Channel earthwork and land area, bed 4 m

Short answer

Earthwork: cutting = 27.77 m³, banking = 2,316.23 m³. Permanent land obtained from mean width × length = 2,330.70 m².

Calculate the quantity of earthwork and area of permanent land required for the land acquisition purpose for a portion of a channel from following data: Bed width = 4 m; Free board = 45 cm; Side slope in cutting = 1:1; Side slope in banking = 1.5:1; Full supply depth = 1 m; Top width of bank = 3 m left and 1.5 m right.

Chainage90120150180210220
RL Ground109.8109.7109.55109.30109.15109.10
RL Bed109.52Bed slope 1:300 rising

Given data and assumptions

  • Bed width 44 m; FSD 11 m; free board 0.450.45 m, so D=1.45D = 1.45 m; top width of bank 33 m (left) and 1.51.5 m (right).
  • Side slope in cutting 1:11:1, in banking 1.5:11.5:1 (inner and outer faces of banks).
  • Bed level 109.52 m at chainage 90, rising at 1 in 300 with chainage (assumed direction): 109.52, 109.62, 109.72, 109.82, 109.92, 109.953 m.

Method

Total depth of canal section D=FSD+free board=1.00+0.45=1.45D = \text{FSD} + \text{free board} = 1.00 + 0.45 = 1.45 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+090109.800109.5200.280part cutting, part banking1.1989.372
0+120109.700109.6200.080part cutting, part banking0.32611.796
0+150109.550109.720-0.170full banking0.00015.800
0+180109.300109.820-0.520full banking0.00022.182
0+210109.150109.920-0.770full banking0.00026.966
0+220109.100109.953-0.853full banking0.00028.602

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+090 – 0+12030.022.87317.51
0+120 – 0+15030.04.90413.93
0+150 – 0+18030.00.00569.73
0+180 – 0+21030.00.00737.22
0+210 – 0+22010.00.00277.84
Total27.772,316.23

Permanent land

Width of land at a section = distance between the outer toes of the banks (banking) or canal top width plus the two bank/berm widths (cutting).

StationLand width (m)
0+09016.080
0+12016.880
0+15017.710
0+18018.760
0+21019.510
0+22019.760

Area of land == mean width × length, summed over the reaches =2,330.70= 2,330.70 m² =0.2331= 0.2331 ha.

Answer: Earthwork in cutting = 27.77 m³; earthwork in banking = 2,316.23 m³; total = 2,344.00 m³. Permanent land = 2,330.70 m².

✓ Answer checked by Claude Opus 5.5 (high effort)