- 2070 Chaitra · 10 marks
Canal earthwork, bed 3 m, free board 0.44 m
Short answer
Total depth D = 1.44 m, cutting slope 1:1, banking 1.5:1. All stations are part cutting/part banking. Volumes: cutting = 431.93 m³, banking = 579.68 m³, total = 1,011.61 m³.
Calculate the quantity of earth work for a portion of channel with the following data: Bed width = 3 m; Free Board = 0.44 m; Side slope for digging = 1:1; Side slope for banking = 1:1½ (V:H); Fully supply depth = 1 m; Top width of bank = 1.5 m.
| Chainage | 0 | 30 | 60 | 90 | 120 | 150 |
|---|---|---|---|---|---|---|
| RL of GL | 225.24 | 224.8 | 224.43 | 224.12 | 224.5 | 224.98 |
| Proposed level | 224.00 | 223.94 | 223.88 | 223.82 | 223.76 | 223.7 |
Also draw a typical X-section.
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of each bank m.
- Side slope for digging ; for banking 1 V : 1½ H, i.e. (H:V) on the inner and outer faces of the banks.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Typical cross-section (part cutting, part banking)
1.5 m 1.5 m
_______ _______ top of bank = bed + 1.44 m
/ \ 1.5:1 1.5:1 / \ (FSD 1.0 m + FB 0.44 m)
/ bank \ / bank \ 1.5:1
__/___________\________ G.L. ____________/___________\__
\ 1:1 1:1 /
\ cutting / e = GL - bed level
\____________________/
b = 3 m
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0 | 225.240 | 224.000 | 1.240 | part cutting, part banking | 5.258 | 0.720 |
| 30 | 224.800 | 223.940 | 0.860 | part cutting, part banking | 3.320 | 2.749 |
| 60 | 224.430 | 223.880 | 0.550 | part cutting, part banking | 1.953 | 5.046 |
| 90 | 224.120 | 223.820 | 0.300 | part cutting, part banking | 0.990 | 7.319 |
| 120 | 224.500 | 223.760 | 0.740 | part cutting, part banking | 2.768 | 3.570 |
| 150 | 224.980 | 223.700 | 1.280 | part cutting, part banking | 5.478 | 0.557 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0 – 30 | 30.0 | 128.66 | 52.04 |
| 30 – 60 | 30.0 | 79.08 | 116.93 |
| 60 – 90 | 30.0 | 44.14 | 185.48 |
| 90 – 120 | 30.0 | 56.36 | 163.33 |
| 120 – 150 | 30.0 | 123.69 | 61.90 |
| Total | 431.93 | 579.68 |
Answer: Earthwork in cutting = 431.93 m³; earthwork in banking = 579.68 m³; total = 1,011.61 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Channel fully in banking, 0.5-1.5 km · Estimating and Costing, chapter 6
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Channel earthwork and land area, 50 cm fall · Estimating and Costing, chapter 6 · asked 2×
- Channel earthwork with drop at 0+090 · Estimating and Costing, chapter 6
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Balancing depth: bed width 25 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Stable depth and bed width: Q 5, d50 3 cm · Irrigation and Drainage Engineering, chapter 4