Skip to main content

Chapter 1 · 3 hours

Introduction

IOE past exam questions

Past questions and answers

18 questions set from this chapter, 2 of them more than once; 2 are most repeated (set, or a close variant set, in 3 or more exams). Most repeated first.

  • Most repeated · 6 of 22 exams
  • Asked 6 times
  • 2082 Bhadra · 1+1+4 marks
  • 2076 Asoj · 1+3+2 marks
  • 2075 Chaitra · 3+3 marks
  • 2073 Shrawan · 2+2+2 marks
  • 2070 Chaitra · 3+5 marks
  • 2065 Shrawan (old course) · 5 marks

What is estimating? Why should an estimate be prepared before construction work? Describe the data required for the preparation of an estimate.

Answer

What is estimating?

Estimating is the process of calculating, in advance, the quantities of the various items of work and the likely cost of a project from its drawings, specifications and current rates. The result, the estimate, is the expected cost before the work is done.

Why an estimate is prepared before construction

  1. To know the probable cost, so the client can decide whether the project is affordable and worth doing.
  2. To obtain administrative and financial approval and a budget. In Nepal, public work cannot start without an approved estimate and budget allocation (Public Procurement Act and Regulation).
  3. To fix the cost estimate for tendering; bids are compared against it, and it helps judge abnormally low or high bids.
  4. To prepare the bill of quantities and the quantities of materials, so purchase and storage can be planned.
  5. To estimate the labour, equipment and time required, and prepare the work programme.
  6. To control cost during the work and compare with the actual expenditure.
  7. To decide the payment and fund flow, and to compare design alternatives.

Data required for an estimate

  • Drawings: plans, elevations, sections, foundation and structural details, and schedules of doors, windows and finishes. Without complete drawings, quantities cannot be taken out.
  • Specifications: the quality of materials and workmanship (for example cement mortar 1:4, M20 concrete, Fe 500 steel), so that the correct rate can be applied.
  • Rates: the District Rate (published yearly by the District Rate Fixation Committee), the DUDBC norms for labour and material consumption, and local market rates for items not covered. Rates of materials, labour, transport (lead), and the contractor's overhead and profit are needed.
  • Site data: site conditions, soil type, water table, distance of material sources (lead), and access.
  • Quantities: the work quantities taken out item by item, using the units of IS 1200 / the Nepal standard methods of measurement.
  • Other data: the applicable taxes (VAT 13%), contingency, price-adjustment and the contract conditions.
  • Most repeated · 4 of 22 exams
  • Asked 4 times
  • 2075 Asoj · 4 marks
  • 2074 Asoj · 4 marks
  • 2076 Chaitra · 3 marks
  • 2080 Bhadra · 2 marks

Mention the various purposes of estimating and costing.

Answer

Estimating and costing means finding the quantities and the probable cost of work before it is done. Its main purposes are:

  1. Probable cost: to know the total money needed, so the owner can decide on the project.
  2. Approval and budget: administrative and financial sanction, and fund allocation, are given on the basis of the estimate.
  3. Tendering: the engineer's estimate is the basis for inviting bids and for judging the reasonableness of the bids received.
  4. Material, labour and equipment planning: quantities from the estimate give the materials to be ordered and the manpower and machines required.
  5. Time scheduling: with the quantities and the productivity, the construction period and the programme are fixed.
  6. Cost control: actual expenditure is compared with the estimate, so overspending is noticed in time.
  7. Contract payment: the BOQ rates are used for interim payments and for valuing variations.
  8. Comparison of alternatives: different designs or materials can be compared on cost.
  9. Loan and cash-flow planning: banks and donors need a reliable cost figure.
  • 2082 Baisakh · 4 marks

Why is estimating done before execution of a project? Explain in the context of a water supply project to be undertaken by a local municipal authority.

Answer

An estimate is prepared before execution because no project can be approved, financed, tendered or managed without knowing its probable cost, quantities and time. For a municipal water supply project it matters for the following reasons.

  1. Approval and budget: the municipal council must approve the programme and allocate funds (from its own revenue, provincial or federal grants, or a loan). The estimate gives the figure for the annual programme and budget.
  2. Feasibility and choice of option: the estimate for the source, intake, transmission main, reservoir and distribution network allows comparing gravity versus pumping, or pipe materials (HDPE, GI, DI), and selecting the economical one.
  3. Tendering: the engineer's estimate is the reference for tender evaluation under the Public Procurement Act, 2063. Bids much below or above it are examined.
  4. Quantities of materials: pipes, fittings, valves, cement, steel and so on can be listed and procured in time, since pipes often have long delivery times.
  5. Manpower, equipment and time: trenching, pipe laying and tank construction need planned labour and machines and a realistic schedule.
  6. Cost sharing and tariff: the user committee's contribution and the water tariff are fixed from the capital cost.
  7. Cost control: after award, progress payments and variations are checked against the estimate.
  • 2080 Bhadra · 3 marks

Estimated cost is never equal to the actual cost of a project. Give your opinion.

Answer

I agree. The estimated cost is a forecast made before the work, from drawings and current rates. The actual cost is what is really spent when the work is finished. The two are almost never equal because an estimate rests on assumptions that change in practice.

Reasons:

  • Change in rates: prices of cement, steel, fuel and wages rise or fall between the estimate and construction (price escalation).
  • Quantity changes: variations in design, site conditions (for example rock found in excavation, or a different soil) change the quantities actually executed.
  • Measurement and calculation allowances: estimates use standard norms and wastage allowances, but real wastage and productivity differ.
  • Unforeseen events: floods, landslides, strikes, delays, shortage of materials, or the need for extra safeguards.
  • Variation orders and additional work requested by the owner.
  • Human and approximation errors in taking out quantities, and omitted items.

Estimates carry contingency (usually 3 to 5%) for such uncertainty. A careful estimate can come close to the actual cost, but exact equality is a matter of chance. Therefore the actual cost is controlled by revised or supplementary estimates when the difference becomes large.

  • 2081 Baisakh · 3 marks

Compare estimated cost and actual cost.

Answer

BasisEstimated costActual cost
MeaningProbable cost calculated before the workCost really spent after completion
TimePrepared before executionKnown during/after execution
BasisDrawings, specifications, norms, prevailing ratesBills, vouchers, measurement book, final account
NatureForecast, approximateFixed, final
AccuracyDepends on data and judgementExact
UsesApproval, budget, tender comparisonPayment, cost record, comparison with estimate
VariationMay be revised or supplementedCannot be changed
IncludesContingency allowanceContingency only if actually used

The estimated cost is normally close to the actual cost only when the design is complete and the rates and site conditions do not change.

  • 2078 Bhadra · 3+2 marks

Explain that estimated cost is never the actual cost. What are the data required for estimating?

Answer

Estimated cost is never the actual cost

Estimated cost is a forecast made before the work. Actual cost is only known when the work ends. They differ because:

  • rates of materials, labour and fuel change with time;
  • site conditions (soil, water table, access) differ from those assumed, changing quantities;
  • design changes, variation orders and extra items appear;
  • wastage, productivity and supervision differ from norms;
  • unforeseen events (weather, strikes, delays) add cost;
  • measurement and approximation errors exist in the estimate.

A contingency of 3 to 5% is added to cover this, but exact equality is not expected.

Data required for estimating

  • Drawings: plans, elevations, sections, foundation and structural details, and schedules of doors, windows and finishes. Without complete drawings, quantities cannot be taken out.
  • Specifications: the quality of materials and workmanship (for example cement mortar 1:4, M20 concrete, Fe 500 steel), so that the correct rate can be applied.
  • Rates: the District Rate (published yearly by the District Rate Fixation Committee), the DUDBC norms for labour and material consumption, and local market rates for items not covered. Rates of materials, labour, transport (lead), and the contractor's overhead and profit are needed.
  • Site data: site conditions, soil type, water table, distance of material sources (lead), and access.
  • Quantities: the work quantities taken out item by item, using the units of IS 1200 / the Nepal standard methods of measurement.
  • Other data: the applicable taxes (VAT 13%), contingency, price-adjustment and the contract conditions.
  • 2066 Bhadra (old course) · 5 marks

What are the purposes of estimating? 'An estimate is never the actual cost of the work', justify your answer.

Answer

Purposes of estimating

  1. To know the probable cost of the project and decide on its feasibility.
  2. To obtain technical, administrative and financial approval and budget allocation.
  3. To prepare tender documents, the engineer's estimate and the bill of quantities.
  4. To plan the materials, labour and equipment needed, and the work schedule.
  5. To fix the period of completion and the cash flow.
  6. To control cost by comparing actual expenditure with the estimate.
  7. To determine the rate and payment for variations, and compare design alternatives.

An estimate is never the actual cost

An estimate is a forecast prepared on the assumption of the present rates, the drawn quantities and standard norms. In real work these assumptions change:

  • Rate variation: market prices and wages change from the time of the estimate; the District Rate itself is revised every year.
  • Quantity variation: unforeseen site conditions (rock, loose soil, water) and design modifications change the executed quantities.
  • Productivity and wastage: actual consumption of materials and labour differs from norms.
  • Unforeseen events: delay, weather, strikes, shortage of material.
  • Errors and approximations in measurement, and the limited accuracy of preliminary estimates.

Hence, an allowance for contingency is made, and when the difference becomes large a revised or supplementary estimate is prepared. The estimate is therefore a guide for decision and control, not an exact record of cost.

  • 2067 Asar (old course) · 3 marks

What is an estimate? What is meant by quantity survey? Distinguish between estimated and actual cost.

Answer

Estimate

An estimate is the calculation of the probable quantities and cost of a work before construction, based on the drawings, specifications and current rates.

Quantity survey

Quantity survey (quantity surveying) is the process of measuring and calculating the quantities of the different items of work and materials from the drawings, and arranging them in a bill of quantities. It is the first step of estimating. It is also used later to measure the completed work for payment.

Estimated cost versus actual cost

Estimated costActual cost
Probable cost calculated before executionReal cost incurred after execution
Based on drawings, norms and current ratesBased on bills, vouchers and measurements
Approximate; has contingencyExact and final
Used for approval, budget, tenderingUsed for final payment and records
Can be revised before or during workCannot be changed
  • 2081 Bhadra · 3 marks

List out the data required for the detailed estimate of any construction project.

Answer

The data required for a detailed estimate are:

  1. Drawings: plans, elevations, sections, foundation and structural details, and door, window and finishing schedules, with dimensions.
  2. Specifications: the quality and standard of materials and workmanship of each item (mix proportions, grade of concrete and steel, brick class, finish).
  3. Rates: District Rates, the DUDBC norms (consumption of materials and labour per unit of work), and the rate analysis of each item, including transport (lead) and overhead.
  4. Quantities: item-wise measurements, taken out by a standard method (long wall-short wall or centre line) with units as per IS 1200 / Nepal practice.
  5. Site information: soil condition, water table, location of material sources and lead, availability of labour and water.
  6. Provisions and taxes: contingency, work-charged establishment, VAT (13%), and price adjustment as applicable.
  7. Time and contract conditions: the construction period and the conditions that affect the cost.
  • 2076 Chaitra · 3 marks

List out the principle of units of measurement. Explain the data required for preparing a detailed estimate.

Answer

Principles of units of measurement

Every item of work is measured and paid in one unit, chosen by the nature of the work, as per IS 1200 and the Nepal standard practice:

  1. Work in one dimension (length governs, section fixed) is measured in running metre (m): e.g. cornice, skirting, pipes, railing.
  2. Work in two dimensions (thickness fixed) is measured in square metre (m²): plastering, flooring, painting, formwork, half-brick wall.
  3. Work in three dimensions is measured in cubic metre (m³): excavation, concrete, brickwork, masonry.
  4. Small, countable items are measured in numbers (nos.): doors, fixtures, W.C.
  5. Items sold by weight are measured in kg, quintal or tonne: reinforcement, structural steel.
  6. Items that cannot be measured are paid as lump sum (L.S.).
  7. Measurement is of the net finished quantity in place; deductions are made for openings and voids as per the rules; dimensions are taken to two decimal places (mm precision for areas); the unit of measurement is the same as the unit of payment.
  8. The description includes all work, materials and incidental labour necessary to complete that unit.

Data required for a detailed estimate

  1. Complete drawings (plans, sections, elevations, details).
  2. Specifications of materials and workmanship.
  3. Rates: District Rate and DUDBC norms for rate analysis.
  4. Site data: soil, lead, water, labour availability.
  5. Item-wise quantity calculation, then abstract of cost.
  6. Contingency, taxes and overhead provisions.
  • 2080 Baisakh · 2+3 marks

What is estimating and costing? Explain the principle of units.

Answer

Estimating and costing

Estimating is calculating the quantities of the items of work and the materials required, from drawings and specifications. Costing is finding the cost of these quantities by multiplying them with the proper rates (rate analysis), and adding overhead, profit, contingency and taxes. Together they give the probable cost of a project before construction.

Principle of units

Each item of work is measured in the unit that suits its geometry, and that same unit is used for payment:

  • Length (m): cornice, skirting, railing, pipes, drains.
  • Area (m²): plastering, flooring, painting, formwork, roofing sheets.
  • Volume (m³): excavation, concrete, brick and stone masonry, filling.
  • Number (nos./set): doors, windows, W.C., lighting points.
  • Weight (kg/tonne): reinforcement, structural steel.
  • Lump sum: items that cannot be measured.

The measurement is of the net work in place; the description of the item covers materials, labour and tools included in the rate.

  • 2082 Baisakh · 2 marks

Write down the unit of measurement and payment of the given items of works: i) Flooring works ii) Skirting iii) Railing works iv) Half brick walls.

Answer

ItemUnit of measurementUnit of paymentRemarks
i) Flooringm²m²Length x width of net floor area, thickness and type stated
ii) Skirtingm (running metre)mHeight and thickness specified; measured along the wall, deducting door openings
iii) Railingm (running metre)mMeasured along the centre line of the top rail, with height and pattern given
iv) Half-brick wallm²m²Thickness 115 mm; the area deducts openings larger than the limit in the rules

In some DUDBC items skirting is also paid per m² by area of the finished strip; the unit stated in the item description governs.

  • 2081 Bhadra · 2 marks

Write down the unit of measurement and payment of the given items of works: i) Iron grills ii) Skirting iii) Formworks iv) Door window shutters.

Answer

ItemUnit of measurementUnit of payment
i) Iron grillsm² of the grill area (frame included) or kg by weightm² or kg, as per the item description
ii) Skirtingm (running metre), height and thickness specifiedm
iii) Formworkm² of the concrete surface in contact with the formm²
iv) Door and window shuttersm² of shutter area, thickness specifiedm²

The measurement of the shutters is taken over the frame opening (rebate included), and the frames are measured separately in m³ or running metre.

  • 2081 Baisakh · 2 marks

Write down the unit of measurement and unit of payment for the following items of works: i) R.C. sunshade with specified width and height ii) Thickness specified shutter of doors and windows iii) Iron grills iv) Asbestos cement sheet in roofs.

Answer

ItemUnit of measurementUnit of payment
i) R.C. sunshade (chajja) with width and thickness specifiedm³ of concrete; formwork in m² and steel in kg, separately (or m² of plan area if a combined rate is given)m³ / m² / kg
ii) Shutters of doors and windows, thickness specifiedm² of shutterm²
iii) Iron grillsm² of area (or kg by weight)m² or kg
iv) Asbestos cement (AC) / CGI sheet in roofsm² of the covered roof area, net, with overlaps not measuredm²

Note: in new work, asbestos-cement sheets have largely been replaced by CGI or colour-coated sheets, but the unit remains m².

  • 2074 Asoj · 4 marks

Write the units of measurement and payment for the following items of work: (i) Surface excavation (ii) Brick work in well steining (iii) Lightening conductor (iv) Cornice.

Answer

ItemUnit of measurementUnit of paymentNotes
(i) Surface excavationm³ for bulk excavation of the area to the depth specified (m² for surface dressing up to 150 mm)m³ (or m²)Length x width x average depth, in the soil type stated
(ii) Brick work in well steiningm³m³Mean circumference x thickness x height, or the ring volume pi x (D² - d²)/4 x height
(iii) Lightning conductorset (number) for the complete installation; extra length of conductor strip in mno. / setIncludes the air terminal, down conductor and earth pit
(iv) Cornicem (running metre), profile and girth givenmMeasured along the centre line of the cornice
  • 2068 Baisakh (old course) · 3 marks

How are the following items of work measured? What are their units of measurement and payment? (i) Pointing work (ii) Steel reinforcement.

Answer

(i) Pointing work

  • Measurement: the exposed face of the masonry joints is measured as a surface area, length x height, after deducting openings (as per the rules, deduct openings above the limit; add reveals where pointed).
  • Unit of measurement and payment: m². The type of pointing (flush, ruled, struck, weathered), the mortar mix and the wall type are stated in the item.

(ii) Steel reinforcement

  • Measurement: the bars are measured from the bar bending schedule: cut length of each bar (including bends, hooks and laps as per design) multiplied by the number of bars, and then converted to weight with the unit weight w=d2/162w = d^2/162 kg/m (d in mm).
  • Cover, bends and development lengths are included in the cut length. Binding wire, spacer bars and chairs are included in the rate (or allowed as about 1% extra, as per the specification).
  • Different diameters are given separately.
  • Unit of measurement and payment: kg (or quintal / tonne), supplied, cut, bent, placed and tied.
  • 2074 Chaitra · 5 marks

Write five units of measurement of each length, area and volume.

Answer

DimensionFive units
Lengthmillimetre (mm), centimetre (cm), metre (m), kilometre (km), running metre (rm), foot (ft), inch (in), yard
Areasquare millimetre (mm²), square centimetre (cm²), square metre (m²), hectare (ha), square foot (ft²), ropani, aana (Nepali land units)
Volumecubic millimetre (mm³), cubic centimetre (cm³), cubic metre (m³), litre (L), cubic foot (ft³), cubic yard

Standard SI units used in estimating are m, m² and m³. Useful conversions: 1 m = 3.281 ft, 1 m² = 10.764 ft², 1 m³ = 35.315 ft³ = 1000 L, 1 ropani = 508.72 m².

  • 2071 Chaitra · 5 marks

List the most common units of measurement and payment for civil works and sanitary works (at least five from each).

Answer

Civil works

ItemUnit of measurement and payment
Earthwork excavation, fillingm³
Plain and reinforced cement concretem³
Brick / stone masonrym³
Plastering, painting, flooring, formwork, damp-proof coursem²
Reinforcement steelkg (or tonne)
Doors and windows (frames in m³ or m; shutters in m²)m², m³
Skirting, cornice, coping, drainm (running metre)

Sanitary works

ItemUnit of measurement and payment
Water closet (W.C.) pan, wash basin, urinal, sinknos. / set
Cistern, taps, valves, showernos.
GI / PVC / HDPE pipes layingm
Manhole, inspection chamber, septic tanknos. (or m³ for the structure)
Soil / waste / vent pipesm
Sewer excavation and backfillingm³
Concrete bedding and surroundm³

Questions from Old Question Collection (CE 705) (IOE exam papers from 2065 Shrawan to 2082 Bhadra (22 papers; 2065-2068 are the older Estimating and Valuation syllabus)). Answers are written for this site; check them against your class notes.

Chapter titles and hours from the IOE syllabus ↗