Hill road earthwork with cross sections

Short answer

Using mean area times 30 m: cutting = (5.556+3.362)/2×30 + (3.362+11.364)/2×30 = 354.66 m³; filling = (0+0.098)/2×30 + (0.098+0)/2×30 = 2.94 m³.

Find out the quantity of a hill road when the following data are given: formation width is 10 m. Side slope in cutting and filling are (1:1 and 2:1) respectively.

ChainageDepth of cutting at centre lineCross slope of ground
00.5 m10:1
300.30 m12:1
601.00 m10:1

Draw cross section at each point.

Given data and assumptions

  • Formation width B=10B = 10 m; side slope in cutting 1:11:1, in filling 2:12:1 (H:V); distance between sections 30 m.

Method

Ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line and du,ddd_u, d_d the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.505.5560.000
0+030cut 0.303.3620.098
0+060cut 1.0011.3640.000

Working for one section:

Take chainage 0+030: centre cutting depth h=0.30h = 0.30 m, n=12n = 12, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =0.717= 0.717 m, at the downhill edge =−0.117= -0.117 m.
  • Toe of the side slope on the uphill side at x=5.782x = 5.782 m from the centre line (ground above formation by 0.782 m); downhill toe at x=5.280x = 5.280 m (ground below formation by 0.140 m).
  • Area from the co-ordinates of the polygon: cutting =3.362= 3.362 m², filling =0.098= 0.098 m².

Cross-sections (vertical scale exaggerated)

Chainage 0+000 (centre cutting 0.50 m, cross slope 10:1; area of cutting 5.556 m², filling 0.000 m²)

...
  ##.....
   ##   ........
    #          .......
    ##               ........
     #                      .......
      #                           ........
      ##########################################
                                               ...

(. ground line, # formation and side slopes)

Chainage 0+030 (centre cutting 0.30 m, cross slope 12:1; area of cutting 3.362 m², filling 0.098 m²)

..
 .##.....
   #    .......
    #         ........
    #                ........
     #                      ........
     ##########################################
                                         .....##.
                                                ..

(. ground line, # formation and side slopes)

Chainage 0+060 (centre cutting 1.00 m, cross slope 10:1; area of cutting 11.364 m², filling 0.000 m²)

..#.
  ##........
   ##      ..........
    ##              .........
     ##                      .........
      ##                             ..........
       #                                      ##..
       ##                                    ##
        ######################################

(. ground line, # formation and side slopes)

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0133.761.47
0+030 – 0+06030.0220.881.47
Total60.0354.642.94

Answer: Earthwork in cutting = 354.64 m³; earthwork in filling = 2.94 m³.