- 2082 Bhadra
Hill road earthwork, chainage 130-280
Short answer
Cutting = 309.82 m³, filing = 471.28 m³. Side-hill areas from given cross slopes and side slopes; volumes by average end-area, transition length prorated.
A road is to be constructed in hill areas with formation width of 8 m. Side slope in banking is 2:1 and side slope in cutting is 1.5:1. Calculate the quantities of earthwork from the following data:
| Chainage | Depth of cutting at centre of road | Height of filling at centre of road | Cross slope of ground |
|---|---|---|---|
| 130 | 0.7 m | - | 12:1 |
| 160 | 0.5 m | - | 15:1 |
| 190 | 0.4 m | - | 12:1 |
| 220 | - | 0.7 m | 10:1 |
| 250 | - | 0.6 m | 15:1 |
| 280 | - | 0.8 m | 12:1 |
Given data and assumptions
- Formation width m in both cutting and filling; side slope in cutting , in filling (H:V).
- Chainages are 30 m apart; cross slopes are taken as (H:V), e.g. 12:1 means 12 horizontal to 1 vertical.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+130 | cut 0.70 | 6.605 | 0.000 |
| 0+160 | cut 0.50 | 4.527 | 0.000 |
| 0+190 | cut 0.40 | 3.664 | 0.000 |
| 0+220 | fill 0.70 | 0.000 | 7.188 |
| 0+250 | fill 0.60 | 0.000 | 5.765 |
| 0+280 | fill 0.80 | 0.000 | 8.128 |
Working for one section:
Take chainage 0+220: centre filling height m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground below formation by 0.250 m); downhill toe at m (ground below formation by 1.375 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between 0+190 (wholly in cutting, 0.40 m) and 0+220 (wholly in filling, 0.70 m): the zero point is m from 0+190, leaving m in filling.
- Cutting m³
- Filling m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+130 – 0+160 | 30.0 | 166.98 | 0.00 |
| 0+160 – 0+190 | 30.0 | 122.86 | 0.00 |
| 0+190 – 0+220 | 30.0 (10.91 cut + 19.09 fill) | 19.98 | 68.61 |
| 0+220 – 0+250 | 30.0 | 0.00 | 194.28 |
| 0+250 – 0+280 | 30.0 | 0.00 | 208.39 |
| Total | 150.0 | 309.82 | 471.28 |
Answer: Earthwork in cutting = 309.82 m³; earthwork in filling = 471.28 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-600 (12 marks) · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×