- 2074 Asoj · 10 marks
Side-long ground hill road, 0-400 m
Short answer
Formation levels are computed from downward gradient 1 in 200, centre heights determined. With cross-slope 1 in 5, side-hill areas calculated and mean area method yields volumes. Earthwork: cutting 225.78 m³, filling 8262.11 m³.
Calculate the quantities of earthwork of a hill road in side long ground from 0 m to 400 m partly in cutting and partly in filling with the following data: width of road = 10 m, side slope in cutting and filling = (1:1) and (2:1). The road has a downward gradient of 1 in 200. The cross slope of ground = 1 in 5. Formation level at 0 m = 1203.50 m.
| Ground level | 1202.50 | 1201.97 | 1202.35 | 1199.66 | 1200.50 |
|---|---|---|---|---|---|
| Distance | 0 | 100 | 200 | 300 | 400 |
Given data and assumptions
- Formation width m; side slope in cutting , in filling ; cross slope of ground in () throughout.
- Formation level at 0 m is 1203.50 m and falls 1 in 200, so it is 1203.50, 1203.00, 1202.50, 1202.00, 1201.50 m at 0, 100, 200, 300, 400 m.
- Ground levels are at the centre line.
Method
Ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line and the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.
| Chainage | GL (m) | FL (m) | Depth of cutting / height of filling (m) |
|---|---|---|---|
| 0+000 | 1,202.500 | 1,203.500 | filling 1.000 |
| 0+100 | 1,201.970 | 1,203.000 | filling 1.030 |
| 0+200 | 1,202.350 | 1,202.500 | filling 0.150 |
| 0+300 | 1,199.660 | 1,202.000 | filling 2.340 |
| 0+400 | 1,200.500 | 1,201.500 | filling 1.000 |
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | fill 1.00 | 0.000 | 16.667 |
| 0+100 | fill 1.03 | 0.000 | 17.169 |
| 0+200 | fill 0.15 | 2.258 | 5.510 |
| 0+300 | fill 2.34 | 0.000 | 43.275 |
| 0+400 | fill 1.00 | 0.000 | 16.667 |
Working for one section:
Take chainage 0+000: centre filling height m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 0.000 m); downhill toe at m (ground below formation by 3.333 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+100 | 100.0 | 0.00 | 1,691.77 |
| 0+100 – 0+200 | 100.0 | 112.89 | 1,133.96 |
| 0+200 – 0+300 | 100.0 | 112.89 | 2,439.28 |
| 0+300 – 0+400 | 100.0 | 0.00 | 2,997.10 |
| Total | 400.0 | 225.78 | 8,262.11 |
Answer: Earthwork in cutting = 225.78 m³; earthwork in filling = 8,262.11 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, cross slope 1 in 5 (0-60) · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Hill road earthwork, 0 m to 90 m, 10/8 m widths · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×