Irrigation canal earthwork, 0-600 m

Short answer

Total depth D = 1.6 m, cutting slope 1:1, banking slope 1.5:1. All three stations are part cutting and part banking. Volumes: cutting = 3,285.68 m³, banking = 2,560.72 m³, total = 5,846.40 m³.

Calculate the quantity of earthwork of an irrigation canal with the following data. Bed width = 5 m, freeboard = 0.6 m, fully supply depth = 1 m, top width of both the bank = 2 m, side slope in cutting = 1:1, side slope in banking = 1½:1.

Distance (m)0300600 m
Ground level (m)325.24324.80324.43
Proposed bed level (m)324.001 in 3000 downward

Given data and assumptions

  • Bed width 55 m; FSD 11 m; free board 0.60.6 m, so D=1.6D = 1.6 m; top width of each bank 22 m; side slope in cutting 1:11:1 and in banking 1.5:11.5:1 (inner and outer faces of banks).
  • Bed RL 324.00 m at 0, falling 1 in 3000: 324.00, 323.90, 323.80 m at 0, 300, 600 m. (No drop is mentioned in the data.)

Method

Total depth of canal section D=FSD+free board=1.00+0.60=1.60D = \text{FSD} + \text{free board} = 1.00 + 0.60 = 1.60 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0325.240324.0001.240part cutting, part banking7.7381.829
300324.800323.9000.900part cutting, part banking5.3104.270
600324.430323.8000.630part cutting, part banking3.5476.703

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0 – 300300.01,957.14914.82
300 – 600300.01,328.541,645.90
Total3,285.682,560.72

Answer: Earthwork in cutting = 3,285.68 m³; earthwork in banking = 2,560.72 m³; total = 5,846.40 m³.

✓ Answer checked by Claude Opus 5.5 (high effort)