- 2075 Chaitra · 6 marks
Irrigation canal earthwork, 0-600 m
Short answer
Total depth D = 1.6 m, cutting slope 1:1, banking slope 1.5:1. All three stations are part cutting and part banking. Volumes: cutting = 3,285.68 m³, banking = 2,560.72 m³, total = 5,846.40 m³.
Calculate the quantity of earthwork of an irrigation canal with the following data. Bed width = 5 m, freeboard = 0.6 m, fully supply depth = 1 m, top width of both the bank = 2 m, side slope in cutting = 1:1, side slope in banking = 1½:1.
| Distance (m) | 0 | 300 | 600 m |
|---|---|---|---|
| Ground level (m) | 325.24 | 324.80 | 324.43 |
| Proposed bed level (m) | 324.00 | 1 in 3000 downward |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of each bank m; side slope in cutting and in banking (inner and outer faces of banks).
- Bed RL 324.00 m at 0, falling 1 in 3000: 324.00, 323.90, 323.80 m at 0, 300, 600 m. (No drop is mentioned in the data.)
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0 | 325.240 | 324.000 | 1.240 | part cutting, part banking | 7.738 | 1.829 |
| 300 | 324.800 | 323.900 | 0.900 | part cutting, part banking | 5.310 | 4.270 |
| 600 | 324.430 | 323.800 | 0.630 | part cutting, part banking | 3.547 | 6.703 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0 – 300 | 300.0 | 1,957.14 | 914.82 |
| 300 – 600 | 300.0 | 1,328.54 | 1,645.90 |
| Total | 3,285.68 | 2,560.72 |
Answer: Earthwork in cutting = 3,285.68 m³; earthwork in banking = 2,560.72 m³; total = 5,846.40 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Channel fully in banking, 0.5-1.5 km · Estimating and Costing, chapter 6
- Irrigation canal earthwork with vertical drop · Estimating and Costing, chapter 6
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Balancing depth: bed width 25 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3
- Stable depth and bed width: Q 5, d50 3 cm · Irrigation and Drainage Engineering, chapter 4