- 2080 Bhadra · 6 marks
Cut and fill volume, 20 m formation width
Short answer
For depths 0.4, 0.8, 1.2 m at 50 m spacing, trapezoidal volumes: cut 1839.90 m³, fill 68.75 m³. Prismoidal: cut 1826.60 m³, fill 54.17 m³. Prismoidal correction: cut 13.30 m³, fill 14.58 m³.
The width of a certain road at the formation level is 20 m, side slope 1:1 for cutting and 1:2 for filling. The ground transverse slope is 1 in 0 [?]. If the depth of excavation at the centre line of three successive sections 50 m apart are 0.4, 0.8 and 1.20 m, calculate the volume of cutting and filling by trapezoidal method and prismoidal correction also.
Reading of the given data: the scanned slope reads "1 in 0", which is incomplete. Because the question asks for both cutting and filling, a cross-fall is needed, so it is read as 1 in 10 (n = 10). Formation width m (half width 10 m), cutting side slope 1:1, filling side slope 1:2 (taken as 2 horizontal : 1 vertical, so ), centre-line depths of excavation 0.4, 0.8 and 1.2 m at 50 m spacing.
Step 1: Type of section at each chainage
With a cross-fall of 1 in 10, the ground is 1.0 m higher than the centre at the formation edge on the high side and 1.0 m lower on the low side. If the centre depth m, the low side is in filling and the high side in cutting (a side-long section). The ground cuts the formation level at a distance from the centre on the low side.
| Chainage | h (m) | Section |
|---|---|---|
| 0 | 0.4 | cut + fill (10h = 4 m < 10 m) |
| 50 | 0.8 | cut + fill (10h = 8 m < 10 m) |
| 100 | 1.2 | full cutting (two-level section) |
Step 2: Areas of cutting and filling
For a side-long section, the cut is a triangle on the high side and the fill is a triangle on the low side.
- Cutting depth at the high-side slope end: and
- Filling height at the low-side slope end: and
| Chainage (m) | h (m) | H (m) | F (m) | A cut (m²) | A fill (m²) |
|---|---|---|---|---|---|
| 0 | 0.4 | 1.556 | 0.750 | 10.889 | 2.250 |
| 50 | 0.8 | 2.000 | 0.250 | 18.000 | 0.250 |
| 100 | 1.2 | 2.444 () | – | 26.707 | 0 |
At 100 m the whole width is in cutting (no filling), so the two-level formula is used with , : m, m (depth of cut on the low side), and m².
Step 3: Trapezoidal volumes
Step 4: Prismoidal volumes and correction
Prismoidal correction :
| Trapezoidal (m³) | Prismoidal (m³) | (m³) | |
|---|---|---|---|
| Cutting | 1839.90 | 1826.60 | 13.30 |
| Filling | 68.75 | 54.17 | 14.58 |
Answer: Cutting = 1839.90 m³ and filling = 68.75 m³ by the trapezoidal method. Prismoidal correction = 13.30 m³ for cutting and 14.58 m³ for filling (prismoidal volumes 1826.60 m³ and 54.17 m³).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Filling volume, 50 m, formation 1081.50 · Surveying I, chapter 9 · asked 4×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, GL 540.70, formation 538.20 · Surveying I, chapter 9 · asked 7×
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, km 8.50 to km 9.00 · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6