Irrigation canal earthwork with vertical drop

Short answer

Canal is wholly in embankment. Banking areas are computed from bank dimensions and mean-area method yields 0.00 m³ cutting and 27,115.52 m³ banking.

Estimate earthwork for an irrigation canal with following data: Bed width of canal = 5 m; F.S.L = 1 m (full supply depth) and free board = 0.5 m. Top width of both banks = 2 m. Outer bank side slope = 1:1 (H:V) and canal section slope = 2:1 (H:V). Canal bed is proposed at uniform gradient of 1 in 5,000. A vertical drop of 0.5 m is to be provided at 0+400 m chainage.

Chainage (m)R.L of Ground (m)R.L of Canal Bed (m)
0+000129.24
0+200129.00130.96
0+400129.20
0+600129.12

Given data and assumptions

  • Bed width b=5b = 5 m; FSD =1= 1 m; free board =0.5= 0.5 m, so D=1.5D = 1.5 m; top width of each bank 22 m.
  • Canal side slope 2:12:1 (inner slope of banks) and outer bank slope 1:11:1 (H:V).
  • Bed RL falls 1 in 5000 in the direction of chainage: bed at 0+200 is 130.96 m, so it is 131.00 m at 0+000 and 130.92 m at 0+400. The drop of 0.5 m at 0+400 lowers the bed to 130.42 m, then 130.38 m at 0+600.
  • The bed is above the ground everywhere, so the canal is wholly in embankment.

Method

Total depth of canal section D=FSD+free board=1.00+0.50=1.50D = \text{FSD} + \text{free board} = 1.00 + 0.50 = 1.50 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+000129.240131.000-1.760full banking0.00047.528
0+200129.000130.960-1.960full banking0.00051.872
0+400 (before drop)129.200130.920-1.720full banking0.00046.668
0+400 (after drop)129.200130.420-1.220full banking0.00036.198
0+600129.120130.380-1.260full banking0.00037.018

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+000 – 0+200200.00.009,939.92
0+200 – 0+400 (before drop)200.00.009,854.00
0+400 (after drop) – 0+600200.00.007,321.60
Total0.0027,115.52

Answer: Earthwork in cutting = 0.00 m³; earthwork in banking = 27,115.52 m³; total = 27,115.52 m³.