- 2076 Chaitra · 6 marks
Earthwork volume, formation 1201.85, 1.65 m depth
Short answer
Determine ground levels and formation levels from given gradients, then compute cross-sectional areas for cutting with side slopes 2:1, transverse slope 6:1, formation width 6 m. Trapezoidal volume = 1999.04 m³, prismoidal volume = 1980.81 m³, prismoidal correction = 18.23 m³.
Find the volume of earthwork by trapezoidal and prismoidal formula in three consecutive sections at 30 m interval. Formation level of starting chainage = 1201.85 m. Formation width = 6 m. Downward slope of formation = 100:1, side slope = 2:1 and transverse slope = 6:1. The ground has an upward gradient of 50:1. The depth of cutting at 0 chainage is 1.65 m. Compute the prismoidal correction also.
A two-level section (ground sloping across the road) is used at every chainage. Data: formation width m, side slope (horizontal : vertical), transverse ground slope , section spacing m.
Step 1: Formation levels and depths at the centre line
The ground level at chainage 0 is m. The ground rises 1 in 50, i.e. m per 30 m, and the formation falls 1 in 100, i.e. m per 30 m. The depth of cut therefore increases by m per 30 m.
| Chainage (m) | GL (m) | FL (m) | Centre depth of cut h (m) |
|---|---|---|---|
| 0 | 1203.50 | 1201.85 | 1.65 |
| 30 | 1204.10 | 1201.55 | 2.55 |
| 60 | 1204.70 | 1201.25 | 3.45 |
Step 2: Cross-sectional areas
Along the cross-section the ground rises on one side and falls on the other. The depths of cut at the two side slope ends (where the side slope meets the ground) are
The horizontal distances from the centre line to these points are and , and the area of the section is
(the triangle between the two side slopes extended and the ground line, minus the triangle below the formation width).
Worked section at chainage 0, m:
| Chainage (m) | h (m) | h₁ (m) | h₂ (m) | d₁ (m) | d₂ (m) | Area A (m²) |
|---|---|---|---|---|---|---|
| 0 | 1.65 | 3.225 | 0.862 | 9.450 | 4.725 | 17.826 |
| 30 | 2.55 | 4.575 | 1.537 | 12.150 | 6.075 | 32.406 |
| 60 | 3.45 | 5.925 | 2.213 | 14.850 | 7.425 | 50.631 |
Step 3: Volume by the trapezoidal formula
Step 4: Volume by the prismoidal formula
Step 5: Prismoidal correction
The trapezoidal formula overestimates the volume by 18.23 m³, so the prismoidal volume is the more accurate one.
Answer: Volume of cutting by the trapezoidal formula = 1999.04 m³; by the prismoidal formula = 1980.81 m³; prismoidal correction = 18.23 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-600 (12 marks) · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6