Channel earthwork and land area, 50 cm fall

Short answer

Part cutting, part banking throughout; cutting = 1,155.86 m³, banking = 785.21 m³. Permanent land area from outer bank toes = 3,365.00 m².

Calculate the quantity of earthwork and area of permanent land required for the land acquisition purpose for a portion of a channel from following data: Bed width = 4 m; Free board = 45 cm; Side slope in cutting = 1:1; Side slope in banking = 1.5:1; Full supply depth = 1 m; Top width of bank = 3 m left and 1.5 m right. There is 50 cm fall at chainage 800 m.

Chainage80085090095010001050
RL ground109.8109.7109.55109.30109.25109.15
RL Bed109.52Bed slope 1:250

Given data and assumptions

  • Bed width 44 m; FSD 11 m; free board 0.450.45 m, so D=1.45D = 1.45 m; top width of bank 33 m (left) and 1.51.5 m (right).
  • Side slope in cutting 1:11:1, in banking 1.5:11.5:1 (inner and outer faces of banks).
  • The ground falls with chainage, so the canal is taken to flow in the direction of increasing chainage, with the bed falling at 1 in 250. The printed bed level 109.52 m at chainage 800 is the level just upstream of the 0.50 m fall. The reach considered lies downstream of the fall, so the bed at 800 is 109.52−0.50=109.02109.52 - 0.50 = 109.02 m, falling 50/250=0.2050/250 = 0.20 m every 50 m: 109.02, 108.82, 108.62, 108.42, 108.22, 108.02 m.

Method

Total depth of canal section D=FSD+free board=1.00+0.45=1.45D = \text{FSD} + \text{free board} = 1.00 + 0.45 = 1.45 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Here every station is in part cutting, part banking, so Ac=(4+e)eA_c = (4 + e)e and Ab=4.5 hb+3 hb2A_b = 4.5\,h_b + 3\,h_b^2.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+800109.800109.0200.780part cutting, part banking3.7284.362
0+850109.700108.8200.880part cutting, part banking4.2943.540
0+900109.550108.6200.930part cutting, part banking4.5853.151
0+950109.300108.4200.880part cutting, part banking4.2943.540
1+000109.250108.2201.030part cutting, part banking5.1812.419
1+050109.150108.0201.130part cutting, part banking5.7971.747

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+800 – 0+85050.0200.57197.54
0+850 – 0+90050.0221.98167.27
0+900 – 0+95050.0221.98167.27
0+950 – 1+00050.0236.88148.97
1+000 – 1+05050.0274.45104.16
Total1,155.86785.21

Permanent land

Width of land at a section = distance between the outer toes of the two banks = canal width at ground level (b+2e)(b + 2e) + inner and outer slopes of both banks (4×1.5 hb)(4 \times 1.5\,h_b) + bank tops (3+1.5)(3 + 1.5).

StationLand width (m)
0+80014.080
0+85013.680
0+90013.480
0+95013.680
1+00013.080
1+05012.680

Area of land == mean width × length, summed over the reaches =694.0+679.0+679.0+669.0+644.0=3,365.00= 694.0 + 679.0 + 679.0 + 669.0 + 644.0 = 3,365.00 m² =0.3365= 0.3365 ha.

Answer: Earthwork in cutting = 1,155.86 m³; earthwork in banking = 785.21 m³; total = 1,941.07 m³. Permanent land = 3,365.00 m².