Compute sectional areas using side-hill formulae. Prorate the cut-fill transition length by centre heights. Mean area volumes: cutting 228.78 m³, filling 390.96 m³.

Calculate the volume of earthwork of a portion of hill road from the given data: Top formation width in cutting = 8 m, top formation width in banking = 10 m, side slope in cutting and banking are 1.5:1 and 2:1 (H:V), respectively.

DistanceHeight of FillingDepth of CuttingTransverse Slope of Ground (H:V)
0 m-0.6010:1
30 m-0.7015:1
60 m0.80-12:1
90 m0.85-10:1

Given data and assumptions

  • Formation width: cutting 88 m, banking 1010 m; side slopes: cutting 1.5:11.5:1, banking 2:12:1 (H:V).
  • Sections 30 m apart. Cutting at 0 m and 30 m, filling at 60 m and 90 m.

Method

The ground has a transverse (cross) slope n:1n:1 (H:V), so each section is a side-hill section. With centre height hh (cutting +, filling −) above/below formation level, formation width BB and side slope s:1s:1:

xu=n (B/2+sh)n−s,du=h+xunxd=n (B/2+sh)n+s,dd=h−xdnA=12Bh+12[B2(du+dd)+h (xu+xd−B)]\begin{aligned} x_u &= \frac{n\,(B/2 + s h)}{n - s},\quad d_u = h + \frac{x_u}{n}\\ x_d &= \frac{n\,(B/2 + s h)}{n + s},\quad d_d = h - \frac{x_d}{n}\\ A &= \tfrac12 B h + \tfrac12\left[\tfrac{B}{2}(d_u + d_d) + h\,(x_u + x_d - B)\right] \end{aligned}

Here xu,xdx_u, x_d are the horizontal distances of the up-hill and down-hill toes from the centre line, and du,ddd_u, d_d are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, xd=n(B/2+sh)/(n−s)x_d = n(B/2 + s h)/(n - s) and xu=n(B/2+sh)/(n+s)x_u = n(B/2 + s h)/(n + s), with hh the filling height and ss the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: V=12A×lV = \tfrac12 A \times l.

Sectional areas

ChainageCentre ht. hh (m)Cutting area (m²)Filling area (m²)
0+000cut 0.605.7080.000
0+030cut 0.706.5070.000
0+060fill 0.800.0009.902
0+090fill 0.850.00010.880

Working for one section:

Take chainage 0+090: centre filling height h=0.85h = 0.85 m, n=10n = 10, B=10.0B = 10.0 m.

  • Ground height above formation at the uphill edge =−0.350= -0.350 m, at the downhill edge =−1.350= -1.350 m.
  • Toe of the side slope on the uphill side at x=5.583x = 5.583 m from the centre line (ground below formation by 0.292 m); downhill toe at x=8.375x = 8.375 m (ground below formation by 1.688 m).
  • Area from the co-ordinates of the polygon: cutting =0.000= 0.000 m², filling =10.880= 10.880 m².

Change-over between 0+030 (wholly in cutting, 0.70 m) and 0+060 (wholly in filling, 0.80 m): the zero point is 30×0.70/1.50=14.0030 \times 0.70/1.50 = 14.00 m from 0+030, leaving 16.0016.00 m in filling.

  • Cutting =12×6.507×14.00=45.55= \tfrac12 \times 6.507 \times 14.00 = 45.55 m³
  • Filling =12×9.902×16.00=79.22= \tfrac12 \times 9.902 \times 16.00 = 79.22 m³

Volumes

BetweenDistance (m)Cutting (m³)Filling (m³)
0+000 – 0+03030.0183.230.00
0+030 – 0+06030.0 (14.00 cut + 16.00 fill)45.5579.22
0+060 – 0+09030.00.00311.74
Total90.0228.78390.96

Answer: Earthwork in cutting = 228.78 m³; earthwork in filling = 390.96 m³.