- 2076 Asoj · 9 marks
Hill road earthwork, chainage 0-150 (50 m)
Short answer
Side-hill section areas computed using formulas for ground cross slope n:1, formation width 10m, cut slope 1:1, fill slope 2:1. Volumes by mean area with zero-point proportion. Earthwork: cutting 403.61 m³, filling 343.58 m³.
A road is to be constructed in hilly area with formation width of 10 m, side slopes in banking and cutting (2:1) and (1:1). The height of banking or depth of cutting at the centre line of the road are given below. The cross slopes of ground are also given at different sections. Calculate the quantities of earthwork.
| Distance | Cutting | Filling | Cross slope of ground |
|---|---|---|---|
| 0 | 0.50 | -- | 12:1 |
| 50 | 0.60 | -- | 10:1 |
| 100 | -- | 0.40 | 15:1 |
| 150 | -- | 0.60 | 12:1 |
Given data and assumptions
- Formation width m; side slope in cutting , in banking (H:V).
- Sections 50 m apart; cutting at 0 and 50 m, filling at 100 and 150 m.
Method
The ground has a transverse (cross) slope (H:V), so each section is a side-hill section. With centre height (cutting +, filling −) above/below formation level, formation width and side slope :
Here are the horizontal distances of the up-hill and down-hill toes from the centre line, and are the heights of the ground above formation at the toes (formulas for cutting). For a section wholly in filling the roles swap: the down-hill toe is the far one, and , with the filling height and the filling slope. Where the ground line crosses the formation level inside the road width (part cutting, part filling), the cutting and filling areas are found separately from the co-ordinates of the section (toe points from the same intersection equations). Volume between sections = mean area × distance, taken separately for cutting and filling. Where the centre changes from cutting to filling between two sections and one type of area is zero at one end, the change-over point is found by proportion of the centre heights, and that area is taken over its own part of the length only: .
Sectional areas
| Chainage | Centre ht. (m) | Cutting area (m²) | Filling area (m²) |
|---|---|---|---|
| 0+000 | cut 0.50 | 5.462 | 0.000 |
| 0+050 | cut 0.60 | 6.677 | 0.000 |
| 0+100 | fill 0.40 | 0.000 | 4.624 |
| 0+150 | fill 0.60 | 0.000 | 7.269 |
Working for one section:
Take chainage 0+000: centre cutting depth m, , m.
- Ground height above formation at the uphill edge m, at the downhill edge m.
- Toe of the side slope on the uphill side at m from the centre line (ground above formation by 1.000 m); downhill toe at m (ground above formation by 0.077 m).
- Area from the co-ordinates of the polygon: cutting m², filling m².
Change-over between 0+050 (wholly in cutting, 0.60 m) and 0+100 (wholly in filling, 0.40 m): the zero point is m from 0+050, leaving m in filling.
- Cutting m³
- Filling m³
Volumes
| Between | Distance (m) | Cutting (m³) | Filling (m³) |
|---|---|---|---|
| 0+000 – 0+050 | 50.0 | 303.46 | 0.00 |
| 0+050 – 0+100 | 50.0 (30.00 cut + 20.00 fill) | 100.15 | 46.24 |
| 0+100 – 0+150 | 50.0 | 0.00 | 297.34 |
| Total | 150.0 | 403.61 | 343.58 |
Answer: Earthwork in cutting = 403.61 m³; earthwork in filling = 343.58 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 130-280 · Estimating and Costing, chapter 6
- Hill road earthwork with cross sections · Estimating and Costing, chapter 6
- Hill road earthwork, chainage 12-15 · Estimating and Costing, chapter 6
- Road earthwork, formation level at 150 m · Estimating and Costing, chapter 6 · asked 2×
- Hill road earthwork, 0-90 m (8 m formation) · Estimating and Costing, chapter 6
- Earthwork volume, formation 1201.85, 1.65 m depth · Surveying I, chapter 9
- Cutting volume, 60 m, GL 1181.50, formation 1179.00 · Surveying I, chapter 9 · asked 8×
- Cut and fill volume, 20 m formation width · Surveying I, chapter 9
- Stabilising formation and cross slopes · Transportation Engineering I, chapter 5