room 2 (3.40 × 4.60 m) is full depth. Walls: external 400 mm, partition 250 mm.

Centre-line lengths (400 mm walls): back 7.5 + right 5.0 + left 3.7 + Room 1 front 3.65 + Room 2 front 3.6 = 23.45 m; 250 mm partition = 4.60 m (clear, between back wall and Room 2 front wall).

Foundation assumed: PCC 1:3:6 0.30 m thick, projecting 0.30 m each side of the wall (so 1.00 m and 0.85 m wide), trench depth 0.90 m, one brick step 0.15 m high 0.1 m wider each side than the wall, then the wall to plinth (0.45 m above GL).

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, 400 mm walls (w = 1.0)123.4501.0000.90021.105
Trench, 250 mm wall (w = 0.85)14.6000.8500.9003.519
Total24.624

b) PCC (1:3:6) in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC 1:3:6, 400 mm walls123.4501.0000.3007.035
PCC 1:3:6, 250 mm wall14.6000.8500.3001.173
Total8.208

c) Brickwork in 1:6 CM up to plinth

Wall height from the step = 0.90 − 0.30 − 0.15 + 0.45 = 0.90 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
400 wall: brick step (0.6 × 0.15)123.4500.6000.1502.110
400 wall: wall to plinth123.4500.4000.9008.442
250 wall: brick step (0.45 × 0.15)14.6000.4500.1500.310
250 wall: wall to plinth14.6000.2500.9001.035
Total11.898

d) 1:4 plastering of ceiling

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Room 1: 3.45 × 3.3013.4503.300–11.385
Room 2: 3.40 × 4.6013.4004.600–15.640
Verandah soffit 4.10 × 1.3014.1001.300–5.330
Total32.355

Answer: Excavation 24.62 m³; PCC 8.21 m³; brickwork to plinth 11.90 m³; ceiling plaster 32.35 m².

  • 2076 Chaitra · 3+3+4 marks

Estimate the quantities of the following items of work from the accompanying drawing (Figure 1): (i) Earthwork excavation in foundation (ii) Wood work for doors and windows frame (iii) Two coats enamel painting over one coat primer in doors and windows. [Figure 1 not included in the scanned paper]

Answer

No drawing is given, so a one-room building is assumed: room 4.5 m × 3.5 m clear, 230 mm walls, centre-line length 16.92 m; trench 0.90 m × 1.00 m; one door 1.0 × 2.1 m (panelled); two glazed windows 1.2 × 1.2 m; frames 100 × 75 mm.

i) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)116.9200.9001.00015.228
Total15.228

ii) Wood work for door and window frames

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Door frame 2×2.1 + 1.015.2000.1000.0750.0390
Window frames 2 × (2×1.2 + 2×1.2)24.8000.1000.0750.0720
Total0.1110

iii) Two coats of enamel paint over one coat of primer

Painted area is measured over the frame and shutter on both sides and multiplied by a coefficient for the type of shutter. The multipliers below are typical textbook values (IS 1200 style; they differ slightly between books): panelled door 1.30 per side measured, glazed window 0.80.

  • Door: 1.0 × 2.1 × 2 sides × 1.30 = 5.46 m²
  • Windows: 2 × 1.2 × 1.2 × 2 sides × 0.80 = 4.61 m²
  • Total painted area = 10.07 m², which is taken for primer (1 coat) and enamel (2 coats).

Answer: Excavation 15.23 m³; timber frames 0.111 m³; painting 10.07 m² (assumed dimensions).

  • 2076 Asoj · 12 marks

Estimate the quantities of the following items of work from the accompanying building drawings: a) Earthwork in excavation in foundation b) Brick work in 2nd footing in foundation c) Wood work for doors and windows frame [Drawing not included in the scanned paper]

Answer

The drawing is not available, so a room 5.0 m × 3.5 m clear with 230 mm walls is assumed. Centre-line length = 2(5.0 + 3.5 + 0.46) = 17.92 m.

Foundation assumed: trench 0.90 m wide × 1.00 m deep, PCC 1:3:6 200 mm, first footing 0.69 m × 0.15 m, second footing 0.46 m × 0.15 m (a footing step projects 115 mm = quarter brick each side beyond the one above), then 230 mm wall. Openings: D 1.0 × 2.1 m (1 no.), W 1.2 × 1.2 m (2 nos.); frame 100 × 75 mm.

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)117.9200.9001.00016.128
Total16.128

b) Brickwork in second footing

The second footing is the upper step, 0.46 m wide:

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Second footing, 0.46 m wide117.9200.4600.1501.236
Total1.236

(If the lower, wider step is counted as the "second" footing in your drawing, its quantity is 1.85 m³, found the same way.)

c) Wood work for door and window frames

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Door frame 2×2.1 + 1.015.2000.1000.0750.0390
Window frames 2 × (2×1.2 + 2×1.2)24.8000.1000.0750.0720
Total0.1110

Answer: Excavation 16.13 m³; second-footing brickwork 1.24 m³; frame timber 0.111 m³ (assumed dimensions).

  • 2075 Chaitra · 4×3 marks

Prepare detailed estimate of the following items of work for a building from the attached Fig. 1. i) Earthwork in excavation in foundation ii) First class brick work in (1:4) cement mortar in foundation and plinth. iii) Wood work in door and window frame. [Fig. 1 not included in the scanned paper]

Answer

Fig. 1 is not available, so the method is worked on an assumed room 4.0 m × 3.6 m clear with 230 mm walls. Centre-line length = 2(4.0 + 3.6 + 2 × 0.23) = 16.12 m.

Assumed data

  • Trench 0.90 m × 1.00 m; PCC 1:3:6 200 mm; first class brick footings 0.69 m and 0.46 m wide (150 mm each); 230 mm wall to plinth (0.45 m above GL), wall height from the last step = 0.95 m.
  • Door D 1.0 × 2.1 (1 no.); windows W1 1.2 × 1.2 (1 no.), W2 1.0 × 1.2 (2 nos.); frames 100 × 75 mm.

i) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)116.1200.9001.00014.508
Total14.508

ii) First class brickwork (1:4) in foundation and plinth

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)116.1200.6900.1501.668
Brick footing step 2 (0.46 m wide)116.1200.4600.1501.112
Wall up to plinth116.1200.2300.9503.522
Total6.303

iii) Wood work in door and window frames

FrameNo.L (m)B (m)H/D (m)Qty (m³)
Door frame D (2×2.1 + 1.0)15.2000.1000.0750.0390
Window frame W1 (2×1.2 + 2×1.2)14.8000.1000.0750.0360
Window frame W2 (2×1.2 + 2×1.0)24.4000.1000.0750.0660
Total0.1410

Answer: Excavation 14.51 m³; brickwork 6.30 m³; timber for frames 0.141 m³ (assumed dimensions).

  • 2075 Asoj · 4×3 marks

Find the following quantities from the attached building drawing (Fig. 1): a) Brick work in 1:6 cement sand mortar up to plinth. b) 10 mm thick cement plastering in ceiling and underside of roof projection. c) PCC (1:3:6) in foundation. [Fig. 1: two-room building. Room A 3600 × 4800 mm and Room B 3600 × (about 3000) mm with doors D1, D2 and windows W1, W2 (sizes 1000/1500/1200 mm as marked); external walls 350 mm, partition 230 mm; roof slab with projection; foundation sections for 350 and 230 mm walls with footing, concrete and plinth; floor: 3 mm cement punning 1:4, 40 mm screed 1:4, 75 mm PCC 1:4:8, 150 mm sand filling, earth filling. The scan is rotated and hard to read.]

Answer

Reading of the figure (scan unclear, so assumptions are stated)

Room A is 3.6 × 4.8 m and Room B is 3.6 × 3.0 m (clear). External walls are 350 mm and the partition 230 mm. Overall length = 0.35 + 3.6 + 0.23 + 3.6 + 0.35 = 8.13 m. The roof slab is taken as a rectangle 8.13 m × 5.50 m with 0.60 m projection all round (assumed, since the projection is not stated).

Foundation sections (as for the matching drawing): external wall: trench 0.90 m wide × 0.90 m deep, concrete 0.15 m, footings 0.59 × 0.13 m and 0.47 × 0.13 m, then 0.35 m wall; internal wall: trench 0.75 m × 0.75 m, concrete 0.13 m, footings 0.47 × 0.13 and 0.35 × 0.13, then 0.23 m wall; plinth 0.45 m above GL.

Centre-line lengths: external walls = back 7.78 + left 5.15 + right 3.35 + front A 3.775 + front B 3.775 = 23.83 m; partition = 4.80 m.

a) Brickwork in 1:6 CM up to plinth

Wall heights: external = 0.90 − 0.15 − 0.13 − 0.13 + 0.45 = 0.94 m; internal = 0.75 − 0.13 − 0.13 − 0.13 + 0.45 = 0.81 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Ext. footing 1: 0.59 × 0.13123.8300.5900.1301.828
Ext. footing 2: 0.47 × 0.13123.8300.4700.1301.456
Ext. wall 0.35 × 0.94123.8300.3500.9407.840
Int. footing 1: 0.47 × 0.1314.8000.4700.1300.293
Int. footing 2: 0.35 × 0.1314.8000.3500.1300.218
Int. wall 0.23 × 0.8114.8000.2300.8100.894
Total12.530

b) 10 mm cement plaster in ceiling and underside of roof projection

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Room A ceiling 3.6 × 4.813.6004.800–17.280
Room B ceiling 3.6 × 3.013.6003.000–10.800
Soffit of slab outside walls: (8.13+1.2)×(5.50+1.2) − rooms − wall area124.986––24.986
Total53.067

c) PCC (1:3:6) in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC external walls (0.90 wide × 0.15)123.8300.9000.1503.217
PCC internal wall (0.75 wide × 0.13)14.8000.7500.1300.468
Total3.685

Answer: Brickwork to plinth 12.53 m³; ceiling and soffit plaster 53.07 m²; foundation PCC 3.69 m³.

  • 2074 Chaitra · 10+5+5 marks

A drawing of a building is attached herewith. Calculate the quantities of: i) Brickwork in cement mortar (1:6) up to plinth ii) 35 mm thick paneled door shutters. iii) 10 mm thick cement plaster in ceilings and underside of roof projection. [Two Room Building: all dimensions in mm, assume necessary dimensions. Plan: room A 3600 × 4800 and room B 3600 × 5500; external walls 350 mm, internal wall 230 mm; bay dimensions 1550, 1200, 2630, 1200, 1550 and 2000, 1500, 2000; front 1050, 1000, 700, 2630, 700, 1000, 1050. Foundation — external wall: depth 900, width 900, concrete depth 150; footings width and depth: 1st 590 and 130, 2nd 470 and 130, 3rd footing and plinth 350 thick; plinth height 450; sill height 750. Internal wall: depth 750, width 750, concrete depth 130; footings: 1st 470 and 130, 2nd 350 and 130, 3rd footing and plinth 230; plinth height 450; sill height 750. Steps: tread 300, riser 150, 100 th PCC. Roofs: RCC slab thickness 100, projection 600, parapet wall 110 thick, 300 high at the end of roof projection. Superstructure: floor to floor height 2700, external wall 350, internal wall 230. Openings: doors D 1200 × 2100, windows W1 1000 × 1000, W2 1200 × 1200, W3 1200 × 1200; frame size 75 × 100; doors and windows shutter 35 thick.]

Answer

Reading of the data

Along the front: 350 + 3600 + 230 + 3600 + 350 = 8130 mm (matches 1550 + 1200 + 2630 + 1200 + 1550 = 8130). Room A is 3.6 × 4.8 m, Room B 3.6 × 5.5 m. External walls 350 mm, internal 230 mm. Slab 100 mm with 600 mm projection, parapet 110 × 300 mm on the projection edge. Number of openings is not given, so 3 doors D (1.2 × 2.1 m) are assumed (two external, one in the partition); the windows are not needed for this question.

Foundation from the given data: external wall trench 900 wide × 900 deep, concrete 150 mm, footings 590 × 130 and 470 × 130, 350 mm wall to plinth (450 mm); internal wall trench 750 × 750, concrete 130 mm, footings 470 × 130 and 350 × 130, 230 mm wall to plinth.

Centre-line lengths: external walls = back 7.78 + left 5.15 + right 5.85 + fronts 7.55 = 26.33 m; partition (full depth of Room B) = 5.50 m.

i) Brickwork in cement mortar 1:6 up to plinth

External wall height = 0.90 − 0.15 − 0.13 − 0.13 + 0.45 = 0.94 m; internal = 0.75 − 0.13 − 0.13 − 0.13 + 0.45 = 0.81 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Ext. footing 1: 0.59 × 0.13126.3300.5900.1302.020
Ext. footing 2: 0.47 × 0.13126.3300.4700.1301.609
Ext. wall 0.35 × 0.94126.3300.3500.9408.663
Int. footing 1: 0.47 × 0.1315.5000.4700.1300.336
Int. footing 2: 0.35 × 0.1315.5000.3500.1300.250
Int. wall 0.23 × 0.8115.5000.2300.8101.025
Total13.902

ii) 35 mm thick panelled door shutters

Frame 75 × 100 mm, so each shutter is smaller than the 1.2 × 2.1 m opening by 75 mm on each vertical side and at the head.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Panelled shutter D 1.2×2.1 less frame (1.05 × 2.025), 3 nos.31.0502.025–6.379
Total6.379

iii) 10 mm plaster in ceilings and underside of roof projection

Slab = 9.33 × 7.40 m; the slab is taken as a full rectangle, so the soffit outside the walls includes the 600 mm projection and the open corner where one room is shorter than the other.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Room A ceiling 3.6 × 4.813.6004.800–17.280
Room B ceiling 3.6 × 5.513.6005.500–19.800
Soffit outside walls: (8.13+1.2)×(6.20+1.2) − rooms − walls121.482––21.482
Total58.562

Answer: Brickwork to plinth 13.90 m³; door shutters 6.38 m² (3 doors); ceiling and soffit plaster 58.56 m².

  • 2074 Asoj · 12 marks

Estimate the quantities of the following items of work from the accompanying Building drawings: a) Earthwork in excavation in foundation b) Panelled door shutter c) Brick work in foundation and plinth [Fig. 3: room 5 m × 4 m with 1.5 m wide verandah and 20 × 20 cm pillars; schedule: door D = 110 × 210 cm, window W = 90 × 150 cm, shelf S = 90 × 150 cm; part sectional elevation on ABCD and section XY: 7.5 L.C. over 10 R.C.C. slab, R.C.C. band lintel, D.P.C., 2.5 C.C. over 7.5 L.C., earth filling, heights 2.50, 2.80, 2.10, 3.60 m; steps tread 30, riser 15; foundation sections on main wall, dwarf wall and pillar with footing widths 45/70/80 cm. Dimensions in cm, details approximate.]

Answer

Reading of the figure

Room 5.0 × 4.0 m (clear), main walls 300 mm, with a 1.5 m verandah on the long side carried on three 20 × 20 cm pillars joined by a 200 mm dwarf wall. Assumed foundations (from the footing widths 45 / 70 / 80 cm marked): main wall PCC 0.80 m wide × 0.25 m, brick steps 0.70 m and 0.45 m wide (0.20 m high each), 300 mm wall; trench depth 0.90 m; dwarf wall trench 0.45 m × 0.75 m deep (PCC 0.20 m); pillar pit 0.70 × 0.70 × 0.90 m. Plinth 0.45 m above GL. Door D 1.10 × 2.10 m (1 no.) is the only door shown.

Centre-line of main walls = 2[(5.0 + 0.3) + (4.0 + 0.3)] = 19.20 m; dwarf wall = 5.3 − 3 × 0.20 = 4.70 m.

a) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Main walls trench 0.80 wide119.2000.8000.90013.824
Dwarf wall trench 0.45 wide × 0.75 deep14.7000.4500.7501.586
Pillar pits 0.70 × 0.70 × 0.90 (3 nos.)30.7000.7000.9001.323
Total16.733

b) Panelled door shutter

Frame assumed 75 mm.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Door shutter D (1.10−0.15) × (2.10−0.075), 1 no.10.9502.025–1.924
Total1.924

c) Brickwork in foundation and plinth

Main wall height above step 2 = 0.90 − 0.25 − 0.20 − 0.20 + 0.45 = 0.70 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Main wall step 1: 0.70 × 0.20119.2000.7000.2002.688
Main wall step 2: 0.45 × 0.20119.2000.4500.2001.728
Main wall 0.30 × 0.70 to plinth119.2000.3000.7004.032
Dwarf wall 0.20 thick: (0.75 − 0.20 + 0.45 = 1.00) high14.7000.2001.0000.940
Pillar footing step 0.60 × 0.60 × 0.2030.6000.6000.2000.216
Pillar base 0.23 × 0.23 × 0.90 to plinth30.2300.2300.9000.143
Total9.747

Answer: Excavation 16.73 m³; door shutter 1.92 m²; brickwork in foundation and plinth 9.75 m³ (assumed details).

  • 2073 Shrawan · 10 marks

Estimate the quantities of the following items of work from the accompanying BUILDING drawings. i) Lime concrete in foundation ii) Brick work in second footing iii) DOOR shutters iv) 25 mm thick DPC [Drawing not included in the scanned paper]

Answer

No drawing is given, so a typical room is assumed: 4.5 m × 3.0 m clear, 230 mm walls; centre-line length = 2(4.5 + 3.0 + 0.46) = 15.92 m. Foundation: trench 0.90 m wide; lime concrete 0.30 m thick; brick footings of 0.69 m (first) and 0.46 m (second), 0.15 m high each; DPC at plinth. Doors: D1 1.0 × 2.1 m, D2 0.9 × 2.1 m; two windows 1.2 × 1.2 m. Door frame 75 mm.

i) Lime concrete in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Lime concrete bed 0.90 wide × 0.30 thick115.9200.9000.3004.298
Total4.298

ii) Brickwork in second footing

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Second footing 0.46 × 0.15115.9200.4600.1501.098
Total1.098

iii) Door shutters

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Door D1 shutter (1.0−0.15)×(2.1−0.075)10.8502.025–1.721
Door D2 shutter (0.9−0.15)×(2.1−0.075)10.7502.025–1.519
Total3.240

iv) 25 mm thick DPC

Measured in m² (length of wall × thickness of wall), not across door openings.

ItemNo.L (m)B (m)H/D (m)Qty (m²)
DPC 25 mm, wall length115.9200.230–3.662
Deduct door openings (1.0 + 0.9)-11.9000.230–-0.437
Total3.225

Answer: Lime concrete 4.30 m³; second-footing brickwork 1.10 m³; door shutters 3.24 m²; DPC 3.22 m² (assumed dimensions).

  • 2073 Shrawan · 16 marks

Calculate the following items of work from the attached building drawing. i) Earthwork in excavation ii) Stone soling in foundation and sand filling in floor. iii) PCC for RCC up to plinth beam iv) Brick work up to plinth [Figure: plan 7.90 m × 4.10 m with two rooms 3.5 × 3.5 m, columns 0.30 × 0.30 m, door D 1.0 × 2.1 m, window 1.8 × 1.5 m; wall section 0.35, 0.30, 0.30 m with 0.45 m plinth, 10 cm PCC, 15 cm stone soling, 30 cm sand filling; column footing 0.90 × 0.90 m, footing depth 1.00 m, plinth beam 0.30 × 0.30 m, 10 cm PCC and 15 cm stone soling below footing. Dimensions in metre, not to scale.]

Answer

Reading of the figure

Plan 7.90 × 4.10 m = columns 0.30 m + room 3.5 m + column 0.30 m + room 3.5 m + column 0.30 m (and 3.5 + 0.3 + 0.3 across). Six columns 0.30 × 0.30 m on a 3.8 m grid; beams and infill walls form 7 panels of 3.5 m clear (4 along the long sides, 3 across). The sketch is approximate, so these assumptions are made: column footing 0.90 × 0.90 m, 0.30 m thick RCC on 10 cm PCC and 15 cm stone soling, bottom at 1.00 m below GL; 0.30 m thick brick wall panels in a 0.35 m wide trench 0.60 m deep (10 cm PCC + 15 cm soling at the bottom) up to the underside of the 0.30 × 0.30 m plinth beam; plinth top 0.45 m above GL.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Column footing pits 0.90 × 0.90 × 1.0060.9000.9001.0004.860
Wall trenches 0.35 wide × 0.60 deep (7 panels, 3.8 − 0.9 each)72.9000.3500.6004.263
Total9.123

ii) Stone soling in foundation and sand filling in floor

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Soling 15 cm under footings60.9000.9000.1500.729
Soling 15 cm under wall trenches72.9000.3500.1501.066
Total1.795
ItemNo.L (m)B (m)H/D (m)Qty (m³)
Sand filling 30 cm in two rooms 3.5 × 3.523.5003.5000.3007.350
Total7.350

Soling = 1.795 m³; sand filling = 7.35 m³.

iii) PCC (for RCC) up to plinth beam

Column height from footing top to plinth = 1.00 − 0.10 − 0.15 − 0.30 + 0.45 = 0.90 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Footings 0.90 × 0.90 × 0.3060.9000.9000.3001.458
Columns 0.30 × 0.30 × 0.90 (footing top to plinth)60.3000.3000.9000.486
Plinth beams 0.30 × 0.30, 3.5 m clear (7 panels)73.5000.3000.3002.205
Total4.149

iv) Brickwork up to plinth

Height below the beam = 0.60 − 0.10 − 0.15 + 0.45 − 0.30 = 0.50 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.30 thick × 0.50 m high, 7 panels of 3.5 m73.5000.3000.5003.675
Total3.675

Answer: Excavation 9.12 m³; soling 1.79 m³ and sand filling 7.35 m³; concrete for RCC 4.15 m³ (footings, columns, plinth beams); brickwork to plinth 3.67 m³.

  • 2071 Chaitra · 4×4 marks

Estimate detailed quantities for the following items from attached building drawing: i) Earth work in excavation in foundation ii) Brick work in cement sand (1:6) mortar up to plinth iii) 40 mm thick sal work wood paneled door shutter iv) 12 mm thick inside cement plaster (1:6) [Figure: single room building with front verandah. Room 4.00 m × 4.50 m (as marked), verandah 2.00 m wide, 30 × 30 cm pillars, 30 cm walls with window; door 100 × 200 cm, window 100 × 140 cm, shelf 100 × 170 cm; steps tread 30, rise 15, 1.40 m / 2.00 m wide; wall section: 7.5 cm L.C. over 10 cm R.B. slab, 3.50 m height, 2.80 m and 2.20 m, 2 cm D.P.C., 45 cm plinth, 80 cm foundation with L.C. 10-30 cm layers; verandah pillar foundation 70 × 70 cm L.C. Details approximate.]

Answer

Reading of the figure

Room 4.0 × 4.5 m clear, 300 mm walls, 2.0 m verandah in front carried on three 30 × 30 cm pillars (pillar footings 70 × 70 cm); door 1.00 × 2.00 m, window 1.00 × 1.40 m, shelf 1.00 × 1.70 m (a recess, plaster surface not deducted). Foundation taken as 0.80 m wide × 0.80 m deep: lime concrete 0.30 m, one brick step 0.60 m × 0.15 m, 300 mm wall; plinth 0.45 m; clear height 2.80 m.

Centre-line length = 2[(4.0 + 0.3) + (4.5 + 0.3)] = 18.20 m.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall trench 0.80 wide × 0.80 deep118.2000.8000.80011.648
Pillar pits 0.70 × 0.70 × 0.80 (3 nos.)30.7000.7000.8001.176
Total12.824

ii) Brickwork in 1:6 up to plinth

Wall height above the step = 0.80 − 0.30 − 0.15 + 0.45 = 0.80 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing 0.60 × 0.15118.2000.6000.1501.638
Wall 0.30 × 0.80 to plinth118.2000.3000.8004.368
Pillar brick step 0.50 × 0.50 × 0.1530.5000.5000.1500.112
Pillar 0.30 × 0.30 × (0.80−0.30−0.15+0.45)30.3000.3000.8000.216
Total6.335

iii) 40 mm thick sal wood panelled door shutter

Frame 100 mm at the sides and 50 mm at the head: shutter = (1.00 − 0.10) × (2.00 − 0.05) = 0.90 × 1.95 = 1.755 m² (1 no.).

iv) 12 mm inside cement plaster (1:6)

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside walls 2(4.0+4.5) × 2.80117.0002.800–47.600
Deduct door 1.0×2.0-11.0002.000–-2.000
Deduct window 1.0×1.4-11.0001.400–-1.400
Total44.200

Answer: Excavation 12.82 m³; brickwork to plinth 6.33 m³; door shutter 1.75 m²; inside plaster 44.20 m² (assumed details).

  • 2070 Chaitra · 5+4+5 marks

Prepare a detailed estimate of the following items of work of a building (drawing attached herewith) i) Earth work in excavation ii) PCC (1:3:6) in foundation iii) Brick work in 1:6 c.s mortar in foundation and plinth [Figure: two rooms 4.5 m × 3.6 m and 4.0 m × 3.6 m with front verandah 1.6 m, 20 × 20 cm pillars, steps 2.4 m wide tread 30 riser 15; door D 1.2 × 2.1 m (frame 10 × 8 cm), window W 1.1 × 1.5 m (frame 10 × 8 cm), shelf S 1.1 × 1.5 m 20 cm deep; walls 30 cm; foundation 90 cm wide with 20 cm layers, 60 cm; 2.5 cm D.P.C.; 15 cm R.C.C. band lintel; AV 10 cm L.C. (2:2:7) over 10 cm RCC slab; wall height 2.7 m, parapet 60 cm. Details approximate.]

Answer

Reading of the figure

Two rooms 4.5 × 3.6 m and 4.0 × 3.6 m (clear) side by side, 300 mm walls, 1.6 m front verandah on four 20 × 20 cm pillars. Foundation (as marked): 90 cm wide, 20 cm layers; assumed trench depth 0.80 m = PCC 1:3:6 0.20 m + brick step 0.60 m × 0.20 m + wall below GL 0.40 m; plinth 0.45 m above GL; pillar footing 0.90 × 0.90 m.

Outside length = 4.5 + 4.0 + 3 × 0.3 = 9.40 m; depth = 3.6 + 0.6 = 4.2 m. Centre-line of outer walls = 2[(9.40 − 0.3) + (4.2 − 0.3)] = 26.00 m; partition (clear) = 3.6 m; total = 29.60 m.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall trench 0.90 × 0.80 deep129.6000.9000.80021.312
Pillar pits 0.90 × 0.90 × 0.80 (4 nos.)40.9000.9000.8002.592
Total23.904

ii) PCC (1:3:6) in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC 1:3:6 under walls 0.90 × 0.20129.6000.9000.2005.328
PCC under pillars 0.90 × 0.90 × 0.2040.9000.9000.2000.648
Total5.976

iii) Brickwork in 1:6 c.s. mortar in foundation and plinth

Wall height above the step = 0.80 − 0.20 − 0.20 + 0.45 = 0.85 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing 0.60 × 0.20129.6000.6000.2003.552
Wall 0.30 × 0.85129.6000.3000.8507.548
Pillar footing step 0.60 × 0.60 × 0.2040.6000.6000.2000.288
Pillar 0.23 × 0.23 × (0.80−0.20−0.20+0.45)40.2300.2300.8500.180
Total11.568

Answer: Excavation 23.90 m³; PCC 5.98 m³; brickwork in foundation and plinth 11.57 m³ (assumed details).

  • 2068 Baisakh (old course) · 3+5+4+4 marks

Estimate the quantity of the following items of work from the accompanying building drawings: i) PCC (1:3:6) in foundation ii) Brick work in (1:6) cement mortar in foundation and plinth. iii) Salwood work for doors and windows frame iv) PCC M20 for R.C.C. slab [Drawing not included in the scanned paper]

Answer

No drawing is given. Assumed: room 4.0 m × 3.5 m clear, 230 mm walls, centre-line length 15.92 m; trench 0.90 m wide × 1.00 m deep; PCC 200 mm; brick steps 0.69 and 0.46 m wide (150 mm each); plinth 0.45 m above GL; door 1.0 × 2.1, two windows 1.2 × 1.2; frames 100 × 75 mm sal; RCC slab 125 mm thick with 0.45 m projection all round (M20).

i) PCC (1:3:6) in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC 1:3:6 under walls 0.90 × 0.20115.9200.9000.2002.866
Total2.866

ii) Brickwork (1:6) in foundation and plinth

Wall height from the last step = 0.95 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)115.9200.6900.1501.648
Brick footing step 2 (0.46 m wide)115.9200.4600.1501.098
Wall up to plinth115.9200.2300.9503.479
Total6.225

iii) Sal wood for door and window frames

FrameNo.L (m)B (m)H/D (m)Qty (m³)
Door frame D (2×2.1 + 1.0)15.2000.1000.0750.0390
Window frame W (2×1.2 + 2×1.2)24.8000.1000.0750.0720
Total0.1110

iv) PCC M20 for RCC slab

ItemNo.L (m)B (m)H/D (m)Qty (m³)
RCC slab 125 mm incl. 0.45 m projection: (4.0+0.46+0.90) × (3.5+0.46+0.90)15.3604.8600.1253.256
Total3.256

(Lintels, beams and reinforcement are measured separately.)

Answer: PCC 2.87 m³; brickwork 6.22 m³; sal wood frames 0.111 m³; M20 concrete in slab 3.26 m³.

  • 2067 Poush (old course) · 18 marks

Estimate the quantities of the following items of work from the accompanying drawing: a) Earth work in excavation in foundation b) Brick work in foundation and plinth c) Inside wall and ceiling cement plaster d) Brick work in superstructure [Drawing: plan 7230 mm × 3730 mm; 230 mm walls; two rooms with 3270 mm clear spans, 3500 mm bays; doors D 1200 × 2100, D1 1000 × 2100; windows W 1200 × 1200, W1 1200 × 1200; section X-X: roof slab with 18 screed over two layers of tarfelt, 600 mm projection, window 3270 wide, heights 2100/2400/1200/900, DPC, floor: 3 cement sand (1:1) pointing over 36 cement concrete (1:2:4), 75 thick brick bats soling, 150 sand filling; foundation 770 mm wide PCC (1:3:6) with footings, layers 150/250/150/150/80 mm.]

Answer

Reading of the drawing

Plan: two rooms 3.27 × 3.27 m clear with 230 mm walls (overall 7.23 × 3.73 m; the given 7230 × 3730). Centre-line = 2[(7.23 − 0.23) + (3.73 − 0.23)] = 21.00 m for the outer walls, plus the central partition 3.27 m, total 24.27 m.

Foundation section as marked: PCC 1:3:6 0.77 m wide × 0.15 m, brick step 0.69 × 0.25 m, brick step 0.46 × 0.15 m, 230 mm wall; assumed trench depth 0.80 m; plinth 0.45 m above GL (floor 150 mm sand, 75 mm brick soling, concrete, 1:1 pointing). Wall height 2.4 m above plinth with door D 1.2 × 2.1 (1), D1 1.0 × 2.1 (1, between rooms), W 1.2 × 1.2 (2), W1 1.2 × 1.2 (1). Plaster 12 mm.

a) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench (centre-line)124.2700.7700.80014.950
Total14.950

b) Brickwork in foundation and plinth

Wall height above step 2 = 0.80 − 0.15 − 0.25 − 0.15 + 0.45 = 0.70 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick step 0.69 × 0.25124.2700.6900.2504.187
Brick step 0.46 × 0.15124.2700.4600.1501.675
Wall 0.23 × 0.70 to plinth124.2700.2300.7003.907
Total9.769

c) Inside wall and ceiling cement plaster

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside walls 2 rooms × 2(3.27+3.27) × 2.4126.1602.400–62.784
Deduct D (one face)-11.2002.100–-2.520
Deduct D1 (both faces)-21.0002.100–-4.200
Deduct windows W 1.2×1.2 (2) and W1 (1)-31.2001.200–-4.320
Ceiling 2 rooms × 3.27 × 3.2723.2703.270–21.386
Total73.130

d) Brickwork in superstructure

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.23 × 2.4 above plinth124.2700.2302.40013.397
Deduct D 1.2×2.1-11.2000.2302.100-0.580
Deduct D1 1.0×2.1-11.0000.2302.100-0.483
Deduct W 1.2×1.2-21.2000.2301.200-0.662
Deduct W1 1.2×1.2-11.2000.2301.200-0.331
Total11.341

Answer: Excavation 14.95 m³; foundation and plinth brickwork 9.77 m³; plaster (walls and ceiling) 73.13 m²; superstructure brickwork 11.34 m³.

Questions from Old Question Collection (CE 705) (IOE exam papers from 2065 Shrawan to 2082 Bhadra (22 papers; 2065-2068 are the older Estimating and Valuation syllabus)). Answers are written for this site; check them against your class notes.

Chapter titles and hours from the IOE syllabus ↗