- 2082 Bhadra · 7 marks
Irrigation canal earthwork with vertical drop
Short answer
Canal is wholly in embankment. Banking areas are computed from bank dimensions and mean-area method yields 0.00 m³ cutting and 27,115.52 m³ banking.
Estimate earthwork for an irrigation canal with following data: Bed width of canal = 5 m; F.S.L = 1 m (full supply depth) and free board = 0.5 m. Top width of both banks = 2 m. Outer bank side slope = 1:1 (H:V) and canal section slope = 2:1 (H:V). Canal bed is proposed at uniform gradient of 1 in 5,000. A vertical drop of 0.5 m is to be provided at 0+400 m chainage.
| Chainage (m) | R.L of Ground (m) | R.L of Canal Bed (m) |
|---|---|---|
| 0+000 | 129.24 | |
| 0+200 | 129.00 | 130.96 |
| 0+400 | 129.20 | |
| 0+600 | 129.12 |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of each bank m.
- Canal side slope (inner slope of banks) and outer bank slope (H:V).
- Bed RL falls 1 in 5000 in the direction of chainage: bed at 0+200 is 130.96 m, so it is 131.00 m at 0+000 and 130.92 m at 0+400. The drop of 0.5 m at 0+400 lowers the bed to 130.42 m, then 130.38 m at 0+600.
- The bed is above the ground everywhere, so the canal is wholly in embankment.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0+000 | 129.240 | 131.000 | -1.760 | full banking | 0.000 | 47.528 |
| 0+200 | 129.000 | 130.960 | -1.960 | full banking | 0.000 | 51.872 |
| 0+400 (before drop) | 129.200 | 130.920 | -1.720 | full banking | 0.000 | 46.668 |
| 0+400 (after drop) | 129.200 | 130.420 | -1.220 | full banking | 0.000 | 36.198 |
| 0+600 | 129.120 | 130.380 | -1.260 | full banking | 0.000 | 37.018 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0+000 – 0+200 | 200.0 | 0.00 | 9,939.92 |
| 0+200 – 0+400 (before drop) | 200.0 | 0.00 | 9,854.00 |
| 0+400 (after drop) – 0+600 | 200.0 | 0.00 | 7,321.60 |
| Total | 0.00 | 27,115.52 |
Answer: Earthwork in cutting = 0.00 m³; earthwork in banking = 27,115.52 m³; total = 27,115.52 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Irrigation canal earthwork, 0-600 m · Estimating and Costing, chapter 6
- Channel earthwork with drop at 0+090 · Estimating and Costing, chapter 6
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3
- Crest width, cistern length of vertical drop, Q 1.55 · Irrigation and Drainage Engineering, chapter 7 · asked 2×
- Vertical drop crest level and width, Q 30 · Irrigation and Drainage Engineering, chapter 7
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×