- 2067 Poush (old course) · 10 marks
Hill road earthwork, km 8.50 to km 9.00
Short answer
Earthwork in cutting = 3,125.00 m³; earthwork in filling = 166.67 m³.
Calculate the quantity of earthwork in cutting and filling in a portion of a hill road from km 8.50 to km 9.00 having cross slope (transverse slope) of ground 1 in 5 with the following data. Formation width of road = 8 m. Side slope in cutting = (1:1). Side slope in filling = (2:1). Depth of cut at centre line at km 8.50 = 40 cm. Depth of cut at centre line at km 9.00 = 80 cm.
Given data and assumptions
- Formation width m; side slope in cutting , in filling ; cross slope of ground in ().
- Centre depth of cutting: 0.40 m at km 8.50 and 0.80 m at km 9.00; the length is 500 m. With only two sections, the mean-area method is used.
Method
Ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line and the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling.
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| km 8.50 | cut 0.40 | 4.500 | 0.667 |
| km 9.00 | cut 0.80 | 8.000 | 0.000 |
Working for one section:
Take chainage km 8.50: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 1.500 m); downhill toe at m (ground below formation by 0.667 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| km 8.50 – km 9.00 | 500.0 | 3,125.00 | 166.67 |
| Total | 500.0 | 3,125.00 | 166.67 |
Answer: Earthwork in cutting = 3,125.00 m³; earthwork in filling = 166.67 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, cross slope 1 in 5 (0-60) · Estimating and Costing, chapter 6
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Side-long ground hill road, 0-400 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 0-150 (50 m) · Estimating and Costing, chapter 6
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×
- Cutting volume, 60 m, formation level 278.00 · Surveying I, chapter 9 · asked 7×