- Asked 2/22
- 2078 Bhadra · 10 marks
Channel earthwork and land area, 50 cm fall
Short answer
Part cutting, part banking throughout; cutting = 1,155.86 m³, banking = 785.21 m³. Permanent land area from outer bank toes = 3,365.00 m².
Calculate the quantity of earthwork and area of permanent land required for the land acquisition purpose for a portion of a channel from following data: Bed width = 4 m; Free board = 45 cm; Side slope in cutting = 1:1; Side slope in banking = 1.5:1; Full supply depth = 1 m; Top width of bank = 3 m left and 1.5 m right. There is 50 cm fall at chainage 800 m.
| Chainage | 800 | 850 | 900 | 950 | 1000 | 1050 |
|---|---|---|---|---|---|---|
| RL ground | 109.8 | 109.7 | 109.55 | 109.30 | 109.25 | 109.15 |
| RL Bed | 109.52 | Bed slope 1:250 |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of bank m (left) and m (right).
- Side slope in cutting , in banking (inner and outer faces of banks).
- The ground falls with chainage, so the canal is taken to flow in the direction of increasing chainage, with the bed falling at 1 in 250. The printed bed level 109.52 m at chainage 800 is the level just upstream of the 0.50 m fall. The reach considered lies downstream of the fall, so the bed at 800 is m, falling m every 50 m: 109.02, 108.82, 108.62, 108.42, 108.22, 108.02 m.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Here every station is in part cutting, part banking, so and .
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0+800 | 109.800 | 109.020 | 0.780 | part cutting, part banking | 3.728 | 4.362 |
| 0+850 | 109.700 | 108.820 | 0.880 | part cutting, part banking | 4.294 | 3.540 |
| 0+900 | 109.550 | 108.620 | 0.930 | part cutting, part banking | 4.585 | 3.151 |
| 0+950 | 109.300 | 108.420 | 0.880 | part cutting, part banking | 4.294 | 3.540 |
| 1+000 | 109.250 | 108.220 | 1.030 | part cutting, part banking | 5.181 | 2.419 |
| 1+050 | 109.150 | 108.020 | 1.130 | part cutting, part banking | 5.797 | 1.747 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0+800 – 0+850 | 50.0 | 200.57 | 197.54 |
| 0+850 – 0+900 | 50.0 | 221.98 | 167.27 |
| 0+900 – 0+950 | 50.0 | 221.98 | 167.27 |
| 0+950 – 1+000 | 50.0 | 236.88 | 148.97 |
| 1+000 – 1+050 | 50.0 | 274.45 | 104.16 |
| Total | 1,155.86 | 785.21 |
Permanent land
Width of land at a section = distance between the outer toes of the two banks = canal width at ground level + inner and outer slopes of both banks + bank tops .
| Station | Land width (m) |
|---|---|
| 0+800 | 14.080 |
| 0+850 | 13.680 |
| 0+900 | 13.480 |
| 0+950 | 13.680 |
| 1+000 | 13.080 |
| 1+050 | 12.680 |
Area of land mean width × length, summed over the reaches m² ha.
Answer: Earthwork in cutting = 1,155.86 m³; earthwork in banking = 785.21 m³; total = 1,941.07 m³. Permanent land = 3,365.00 m².
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Channel earthwork with drop at 0+090 · Estimating and Costing, chapter 6
- Channel fully in banking, 0.5-1.5 km · Estimating and Costing, chapter 6
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6