Skip to main content

Canal earthwork, bed 3 m, free board 0.44 m

Short answer

Total depth D = 1.44 m, cutting slope 1:1, banking 1.5:1. All stations are part cutting/part banking. Volumes: cutting = 431.93 m³, banking = 579.68 m³, total = 1,011.61 m³.

Calculate the quantity of earth work for a portion of channel with the following data: Bed width = 3 m; Free Board = 0.44 m; Side slope for digging = 1:1; Side slope for banking = 1:1½ (V:H); Fully supply depth = 1 m; Top width of bank = 1.5 m.

Chainage0306090120150
RL of GL225.24224.8224.43224.12224.5224.98
Proposed level224.00223.94223.88223.82223.76223.7

Also draw a typical X-section.

Given data and assumptions

  • Bed width 33 m; FSD 11 m; free board 0.440.44 m, so D=1.44D = 1.44 m; top width of each bank 1.51.5 m.
  • Side slope for digging 1:11:1; for banking 1 V : 1½ H, i.e. 1.5:11.5:1 (H:V) on the inner and outer faces of the banks.

Method

Total depth of canal section D=FSD+free board=1.00+0.44=1.44D = \text{FSD} + \text{free board} = 1.00 + 0.44 = 1.44 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Typical cross-section (part cutting, part banking)

      1.5 m                                  1.5 m
     _______                                _______   top of bank = bed + 1.44 m
    /       \ 1.5:1                  1.5:1 /       \     (FSD 1.0 m + FB 0.44 m)
   /  bank   \                            /  bank   \ 1.5:1
__/___________\________ G.L. ____________/___________\__
               \  1:1               1:1 /
                \      cutting         /    e = GL - bed level
                 \____________________/
                        b = 3 m

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0225.240224.0001.240part cutting, part banking5.2580.720
30224.800223.9400.860part cutting, part banking3.3202.749
60224.430223.8800.550part cutting, part banking1.9535.046
90224.120223.8200.300part cutting, part banking0.9907.319
120224.500223.7600.740part cutting, part banking2.7683.570
150224.980223.7001.280part cutting, part banking5.4780.557

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0 – 3030.0128.6652.04
30 – 6030.079.08116.93
60 – 9030.044.14185.48
90 – 12030.056.36163.33
120 – 15030.0123.6961.90
Total431.93579.68

Answer: Earthwork in cutting = 431.93 m³; earthwork in banking = 579.68 m³; total = 1,011.61 m³.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Estimating and Costing chapter 6 questions →