- Asked 2/22
- 2080 Bhadra · 8 marks
Hill road earthwork, 0 m to 90 m, 10/8 m widths
Short answer
Compute sectional areas using side-hill formulae. Prorate the cut-fill transition length by centre heights. Mean area volumes: cutting 228.78 m³, filling 390.96 m³.
Calculate the volume of earthwork of a portion of hill road from the given data: Top formation width in cutting = 8 m, top formation width in banking = 10 m, side slope in cutting and banking are 1.5:1 and 2:1 (H:V), respectively.
| Distance | Height of Filling | Depth of Cutting | Transverse Slope of Ground (H:V) |
|---|---|---|---|
| 0 m | - | 0.60 | 10:1 |
| 30 m | - | 0.70 | 15:1 |
| 60 m | 0.80 | - | 12:1 |
| 90 m | 0.85 | - | 10:1 |
Given data and assumptions
- Formation width: cutting m, banking m; side slopes: cutting , banking (H:V).
- Sections 30 m apart. Cutting at 0 m and 30 m, filling at 60 m and 90 m.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | cut 0.60 | 5.708 | 0.000 |
| 0+030 | cut 0.70 | 6.507 | 0.000 |
| 0+060 | fill 0.80 | 0.000 | 9.902 |
| 0+090 | fill 0.85 | 0.000 | 10.880 |
Working for one section:
Take chainage 0+090: centre filling height m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground below formation by 0.292 m); downhill toe at m (ground below formation by 1.688 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between 0+030 (wholly in cutting, 0.70 m) and 0+060 (wholly in filling, 0.80 m): the zero point is m from 0+030, leaving m in filling.
- Cutting m³
- Filling m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+030 | 30.0 | 183.23 | 0.00 |
| 0+030 – 0+060 | 30.0 (14.00 cut + 16.00 fill) | 45.55 | 79.22 |
| 0+060 – 0+090 | 30.0 | 0.00 | 311.74 |
| Total | 90.0 | 228.78 | 390.96 |
Answer: Earthwork in cutting = 228.78 m³; earthwork in filling = 390.96 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, 0+020 to 0+140 · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, 0+060 to 0+120 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Hill road earthwork, cross slope 1 in 5 (0-60) · Estimating and Costing, chapter 6
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×