- 2075 Chaitra · 10 marks
Hill road earthwork, cutting 4 m / banking 6 m
Short answer
Side-hill section formulas for different formation widths (cut: 4m, slope 2:1; fill: 6m, slope 3:1) and given cross slopes. Volumes by mean area with zero-point proportioning. Earthwork: cutting 428.42 m³, filling 606.34 m³.
Estimate the quantity of earthwork of a hill road when the formation width in cutting is 4 m and side slope is 2:1. The formation width in banking is 6 m and side slope 3:1. The ground and formation level at the centre of road and also the transverse slopes of ground surface are as below:
| Chainage (m) | 0 | 50 | 100 | 150 | 200 | 250 |
|---|---|---|---|---|---|---|
| RL of GL (m) | 1150.00 | 1150.60 | 1151.50 | 1150.80 | 1151.50 | 1152.00 |
| RL of FL (m) | 1149.20 | 1150.00 | 1150.80 | 1151.60 | 1151.50 | 1153.20 |
| Cross slope (m) | 1:10 | 1:1 | 1:14 | 1:12 | 0 | 1:10 |
Given data and assumptions
- Formation width: cutting m with side slope ; banking m with side slope (H:V). Sections are 50 m apart.
- Centre height = GL − FL: 0.80, 0.60, 0.70 (cutting), −0.80 (filling), 0.00, −1.20 (filling).
- The cross slope printed as 1:1 at 50 m is steeper than the 2:1 cut slope (the cut face would never meet the ground), so it is taken as 1:10. At 200 m the cross slope is 0 (level ground) and the centre height is zero.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | cut 0.80 | 4.750 | 0.000 |
| 0+050 | cut 0.60 | 3.333 | 0.000 |
| 0+100 | cut 0.70 | 3.900 | 0.000 |
| 0+150 | fill 0.80 | 0.000 | 7.368 |
| 0+200 | 0.00 | 0.000 | 0.000 |
| 0+250 | fill 1.20 | 0.000 | 12.956 |
Working for one section:
Take chainage 0+050: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 1.000 m); downhill toe at m (ground above formation by 0.333 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between 0+100 (wholly in cutting, 0.70 m) and 0+150 (wholly in filling, 0.80 m): the zero point is m from 0+100, leaving m in filling.
- Cutting m³
- Filling m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+050 | 50.0 | 202.08 | 0.00 |
| 0+050 – 0+100 | 50.0 | 180.84 | 0.00 |
| 0+100 – 0+150 | 50.0 (23.33 cut + 26.67 fill) | 45.50 | 98.24 |
| 0+150 – 0+200 | 50.0 | 0.00 | 184.20 |
| 0+200 – 0+250 | 50.0 | 0.00 | 323.90 |
| Total | 250.0 | 428.42 | 606.34 |
Answer: Earthwork in cutting = 428.42 m³; earthwork in filling = 606.34 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-600 (12 marks) · Estimating and Costing, chapter 6
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9