- 2080 Bhadra · 8 marks
Channel earthwork with drop at 0+090
Short answer
Mean-area method applied across a drop; all sections have part cutting and part banking. Cutting = 1,139.85 m³, banking = 953.55 m³, total = 2,093.40 m³.
Calculate the quantity of the earthwork of a channel with the following data: Bed width = 6 m, free board = 50 cm, slope of cutting 1:1, side slope of banking 1.5:1, full supply depth is 2 m, width of the banks is 1.5 m. There is vertical drop of 0.5 m at ground surface at chainage 0+090. The longitudinal slope of canal is 1 in 600.
| Chainage | Ground Level (m) | Bed Level (m) |
|---|---|---|
| 0+000 | 225.3 | 224.00 |
| 0+030 | 225.2 | |
| 0+060 | 225.1 | |
| 0+090 | 225.2 / 224.7 (as printed, before and after drop) | |
| 0+120 | 224.8 |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; width (top) of each bank m.
- Side slope in cutting ; banks on both faces.
- Bed falls 1 in 600: 30 m gives 0.05 m, so the bed is 224.00, 223.95, 223.90, 223.85 m up to the drop at 0+090. The 0.5 m drop gives 223.35 m after the drop, and 223.30 m at 0+120. Ground level at 0+090 is 225.2 m before and 224.7 m after the drop.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0+000 | 225.300 | 224.000 | 1.300 | part cutting, part banking | 9.490 | 7.920 |
| 0+030 | 225.200 | 223.950 | 1.250 | part cutting, part banking | 9.062 | 8.438 |
| 0+060 | 225.100 | 223.900 | 1.200 | part cutting, part banking | 8.640 | 8.970 |
| 0+090 (before drop) | 225.200 | 223.850 | 1.350 | part cutting, part banking | 9.922 | 7.418 |
| 0+090 (after drop) | 224.700 | 223.350 | 1.350 | part cutting, part banking | 9.922 | 7.418 |
| 0+120 | 224.800 | 223.300 | 1.500 | part cutting, part banking | 11.250 | 6.000 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0+000 – 0+030 | 30.0 | 278.29 | 245.36 |
| 0+030 – 0+060 | 30.0 | 265.54 | 261.11 |
| 0+060 – 0+090 (before drop) | 30.0 | 278.44 | 245.81 |
| 0+090 (after drop) – 0+120 | 30.0 | 317.59 | 201.26 |
| Total | 1,139.85 | 953.55 |
Answer: Earthwork in cutting = 1,139.85 m³; earthwork in banking = 953.55 m³; total = 2,093.40 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Channel earthwork and land area, 50 cm fall · Estimating and Costing, chapter 6 · asked 2×
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Irrigation canal earthwork with vertical drop · Estimating and Costing, chapter 6
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Crest width, cistern length of vertical drop, Q 1.55 · Irrigation and Drainage Engineering, chapter 7 · asked 2×
- Balancing depth: bed width 25 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×