- 2068 Baisakh (old course) · 10 marks
Hill road earthwork, cross slope 1 in 5 (0-60)
Short answer
Using side-hill section formulas with cross slope 1:5, formation width 8 m, side slopes 1:1 in cutting and 2:1 in filling, the earthwork is 330.00 m³ in cutting and 1,110.00 m³ in filling.
Work out the quantity of earth work in cutting and filling of a portion of a hill road as per data given below: Cross slope = 1 in 5, formation width = 8 m, side slope in cutting = 1:1, side slope in filling = 2:1.
| R.L. of formation | 699.20 | 702.20 | 704.20 |
|---|---|---|---|
| R.L. of ground | 698.80 | 700.00 | 706.20 |
| Distance (m) | 0 | 30 | 60 |
Given data and assumptions
- Formation width m; side slope in cutting , in filling ; ground cross slope in .
Method
Ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line and the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.
| Chainage | GL (m) | FL (m) | Depth of cutting / height of filling (m) |
|---|---|---|---|
| 0+000 | 698.800 | 699.200 | filling 0.400 |
| 0+030 | 700.000 | 702.200 | filling 2.200 |
| 0+060 | 706.200 | 704.200 | cutting 2.000 |
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | fill 0.40 | 0.500 | 6.000 |
| 0+030 | fill 2.20 | 0.000 | 34.000 |
| 0+060 | cut 2.00 | 21.500 | 0.000 |
Working for one section:
Take chainage 0+000: centre filling height m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 0.500 m); downhill toe at m (ground below formation by 2.000 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+030 | 30.0 | 7.50 | 600.00 |
| 0+030 – 0+060 | 30.0 | 322.50 | 510.00 |
| Total | 60.0 | 330.00 | 1,110.00 |
Answer: Earthwork in cutting = 330.00 m³; earthwork in filling = 1,110.00 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, km 8.50 to km 9.00 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-600 (12 marks) · Estimating and Costing, chapter 6
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×