- 2071 Chaitra · 12 marks
Hill road earthwork, 0-90 m (8 m formation)
Short answer
Areas computed with side-hill formulas for given cross slopes; transition from cut to fill between 30 m and 60 m handled by zero point. Total earthwork: cutting 74.58 m³, filling 261.08 m³.
Calculate the quantities of earthwork of a portion of hill road from the following data: Formation width = 8 m, side slope in cutting and filling = (1:1) and (2:1).
| Distance | Depth of cut | Depth of fill | Cross slope of ground |
|---|---|---|---|
| 0 m | 0.30 | - | 10:1 |
| 30 m | 0.20 | - | 15:1 |
| 60 m | - | 0.50 | 12:1 |
| 90 m | - | 0.70 | 8:1 |
Given data and assumptions
- Formation width m; side slope in cutting , in filling .
- Sections 30 m apart. Some of the cutting sections (small centre depth, steep cross slope) are partly in filling on the low side, and are calculated that way.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | cut 0.30 | 2.722 | 0.063 |
| 0+030 | cut 0.20 | 1.750 | 0.038 |
| 0+060 | fill 0.50 | 0.000 | 4.857 |
| 0+090 | fill 0.70 | 0.000 | 7.552 |
Working for one section:
Take chainage 0+000: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 0.778 m); downhill toe at m (ground below formation by 0.125 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between 0+030 (cutting 0.20 m at the centre) and 0+060 (wholly in filling, 0.50 m): the zero point is m from 0+030.
- Cutting is zero at 0+060, so it is taken over the 8.57 m only: m³
- Filling is present at both ends (0.038 and 4.857 m²), so the mean area is used: m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+030 | 30.0 | 67.08 | 1.51 |
| 0+030 – 0+060 | 30.0 (cutting over 8.57) | 7.50 | 73.43 |
| 0+060 – 0+090 | 30.0 | 0.00 | 186.14 |
| Total | 90.0 | 74.58 | 261.08 |
Answer: Earthwork in cutting = 74.58 m³; earthwork in filling = 261.08 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, 0 m to 90 m, 10/8 m widths · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, cross slope 1 in 5 (0-60) · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, 0+060 to 0+120 · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×