Skip to main content

Chapter 3 · 3 hours

Types of Estimate

IOE past exam questions

Past questions and answers

20 questions set from this chapter, 6 of them more than once; 4 are most repeated (set, or a close variant set, in 3 or more exams). Most repeated first.

  • Most repeated · 6 of 22 exams
  • Asked 6 times
  • 2076 Chaitra · 4 marks
  • 2070 Chaitra · 4+4 marks
  • 2080 Baisakh · 2 marks
  • 2081 Baisakh · 2 marks
  • 2068 Baisakh (old course) · 4 marks
  • 2066 Bhadra (old course) · 2 marks

What do you understand by approximate (preliminary) estimate? When and why is it prepared? Also write a short note on it.

Answer

Meaning

An approximate (preliminary) estimate is a rough estimate of the probable cost of a project, prepared quickly from the general requirements and past experience, without detailed drawings or item quantities.

When and why it is prepared

  1. At the planning stage, to decide whether the project is feasible and affordable.
  2. To obtain administrative approval and budget allocation from the ministry/municipality.
  3. To compare alternatives (sites, designs, types of structure).
  4. For funding and loan applications, and in the preparation of the annual programme.
  5. When there is no time or data for detailed estimation, as at the start of a design.

Short note

  • Methods: plinth area method, cubic content (cube) rate method, unit base (per bed, per student, per km, per cum of storage) method, approximate quantity method, and the cost of a similar building in the locality.
  • Data: area of the building, the prevailing plinth area rate, percentages for services and contingency.
  • Contents: cost of the civil works (plinth area x rate), special architectural treatment, water supply and sanitary, electrical works, external services, contingency and supervision charge.
  • Accuracy: about 10 to 15% from the final cost; it is not used for tendering.
  • It is followed by the detailed estimate after design is completed.
  • Most repeated · 4 of 22 exams
  • Asked 4 times
  • 2074 Asoj · 6 marks
  • 2076 Asoj · 6 marks
  • 2066 Bhadra (old course) · 5 marks
  • 2065 Shrawan (old course) · 5 marks

List the various types of estimates and describe the circumstances under which each (preliminary, detailed, revised, supplementary, complete) is prepared, with examples.

Answer

TypeMeaningCircumstances in which it is preparedExample
Preliminary (approximate) estimateRough cost from plinth area/unit rates, before designPlanning, feasibility and administrative approvalSchool of 600 students by plinth area rate
Detailed estimateItem-wise quantities with rates and abstractAfter design and drawings, for technical sanction and tenderDetailed estimate of a hospital building
Revised estimateNew estimate replacing the sanctioned oneThe sanctioned estimate is likely to be exceeded by more than the allowed limit (usually 5%) due to rate rise, design change or quantity changeEstimate of a bridge revised after deeper foundation was needed
Supplementary estimateEstimate for additional work not included earlierExtra work is needed during construction on an already-sanctioned projectAdding a boundary wall to a completed building
Complete estimateTotal cost of all components of a projectTo know the final overall cost including land, design, equipment and servicesComplete cost of a hospital with equipment
Annual repair and maintenance estimateYearly cost of repairsPreparing the yearly maintenance budgetMaintenance of a road section
Extension and improvement estimateCost of new additions and improvementWhen an existing structure is extendedExtra floor on a building

Circumstances (summary)

  • Preliminary: the approval stage when drawings are not ready.
  • Detailed: once drawings are available, before tendering; it is the basis of the contract.
  • Revised: when the original sanction is exceeded; it replaces the old estimate.
  • Supplementary: a new addition to a sanctioned work; the original remains valid.
  • Complete: where the project cost includes more than construction.
  • Most repeated · 4 of 22 exams
  • Asked 4 times
  • 2075 Chaitra · 2 marks
  • 2074 Chaitra · 5 marks
  • 2065 Shrawan (old course) · 2 marks
  • 2068 Baisakh (old course)

What do you mean by contingencies and work charged establishment?

Answer

Contingencies

Contingency is a lump-sum allowance (usually 3 to 5% of the estimated cost) added to the estimate to cover small, unforeseen expenses that cannot be foreseen at the time of estimating: small changes in quantity, minor extra items, errors and omissions, and temporary rise in costs. It is spent only with the sanction of the competent authority. It includes also items such as the cost of stationery, travelling and testing in some practice.

Work-charged establishment

Work-charged establishment means the temporary staff engaged for a specific work and paid from the cost of that work rather than from the regular office budget. These include supervisors, overseers, store keepers, watchmen (chowkidar), chainmen, mates and clerks employed for the project period. An allowance of about 1.5 to 2.5% of the estimated cost is added to the estimate for it. Such staff are released when the work ends.

  • Most repeated · 3 of 22 exams
  • Asked 3 times
  • 2079 Bhadra · 4 marks
  • 2074 Chaitra
  • 2066 Bhadra (old course) · 2 marks

Why and when should a revised estimate be prepared? Explain with an example.

Answer

A revised estimate is a fresh estimate prepared to replace the original sanctioned estimate when it is found that the original will be exceeded.

Why it is prepared

  • To bring the sanctioned amount in line with the actual probable cost, so that payment beyond the sanction does not occur.
  • To obtain approval for the changed cost before further expenditure.

When it is prepared

  1. The cost is likely to exceed the sanctioned estimate by more than the permitted limit (about 5%, as per the rule of the agency).
  2. Changes in rates of material or labour, or a new District Rate.
  3. Design changes or changes in the specification required by the site.
  4. Major variation in quantities, such as deeper or rock foundation.
  5. Cost of the work already done and the balance work have to be re-estimated after a long delay.

Example

A school building was sanctioned for Rs 20,000,000. During excavation, the soil was found weak and the foundation had to be deepened, adding Rs 2,000,000 (10%). As the increase exceeds the limit, a revised estimate of Rs 22,000,000 is prepared, giving the original items, extra items and the reason for each change, and sent for fresh approval.

  • Asked 2 times
  • 2071 Chaitra · 5 marks
  • 2067 Poush (old course) · 5 marks

Explain with example the process of preparation of a preliminary estimate of an office building. (Describe how you will prepare a preliminary estimate of a government office building for administrative approval, including external services.)

Answer

A preliminary estimate is prepared by the plinth area method, as follows. It is for the administrative approval, so the drawings are not yet detailed.

Steps

  1. Establish the requirement: the number of staff and rooms, and from these the total carpet area (usable floor area) from the norms for office space per person.
  2. Find the plinth (built-up) area:
Plinth area=Carpet area1−(circulation %+wall %)\text{Plinth area} = \frac{\text{Carpet area}}{1 - (\text{circulation \%} + \text{wall \%})}

The circulation area (corridors, verandah, stairs, toilets) is taken as 20 to 30% and walls as 8 to 10% of the plinth area. 3. Select the plinth area rate prevailing in the locality (or the DUDBC / department rate) for the type of building. 4. Building cost = plinth area x plinth area rate. 5. Add the extras as percentages of the building cost: special architectural treatment, water supply and sanitary works, electrical installation (and lift), deep foundation, and other services. 6. Add external services: compound wall, approach road, drainage, septic tank and landscaping. 7. Add contingency (3 to 5%) and supervision/departmental charge (3 to 8%). 8. Total is the estimate for approval.

Example (assumed)

Carpet area 1,000 m²; circulation 30% and walls 10%, so plinth area = 1000 / 0.6 = 1,666.67 m². Plinth area rate Rs 20,000 per m² gives a building cost of Rs 33.33 million. Electrical at 8% and other services at 5% add Rs 4.33 million. Contingency 5% and supervision 5% are then added on the total. The result, about Rs 41.4 million, is submitted for approval.

  • Asked 2 times
  • 2081 Baisakh · 5 marks
  • 2066 Bhadra (old course) · 7 marks

Prepare a preliminary estimate of a 4 storied office building having a total carpet area of 2000 m² for obtaining the administrative approval of the ministry. Given the following data:
  • 30% built up area will be taken up by corridors, verandah, toilets, staircase etc.
  • 10% of built-up area will be occupied by walls
  • Plinth area rate is Rs. 15000/m²
  • Extra for special architecture treatment 1.5% of the building cost
  • Extra for electric installation 8% of the building cost
  • Extra for other services 5% of the building cost
  • Contingencies 5% of the total building cost
  • Supervision charge 5% of the total building cost

Answer

Method

Plinth (built-up) area is found from the carpet area, as the carpet area is what remains after the circulation (30%) and wall (10%) areas are removed:

Plinth area=20001−0.30−0.10=20000.60=3333.33 m2\text{Plinth area} = \frac{2000}{1 - 0.30 - 0.10} = \frac{2000}{0.60} = 3333.33\ \text{m}^2

This is the total plinth area of all 4 floors (833.33 m² per floor).

Calculation

ItemBasisAmount (Rs)
Building cost3333.33 m² x 15,00050,000,000
Special architectural treatment1.5% of 50,000,000750,000
Electric installation8%4,000,000
Other services5%2,500,000
Total building cost57,250,000
Contingencies5% of 57,250,0002,862,500
Supervision charge5% of 57,250,0002,862,500
Total estimated cost62,975,000

Answer: Plinth area = 3333.33 m²; total estimated cost = Rs 62,975,000 (about Rs 6.30 crore).

Contingency and supervision are taken on the total building cost (Rs 57,250,000) as given in the question.

  • 2080 Baisakh · 2 marks

Why and when is a complete estimate prepared/used?

Answer

A complete estimate gives the total cost of a project, covering every cost needed to make it ready for use: land, building (civil) works, services, furniture and equipment, design and supervision, contingency and taxes.

Why it is prepared

  • To know the full financial commitment, not only the construction cost, so the owner or donor can sanction the money.
  • To avoid supplementary demands later, because nothing important is left out.
  • To compare the cost of the project with its benefit and to arrange the finance.

When it is prepared

  • At the project planning and approval stage, after the detailed estimates of the individual works are ready.
  • For large projects such as hospitals, hostels, dams and water supply schemes where land, equipment and external works are included.
  • When a loan or a grant is requested.
  • 2082 Bhadra · 2+4 marks

List the various types of estimates. Differentiate between revised estimate and supplementary estimate for a project.

Answer

Types of estimates

  1. Preliminary (approximate) estimate
  2. Detailed estimate
  3. Revised estimate
  4. Supplementary estimate
  5. Complete estimate
  6. Annual repair and maintenance estimate
  7. Extension and improvement estimate

Revised versus supplementary estimate

BasisRevised estimateSupplementary estimate
MeaningNew estimate that replaces the original sanctioned estimateAn additional estimate for extra work over the sanctioned one
ReasonOriginal cost will be exceeded (rate rise, design or quantity change)New work not in the original estimate is needed during construction
Effect on originalOriginal is cancelled and replacedOriginal remains valid; the new one is added to it
ScopeCovers the whole work (changed items and unchanged)Covers only the additional items
LimitUsually when cost exceeds the sanction by about 5%Prepared whenever extra work is required
ExampleFoundation deepened, cost rises, whole estimate redoneBoundary wall added to a building project
  • 2073 Shrawan · 6 marks

What are the different methods of preparing an approximate estimate? Write the suitability of each method.

Answer

MethodHow the cost is foundSuitability
1. Plinth area methodPlinth area x plinth area rate of a similar building, plus extras for servicesBuildings of similar type and finish; the commonest method for the preliminary estimate of offices, schools, hospitals
2. Cubic content (cube rate) methodVolume of the building (plinth area x height) x rate per m³Multi-storey buildings, where height differs; more accurate than plinth area
3. Unit base methodCost per unit of function, such as per bed (hospital), per student (school), per seat (hall), per km (road) x number of unitsQuick estimate of buildings and projects when the function is known
4. Approximate quantity (typical bay) methodQuantities of one typical bay/unit are found and multiplied; add the remaining partsBuildings with repeated bays or units, such as sheds and hostels
5. Cost of similar structureThe actual cost of a similar completed work, adjusted for time and placeSimple, when records of near-identical works are available
6. Cost per kilometre/lengthRate per km of road, canal or pipelineLinear projects (roads, canals, pipelines)

The accuracy is about 10 to 15%, best for the cube rate method, and the least for the unit base method. The estimate must be adjusted for the location, the year and the specification.

  • 2082 Bhadra · 6 marks

Prepare preliminary estimate of an office building having total carpet area of 3275 m². The area occupied by circulation area is 20% and area occupied by wall is 7%. Assume other data suitably, if needed.
  • Plinth area rate of building = Rs. 25,000 per m² (printed as m³)
  • Extra for deep foundation = 1.5% of civil cost
  • Extra for architectural work = 5% of civil cost
  • Extra for water supply work = 6% of civil cost
  • Extra for sanitary work = 5% of civil cost
  • Extra for electrical works = 8% of civil cost
  • Contingencies = 3%
  • Supervision charge = 8%

Answer

Plinth area

Carpet area is what remains after circulation (20%) and walls (7%) are taken from the plinth area:

Plinth area=32751−0.20−0.07=32750.73=4,486.30 m2\text{Plinth area} = \frac{3275}{1 - 0.20 - 0.07} = \frac{3275}{0.73} = 4,486.30\ \text{m}^2

Estimate

Plinth area rate = Rs 25,000 per m² (the paper prints m³, taken as m² because the rate is applied on the plinth area). Extras are taken on the civil cost; contingency and supervision on the total building cost, as the question says.

ItemBasisAmount (Rs)
Building cost (plinth area x rate)4,486.30 m² x 25,000112,157,534.25
Extra for deep foundation1.5% of civil cost1,682,363.01
Extra for architectural work5% of civil cost5,607,876.71
Extra for water supply6% of civil cost6,729,452.05
Extra for sanitary work5% of civil cost5,607,876.71
Extra for electrical work8% of civil cost8,972,602.74
Total building cost140,757,705.48
Contingencies3% of 140,757,7054,222,731.16
Supervision charge8% of 140,757,70511,260,616.44
Total estimated cost156,241,053.08

Answer: Plinth area = 4,486.30 m²; total estimated cost = Rs 156,241,053.08.

  • 2082 Baisakh · 7 marks

Prepare the preliminary estimate for the building project from the following data. Residential building of 4 stories having total carpet area of 500 m² and the wall is 8% of plinth area and that for circulation area occupied by passage, verandah, staircase, etc. is 10% of plinth area. The provision for architectural design is 10% of the civil cost, provision for water supply and sanitary are 6% of civil cost for each and for electrification is 8% of civil cost. The floor height of one flat of the building is 3 m and height of parapet wall on the top is 1.2 m. The rate of per cubic content is Rs. 5000 per m³. Assume suitable percentage contingencies and work charge establishment.

Answer

Assumptions

The total carpet area of 500 m² is for the whole four-storey building, and the plinth area is the same on each floor. Contingency is taken as 5% and work-charged establishment as 2.5% of the total building cost.

Plinth area and volume

Total plinth area=5001−0.08−0.10=609.76 m2\text{Total plinth area} = \frac{500}{1 - 0.08 - 0.10} = 609.76\ \text{m}^2

Plinth area per floor = 609.76 / 4 = 152.44 m².

Height of the building = 4 x 3.0 + 1.2 (parapet) = 13.2 m.

Volume=152.44×13.2=2,012.20 m3\text{Volume} = 152.44 \times 13.2 = 2,012.20\ \text{m}^3

Estimate

ItemBasisAmount (Rs)
Civil cost (volume x cube rate)2,012.20 m³ x 5,00010,060,975.61
Architectural design10% of civil cost1,006,097.56
Water supply6% of civil cost603,658.54
Sanitary work6% of civil cost603,658.54
Electrification8% of civil cost804,878.05
Total building cost13,079,268.29
Contingency (assumed)5% of 13,079,268653,963.41
Work-charged establishment (assumed)2.5% of 13,079,268326,981.71
Total estimated cost14,060,213.41

Answer: Volume = 2,012.20 m³; civil cost = Rs 10,060,975.61; total estimated cost = Rs 14,060,213.41.

  • 2081 Bhadra · 7 marks

Prepare the preliminary estimate for a school building for 600 students. The carpet area required per student is 1.2 m² and for office rooms is 50 sqm. If 20% of built up area of building is occupied by circulation area and 10% by walls. The provision for architectural treatment is 1% of civil cost, for water sanitary works is 5% of civil works and 6% of civil cost for electrification. If prevailing plinth area rate in the area is Rs 3400/sq. ft. Assume other data if necessary.

Answer

Carpet and plinth area

Carpet area of classes = 600 x 1.2 = 720 m²; add offices 50 m²; total carpet area = 770.00 m².

Plinth area=7701−0.20−0.10=1,100.00 m2\text{Plinth area} = \frac{770}{1 - 0.20 - 0.10} = 1,100.00\ \text{m}^2

Rate conversion

Plinth area rate = Rs 3,400 per sq. ft; 1 m² = 10.7639 sq. ft, so rate = 3,400 x 10.7639 = Rs 36,597.26 per m². (The rate is used as printed in the question, in sq. ft.)

Estimate

Contingency 5% and supervision/work-charged 3% are assumed, since the question leaves them open.

ItemBasisAmount (Rs)
Building cost (plinth area x rate)1,100.00 m² x 36,597.2640,256,986.00
Architectural treatment1% of civil cost402,569.86
Water supply and sanitary works5% of civil cost2,012,849.30
Electrification6% of civil cost2,415,419.16
Total building cost45,087,824.32
Contingency (assumed)5% of 45,087,8242,254,391.22
Supervision / work-charged (assumed)3% of 45,087,8241,352,634.73
Total estimated cost48,694,850.27

Answer: Plinth area = 1,100.00 m²; total estimated cost = Rs 48,694,850.27 (about Rs 4.87 crore).

  • 2080 Bhadra · 6 marks

Prepare a preliminary estimate of a poly-technique building for student number 800 in order to assess the amount for building based on the following particulars. Carpet area required per student = 1.2 sq.m. Area of corridors, verandah etc. = 20% of plinth area Plinth area rate = Rs. 3500 per square meters. Area of walls = 15% of plinth area. Cost of water supply work = 5% of building cost. Cost of sanitary = 7% of building cost. Cost of electrification = 12% of building cost. Cost of approach road and boundary walls = 3% of building cost. Contingencies and work charge establishments shall be 5% and 2.5% of the total cost respectively.

Answer

Plinth area

Carpet area = 800 x 1.2 = 960 m².

Plinth area=9601−0.20−0.15=9600.65=1,476.92 m2\text{Plinth area} = \frac{960}{1 - 0.20 - 0.15} = \frac{960}{0.65} = 1,476.92\ \text{m}^2

Estimate

Extras are percentages of the building cost; contingency and work-charged establishment are on the total cost (building plus extras).

ItemBasisAmount (Rs)
Building cost (plinth area x rate)1,476.92 m² x 3,5005,169,230.77
Water supply work5% of civil cost258,461.54
Sanitary work7% of civil cost361,846.15
Electrification12% of civil cost620,307.69
Approach road and boundary walls3% of civil cost155,076.92
Total building cost6,564,923.08
Contingencies5% of 6,564,923328,246.15
Work-charged establishment2.5% of 6,564,923164,123.08
Total estimated cost7,057,292.31

Answer: Total estimated cost = Rs 7,057,292.31.

  • 2079 Bhadra · 6 marks

Prepare a preliminary estimate of a building having a total carpet area of 2000 m² for obtaining the administrative approval of the ministry. Given the following data:
  • 30% built up area will be taken up by circulation space
  • 10% built up area is occupied by walls
  • Plinth area rate is Rs 20000.00 /sqm
  • Interior design will take 1% of the building cost
  • Other extra services will cost 5% of the building cost
  • Take supervision charge as 3%

Answer

Plinth area

Plinth area=20001−0.30−0.10=3,333.33 m2\text{Plinth area} = \frac{2000}{1 - 0.30 - 0.10} = 3,333.33\ \text{m}^2

Estimate

No contingency is given; 5% is assumed (usual practice). Supervision is 3% as given.

ItemBasisAmount (Rs)
Building cost (plinth area x rate)3,333.33 m² x 20,00066,666,666.67
Interior design1% of civil cost666,666.67
Other extra services5% of civil cost3,333,333.33
Total building cost70,666,666.67
Contingency (assumed)5% of 70,666,6673,533,333.33
Supervision charge3% of 70,666,6672,120,000.00
Total estimated cost76,320,000.00

Answer: Plinth area = 3,333.33 m²; total estimated cost = Rs 76,320,000.00.

  • 2078 Bhadra · 5 marks

Prepare a preliminary estimate of the four storied office building having carpet area of 250 m² per story. The height of each story is 3.5 m and on the roof floor there is parapet wall of 0.90 m height. The cube rate of the building in that locality is Rs. 250/cu.m. Take 10% built up area is covered by walls and 35% by circulation purposes. Assume other necessary suitable provisions.

Answer

Plinth area and volume

Total carpet area = 4 x 250 = 1000 m².

Total plinth area=10001−0.10−0.35=1,818.18 m2\text{Total plinth area} = \frac{1000}{1 - 0.10 - 0.35} = 1,818.18\ \text{m}^2

Plinth area per storey = 1,818.18 / 4 = 454.55 m².

Height = 4 x 3.5 + 0.90 (parapet) = 14.9 m, so volume = 454.55 x 14.9 = 6,772.73 m³.

Estimate

The cube rate is used as printed (Rs 250/m³). The provisions for architecture 1%, water supply 6%, sanitary 6%, electrification 8%, contingency 5% and supervision 3% are assumed.

ItemBasisAmount (Rs)
Civil cost (volume x cube rate)6,772.73 m³ x 2501,693,181.82
Architectural treatment (assumed)1% of civil cost16,931.82
Water supply (assumed)6% of civil cost101,590.91
Sanitary work (assumed)6% of civil cost101,590.91
Electrification (assumed)8% of civil cost135,454.55
Total building cost2,048,750.00
Contingency (assumed)5% of 2,048,750102,437.50
Supervision charge (assumed)3% of 2,048,75061,462.50
Total estimated cost2,212,650.00

Answer: Volume = 6,772.73 m³; total estimated cost = Rs 2,212,650.00. If the rate is in fact Rs 2,500/m³, every amount is ten times larger.

  • 2076 Chaitra · 4 marks

Prepare a preliminary estimate of a six storied framed structure office building having a total carpet area 3000.00 m². (i) Area for circulation is 20% of plinth area. (ii) Area for wall and column is 10% of plinth area. (iii) Prevailing plinth area rate per m² is Rs. 25000.00. (iv) Extra cost for other services 25% of the cost of building.

Answer

Plinth area

Plinth area=30001−0.20−0.10=30000.70=4,285.71 m2\text{Plinth area} = \frac{3000}{1 - 0.20 - 0.10} = \frac{3000}{0.70} = 4,285.71\ \text{m}^2

(total over the six floors; 714.29 m² per floor.)

Estimate

ItemBasisAmount (Rs)
Cost of building4,285.71 x 25,000107,142,857.14
Other services25% of the building cost26,785,714.29
Total133,928,571.43

Answer: Total estimated cost = Rs 133,928,571.43 (about Rs 13.39 crore). No contingency is given in the question; if required it is added on this total.

  • 2076 Asoj · 5 marks

Prepare a preliminary estimate of a five storied office building having total carpet area of 2500 m² for obtaining the administrative approval of the government, given the following data: (i) 30% of the built-up area will be taken up by corridors, verandah, staircase, lift etc and 10% of the built up area will be occupied by walls. (ii) Prevailing plinth area rate Rs. 25000.00 per m². (iii) Provide 20% extra cost for water supply and sanitary fittings, electrical works, contingencies and other services.

Answer

Plinth area

Plinth area=25001−0.30−0.10=4,166.67 m2\text{Plinth area} = \frac{2500}{1 - 0.30 - 0.10} = 4,166.67\ \text{m}^2

(total of five floors; 833.33 m² per floor.)

Estimate

ItemBasisAmount (Rs)
Cost of building4,166.67 x 25,000104,166,666.67
Water supply, sanitary, electrical, contingency and other services20% of building cost20,833,333.33
Total125,000,000.00

Answer: Total estimated cost = Rs 125,000,000.00 (Rs 12.5 crore).

  • 2075 Chaitra · 4 marks

The plinth area of an apartment is 500 Sq.m. Determine the total cost of building from the following data: i) Rate of construction = Rs. 3450 per m³ ii) The height of apartment = 16.25 m iii) Water supply, sanitary and electrical installations each at 6% of building cost iv) Architectural appearance @ 1% of building cost v) Unforeseen item @ 2% of building cost vi) P.S and contingencies @ 4% of building cost

Answer

Volume and building cost

Plinth area = 500 m², height = 16.25 m.

Volume=500×16.25=8,125.00 m3\text{Volume} = 500 \times 16.25 = 8,125.00\ \text{m}^3

Cost of building = 8,125.00 x 3,450 = Rs 28,031,250.00.

Additional items (percentages of building cost)

ItemPercentageAmount (Rs)
Water supply6%1,681,875.00
Sanitary installation6%1,681,875.00
Electrical installation6%1,681,875.00
Architectural appearance1%280,312.50
Unforeseen items2%560,625.00
P.S. and contingencies4%1,121,250.00
Total additions25%7,007,812.50

Answer: Total cost = 28,031,250.00 + 7,007,812.50 = Rs 35,039,062.50.

  • 2067 Asar (old course) · 6 marks

Prepare a preliminary estimate of a two storied health post building to get administrative approval of Ministry. Data are given as below. 30% built up area is occupied by circulation space. [10% built up area is occupied by walls - struck out in the paper] Plinth area rate is Rs. 18000.00/sq.m. Extra cost for interior design 1% of building cost. Extra cost for electrical installation 8% of building cost. Extra cost for other service 5% of building cost. Contingency = 5% Supervision charge = 3%

Answer

Assumptions

The question does not give the carpet area (and the wall percentage is struck out in the paper). I take an assumed total carpet area of 400 m² for the two floors (200 m² each), and the wall area as 10% of the built-up area, as in similar questions. The method is the same for any other carpet area CC: plinth area =C/0.60= C/0.60.

Plinth area

Plinth area=4001−0.30−0.10=666.67 m2\text{Plinth area} = \frac{400}{1 - 0.30 - 0.10} = 666.67\ \text{m}^2

Estimate

ItemBasisAmount (Rs)
Building cost (plinth area x rate)666.67 m² x 18,00012,000,000.00
Interior design1% of civil cost120,000.00
Electrical installation8% of civil cost960,000.00
Other services5% of civil cost600,000.00
Total building cost13,680,000.00
Contingency5% of 13,680,000684,000.00
Supervision charge3% of 13,680,000410,400.00
Total estimated cost14,774,400.00

Answer: Plinth area = 666.67 m²; total estimated cost = Rs 14,774,400.00 for the assumed 400 m² carpet area. (Cost = 1.14 x 1.08 x 18,000 x C/0.60 = Rs 36,936 per m² of carpet area.)

  • 2065 Shrawan (old course) · 7 marks

Prepare a preliminary estimate of a two storied VDC's office building to get administrative approval of district development committee having carpet area 500 m². 30% of the built up area is occupied by circulation element and 10% of built up area is occupied by walls. Plinth area rate for civil work is Rs. 10,000 per m². Cost of water supply, sanitary and electrification is 15% of civil cost. Cost of other services is 10% of civil cost. Departmental charge 8% of total cost.

Answer

Plinth area

Plinth area=5001−0.30−0.10=833.33 m2\text{Plinth area} = \frac{500}{1 - 0.30 - 0.10} = 833.33\ \text{m}^2

(for the two floors together; 416.67 m² per floor.)

Estimate

ItemBasisAmount (Rs)
Civil cost833.33 x 10,0008,333,333.33
Water supply, sanitary and electrification15% of civil cost1,250,000.00
Other services10% of civil cost833,333.33
Total cost10,416,666.67
Departmental charge8% of total cost833,333.33
Total estimated cost11,250,000.00

Answer: Total estimated cost = Rs 11,250,000.00.

Questions from Old Question Collection (CE 705) (IOE exam papers from 2065 Shrawan to 2082 Bhadra (22 papers; 2065-2068 are the older Estimating and Valuation syllabus)). Answers are written for this site; check them against your class notes.

Chapter titles and hours from the IOE syllabus ↗