- 2081 Bhadra · 8 marks
Hill road earthwork, 0+020 to 0+140
Short answer
Use side-hill section formulas to find areas. Where cutting changes to filling, prorate length by centre heights. Volume by mean area method gives cutting 411.66 m³, filling 184.84 m³.
Data for a hill road portion is given below. Calculate the volume of earthwork.
| Chainage | Depth of Cutting (m) | Height of banking (m) | Transverse Slope of Ground |
|---|---|---|---|
| 0+020 m | 0.6 | - | 10:1 |
| 0+070 m | 0.7 | - | 15:1 |
| 0+140 m | - | 0.8 | 12:1 |
Width in cutting = 8 m, Formation width in banking = 10 m, Side slope in cutting = 1.5:1 (H:V), Side slope in banking = 2:1 (H:V).
Given data and assumptions
- Formation width: cutting m, banking m; side slopes: cutting , banking (H:V).
- Sections at 0+020, 0+070 and 0+140 m, so the distances are 50 m and 70 m.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+020 | cut 0.60 | 5.708 | 0.000 |
| 0+070 | cut 0.70 | 6.507 | 0.000 |
| 0+140 | fill 0.80 | 0.000 | 9.902 |
Working for one section:
Take chainage 0+020: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 1.176 m); downhill toe at m (ground above formation by 0.174 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between 0+070 (wholly in cutting, 0.70 m) and 0+140 (wholly in filling, 0.80 m): the zero point is m from 0+070, leaving m in filling.
- Cutting m³
- Filling m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+020 – 0+070 | 50.0 | 305.38 | 0.00 |
| 0+070 – 0+140 | 70.0 (32.67 cut + 37.33 fill) | 106.28 | 184.84 |
| Total | 120.0 | 411.66 | 184.84 |
Answer: Earthwork in cutting = 411.66 m³; earthwork in filling = 184.84 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, 0 m to 90 m, 10/8 m widths · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-600 (12 marks) · Estimating and Costing, chapter 6
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×