Chapter 5 · 5 hours

Project Estimate

IOE past exam questions

Past questions and answers

12 questions set from this chapter, 3 of them more than once; 1 is most repeated (set, or a close variant set, in 3 or more exams). Most repeated first.

  • Most repeated · 4 of 22 exams
  • Asked 4 times
  • 2075 Chaitra · 6 marks
  • 2071 Chaitra · 5 marks
  • 2078 Bhadra · 4 marks
  • 2081 Bhadra · 6 marks

Define project. Discuss the estimate of an irrigation project (data required and sub-heads to be included in the detailed estimation report).

Answer

Project

A project is a temporary, one-time undertaking with a defined objective, scope, budget, schedule and a clear start and end, carried out to create a unique product or facility. An irrigation project, for example, aims to bring water to a command area through a diversion weir, canals and structures.

Data required for an irrigation project estimate

  1. Topographic and survey data: contour map, longitudinal profile and cross-sections of canal alignment, command area map.
  2. Hydrological data: river discharge records, flood levels, rainfall, water requirement of crops (duty/delta).
  3. Geological and soil data: bed material at weir site, soil type along canal, seepage, bearing capacity.
  4. Design drawings: layout plan, weir and canal designs, drawings of all structures.
  5. Quantities: earthwork, concrete, masonry, gabion, steel, etc., from the drawings.
  6. Rates: District Rates, rate analysis and norms of DUDBC/Department of Irrigation, lead and lift for materials, transport, taxes.
  7. Land and social data: land to be acquired, compensation, crops, forest and environmental clearance, resettlement.
  8. Specifications and time: construction method, season, work programme.

Sub-heads of the detailed estimation report

Sub-headMain items
A. PreliminarySurvey, investigation, design, feasibility study, soil tests
B. Land and compensationLand acquisition, trees, structures, forest clearance
C. Head worksDiversion weir/barrage, intake, under-sluice, settling basin, river training
D. CanalsMain, branch and distributary canals: earthwork, lining
E. Canal structuresRegulators, aqueducts/siphons, drops, culverts, escapes, outlets, bridges
F. DrainageField and main drains, flood protection
G. Buildings and roadsInspection path, canal roads, office/quarters, gauge posts
H. Electro-mechanicalGates, hoists, pump (if any)
I. Environmental and socialMitigation, afforestation, user training
J. Tools and plant, miscellaneousEquipment, communications
K. Establishment/supervision and contingenciesSupervision ~3–5%, physical contingency ~5%, price escalation, VAT 13%

The report contains an introduction, abstract of cost, detailed estimate sheets, rate analysis, specifications, drawings and a construction programme.

  • Asked 2 times
  • 2078 Bhadra · 4 marks
  • 2070 Chaitra · 6 marks

What are the works/tasks that an estimator has to take into account in preparing the estimate of a building project? Explain in brief.

Answer

An estimator turns drawings and specifications into a complete cost by taking into account every work that is needed to complete and hand over the building, not only the visible main work.

Works and tasks to be considered

  1. Study of drawings, specifications and site: read plans, sections, structural and service drawings; visit the site for access, soil, water and power.
  2. Preliminary and site works: site clearance, setting out, temporary shed and store, fencing, water and electricity for construction, soil test.
  3. Substructure: excavation, PCC, foundation (footing, plinth beam), masonry in substructure, DPC, backfilling, plinth filling.
  4. Superstructure: columns, beams, slabs, brick or block walls, lintels, staircases, parapet, formwork and reinforcement.
  5. Finishing works: plaster, flooring, tiles, skirting, doors and windows, painting, whitewash, ceilings, railings.
  6. Roofing: truss or slab, CGI sheet, waterproofing, rain-water pipes.
  7. Services: sanitary and plumbing, drainage and septic tank, water tank, electrical wiring, fittings, earthing, fire safety, lift (if provided).
  8. External works: boundary wall, gate, paving, drains, landscaping.
  9. Rates and taxes: rate analysis from District Rates, overhead and profit, VAT 13%, insurance, contingencies (usually 5%), supervision charges, price adjustment.
  10. Bill of quantities and abstract: measure each item, group them into a BOQ, and prepare the abstract of cost.

Items such as seismic details (NBC 105, NBC 201/202), approval fees and the municipality's requirements are also included.

  • Asked 2 times
  • 2082 Baisakh · 6 marks
  • 2080 Bhadra · 6 marks

Explain the different data required and sub-heads of sanitary works to be included in the detailed estimation report for installation of sewer in a city (prepare a detailed estimate report for a small sewerage project).

Answer

A sewerage project collects and carries the wastewater of a town through a network of pipes to a treatment unit and a safe disposal point. Its detailed estimate is prepared after the survey and design are complete.

Data required

  1. Survey: topographic map, road network, levels and slopes, location of outfall and treatment site.
  2. Population and flow data: present and design-year population (usually 20 years), per-capita water supply (typically 100–135 lpcd in towns), sewage flow = 80% of water supply, peak factor.
  3. Hydraulic design: pipe diameters, gradients (self-cleansing velocity not below 0.6–0.75 m/s, not above about 3 m/s), manhole spacing (30–50 m), depth of cover.
  4. Soil and groundwater data for trench excavation, shoring and dewatering.
  5. Drawings and specifications: layout, longitudinal sections, manhole details, treatment plant design.
  6. Rates: District Rates for excavation, pipes, concrete, brickwork, labour, transport; land and wayleave data; environmental and social data.

Sub-heads of sanitary works

  • Preliminary: survey, investigation, design, supervision.
  • Land and compensation (treatment site, wayleave).
  • Excavation, shoring, dewatering, bedding and backfilling of trenches.
  • Supply, laying, jointing and testing of sewer pipes (trunk, main, lateral).
  • Manholes, drop manholes, inspection chambers, flushing and ventilating arrangements.
  • House connections and gully traps.
  • Pumping station (if gravity flow is not possible) and electromechanical works.
  • Treatment plant (screen, grit chamber, sedimentation, stabilisation pond or similar) and outfall.
  • Restoration of road surface, miscellaneous and contingencies, supervision, VAT.

Specimen detailed estimate report for a small sewerage scheme

Report headings: (1) introduction and project description, (2) design basis, (3) abstract of cost, (4) detailed quantities and rate analysis, (5) specifications, (6) drawings, (7) work programme. Illustrative abstract of cost (quantities and rates are assumed):

S.N.ItemQtyUnitRate (NPR)Amount (NPR)
1Survey, design and investigation (lump)1LS350,000350,000
2Excavation in trenches3,200m³7002,240,000
3300 mm dia. RCC NP2 sewer pipe, laid and jointed1,500m3,8005,700,000
4200 mm dia. uPVC sewer pipe, laid and jointed1,200m2,2002,640,000
5Brick manholes (1.2 m dia., about 1.8 m deep)45no38,0001,710,000
6House connections120no6,500780,000
7Backfilling and compaction2,800m³350980,000
8Road and pavement restoration900m²1,8001,620,000
9Waste stabilisation pond / treatment unit (lump)1LS4,500,0004,500,000
Sub-total20,520,000
Physical contingency 5%1,026,000
Supervision and administration 3%615,600
VAT 13%2,881,008
Total project cost25,042,608

Total estimated cost = NPR 25,042,608.

  • 2074 Chaitra · 5 marks

Define project. Discuss estimation of a road project.

Answer

A project is a set of planned, interrelated activities with a clear objective, definite scope, limited time and a fixed budget. A road project is the construction (or upgrading) of a road of a defined standard between two points.

Estimation of a road project

  1. Survey and design data: reconnaissance and detailed survey, centre line, longitudinal section, cross-sections, traffic and soil (CBR) data, design standard (Nepal Road Standard 2070), drainage and structure design.
  2. Quantities are taken out from the drawings:
    • Earthwork in cutting and filling from cross-sections (mean-area or prismoidal method); rock excavation separately.
    • Sub-base, base course, wearing course (bituminous or concrete).
    • Drainage: side drains, culverts, causeways, bridges.
    • Protection works: retaining and breast walls, gabion, bio-engineering.
    • Road furniture: signs, kilometre stones, guard stones, markings.
  3. Rates from the District Rates and norms, with lead and lift for materials and plant (roller, grader, paver, tipper).
  4. Abstract of cost: the cost of all items is totalled; overhead and profit, physical contingency (5%), supervision and administration, environmental mitigation, price adjustment and VAT 13% are added.
  5. Report: introduction, design standards, quantities and rate analysis, abstract, specifications, drawings and construction programme.

Land acquisition and utility shifting are included as separate heads.

  • 2081 Baisakh · 8 marks

What is project? Explain its characteristics. Describe the stages of estimating a project.

Answer

Project

A project is a one-time, temporary undertaking carried out by a team with limited resources to create a unique product, service or facility (for example a road, bridge, building or water supply scheme).

Characteristics of a project

  1. Definite objective: it is done to achieve a clear goal.
  2. Unique: each project differs in location, design and conditions.
  3. Temporary: it has a start date and an end date.
  4. Limited resources: budget, labour, materials, equipment and time are fixed.
  5. Complexity: several disciplines and organisations (owner, designer, contractor, consultant) work together.
  6. Risk and uncertainty: weather, geology, price change and delay affect it.
  7. Life cycle: it passes through conception, planning, execution and closing.

Stages of estimating a project

StageWork done
1. Identification and preliminary estimateIdea, need, rough cost from cost per unit (per km, per m², per family) to check feasibility
2. Survey and investigationTopographic, geological, hydrological, traffic and soil surveys
3. Planning and designLayout, structural and service design, drawings, specifications
4. Taking out quantitiesMeasurement of each item from drawings, abstracting them in a BOQ
5. Rate analysisRates from norms and District Rates, with lead and lift, transport, overhead and profit
6. Detailed estimateQuantity × rate for each item; abstract of cost with contingency, supervision and VAT
7. Estimate report and approvalReport with drawings, specifications, rate analysis; technical and financial approval
8. Tendering and revisionBid document is prepared; revised or supplementary estimates are made if the scope changes
  • 2080 Baisakh · 4 marks

Describe the different stages of project estimate.

Answer

A project estimate is prepared in steps, each making the cost more accurate than the last.

  1. Identification (preliminary/approximate estimate): the need of the project is established and a rough cost is obtained from plinth-area rate, cost per km, or cost of a similar project. This is used for a feasibility decision and budget allocation.
  2. Survey and investigation: topography, soil, geology, hydrology and traffic data are collected to decide the layout.
  3. Design and drawings: the project is designed and detailed drawings and specifications are prepared.
  4. Quantity calculation: the quantity of each item is measured from drawings and placed in a bill of quantities.
  5. Rate analysis: rates of items are fixed from norms, material and labour rates, lead and lift, transport, overhead and profit.
  6. Detailed estimate and abstract of cost: cost of each item is calculated and added; contingency, supervision, escalation and VAT are included.
  7. Preparation of the report: the estimate report with drawings, specifications, calculations and rate analysis is written.
  8. Approval and tendering: competent authority approves the estimate; it becomes the basis for tender evaluation. Later, revised or supplementary estimates cover changes during construction.
  • 2080 Baisakh · 4 marks

Explain the characteristics of technical report writing of a project.

Answer

A technical report is a formal document that records the facts, calculations, findings and recommendations of a technical work, so that a decision-maker can act on it. For a project (estimate) report, the main characteristics are:

  1. Accuracy: facts, quantities, rates and calculations are correct and checked.
  2. Clarity and simplicity: plain language, short sentences, defined technical terms, tables and figures instead of long text.
  3. Conciseness and completeness: only the necessary information, but nothing important is missing (scope, data, method, results).
  4. Logical organisation: standard order - title page, summary, introduction, data and method, results, discussion/abstract of cost, conclusions and recommendations, appendices.
  5. Objectivity: based on facts and measurement, not opinion or bias.
  6. Audience orientation: matched to the reader (owner, engineer, financing agency, approving authority).
  7. Proper presentation: numbered headings, tables, drawings, references and units, consistent format.
  8. Documentation: source of data, standards (NBC, DUDBC norms, NRS), assumptions and calculations are listed.
  9. Usefulness: gives clear conclusions and recommendations for approval, tendering and construction.
  • 2079 Bhadra · 4+4 marks

What are the requisites for a project estimate? Explain in brief the factors you consider while preparing a building project estimate.

Answer

Requisites for a project estimate

An estimate can be prepared properly only when the following are available:

  1. Drawings: plans, elevations, sections and detailed drawings of all items, to scale and dimensioned.
  2. Specifications: the quality of materials and workmanship for every item.
  3. Rates: current District Rates for materials, labour and equipment, with rate analysis of non-scheduled items.
  4. Site data: survey, soil and geological reports, access, lead and lift of materials.
  5. Norms and standards: DUDBC norms, Nepal Building Code, Nepal Road Standard, units of measurement.
  6. Policy data: provisions for contingency, overhead, profit, VAT and supervision as per the Public Procurement Act and Rules.

Factors considered in a building project estimate

  • Type and purpose of the building (residential, school, hospital) and its quality of finish.
  • Location and site condition: soil, water table, slope, access, local availability of materials and labour.
  • Seismic zone and structural system - load-bearing or RCC frame, as per NBC.
  • Cost of materials, labour and transport: changes in market rates and seasons.
  • Time: shorter completion time needs more machinery and overtime cost.
  • Construction method and equipment: mixers, lifts, scaffolding.
  • Services and external works: sanitary, electrical, water supply, fire safety, boundary wall.
  • Taxes, overhead, profit, contingency (5%), escalation and supervision cost.
  • 2076 Chaitra · 6 marks

What is Project? How is a building project estimate prepared?

Answer

A project is a temporary undertaking with a definite objective, scope, time and budget to create a unique product - for example a building.

Preparing a building project estimate

  1. Collect the data: architectural and structural drawings, specifications, soil report, site visit, and the District Rate list.
  2. Decide the method of estimate: the preliminary estimate may use plinth-area rate; the detailed estimate uses item-wise quantities (long-wall and short-wall or centre-line method).
  3. Take out quantities: list the items in order of work - earthwork, foundation (PCC, masonry), plinth, superstructure (RCC, brickwork), roof, plaster, flooring, doors and windows, painting, sanitary and electrical works. Each has its dimensions, number, length, breadth, height, and quantity in proper units.
  4. Prepare the abstract of quantities (bill of quantities) by combining the same items.
  5. Rate analysis: calculate the rate for each item from material, labour, equipment and overhead.
  6. Abstract of cost: quantity × rate for every item; then add contingency (about 5%), supervision, work-charged establishment and VAT 13% to find the total.
  7. Prepare the report: include a description, drawings, specification, quantities, rate analysis and the abstract of cost for approval.
  • 2075 Asoj · 1+2+3 marks

What do you mean by Project estimate? How do you prepare a project estimate? State the reports on estimate.

Answer

Project estimate

A project estimate is the calculated cost of completing a project, found from the quantities of all works, their rates and the other charges. It is used to get approval, fix the budget and decide the tender price.

Preparing a project estimate

  1. Study the project needs and collect the survey, design, drawings and specifications.
  2. Prepare a preliminary (approximate) estimate to check feasibility.
  3. Take out quantities of all items from the drawings.
  4. Analyse rates using norms and District Rates.
  5. Calculate the cost of each item (quantity × rate) and prepare the abstract of cost.
  6. Add contingency (about 5%), supervision, price escalation and VAT 13%.
  7. Write the report and send it for approval.

Reports on estimate

  1. Preliminary report - the need and feasibility of the project with a rough cost.
  2. Detailed estimate report - quantities, rate analysis, specification, drawings and abstract of cost.
  3. Revised report - when the estimate is exceeded by more than a permissible limit or the plan is changed.
  4. Supplementary report - for additional work not in the original estimate.
  5. Completion report - after completion, comparing actual cost with the estimate.
  • 2081 Bhadra · 4 marks

Briefly describe the components of the detail estimation report with their format for a road project.

Answer

The detailed estimate report of a road project tells the approving authority what is to be built, how much it costs and on what basis. It has the following components.

S.N.ComponentContents
1Title and summaryName of road, location, length, total cost, standard (NRS 2070 class)
2IntroductionObjective, benefited population, traffic, climate, terrain, access
3Design dataGeometric design (width, gradient, curves), pavement design (CBR, traffic), drainage design
4DrawingsPlan, longitudinal profile, typical cross-sections, drawings of structures
5Quantity sheetsItem-wise measurement: earthwork (chainage-wise), pavement, drains, culverts, retaining walls
6Rate analysisBasis of rates, norms, lead and lift, transport, overhead, profit
7Abstract of costItem, quantity, unit, rate, amount; total with contingency, supervision, VAT
8SpecificationsMaterial and workmanship standards
9Work programmeConstruction schedule, equipment and manpower
10ConclusionRecommendation and approval request

Format of the abstract of cost:

S.N.Description of itemUnitQuantityRate (NPR)Amount (NPR)
1Clearing and grubbingm²---
2Earthwork in cutting/fillingm³---
3Sub-base and base coursem³---
4Wearing coursem²---
5Drains and culvertsm---
Total, contingency, supervision, VAT
  • 2082 Bhadra · 5 marks

Prepare a project estimate for water supply project.

Answer

The estimate of a water supply project is prepared by finding the quantities of all works from the design, applying rates, and adding the other charges.

Steps

  1. Data: population (design year, 20 years ahead), demand (about 45–135 lpcd depending on the scheme), source discharge, topographic survey, pipe-network design and drawings.
  2. Components to be estimated: intake and source protection; transmission main; sedimentation/filtration and chlorination; reservoir tank; distribution network; valve and break-pressure chambers; tap stands or house connections; land and compensation; survey, design and supervision.
  3. Quantities of excavation, pipe, masonry, concrete, backfilling and fittings are measured from the drawings.
  4. Rates from District Rates and DUDBC norms, with lead and lift for pipes and materials.
  5. Abstract of cost with contingency 5%, supervision, VAT 13% (and price escalation if the period is long).

Illustrative estimate for a small gravity scheme

Assumptions: 25 public taps for about 1,000 people, quantities and rates are illustrative.

S.N.ItemQtyUnitRate (NPR)Amount (NPR)
1Survey, design and investigation (lump)1LS250,000250,000
2Intake structure with spring box (lump)1LS450,000450,000
3Excavation in trench for pipelines3,200m³6001,920,000
4110 mm HDPE pipe PN10, laid (transmission)2,500m1,8004,500,000
563 mm HDPE pipe PN10, laid (distribution)4,000m9503,800,000
6Backfilling2,900m³300870,000
750 m³ RCC reservoir tank (lump)1LS1,800,0001,800,000
8Valve chambers, air valves, wash-outs15no25,000375,000
9Public tap stands25no35,000875,000
10Chlorination and sedimentation unit (lump)1LS600,000600,000
Sub-total15,440,000
Physical contingency 5%772,000
Supervision and administration 3%463,200
VAT 13%2,167,776
Total project cost18,842,976

Total estimated cost = NPR 18,842,976 (about NPR 18,843 per person).