- Asked 2/22
- 2080 Baisakh · 12 marks
Channel earthwork and land area, bed 4 m
Short answer
Earthwork: cutting = 27.77 m³, banking = 2,316.23 m³. Permanent land obtained from mean width × length = 2,330.70 m².
Calculate the quantity of earthwork and area of permanent land required for the land acquisition purpose for a portion of a channel from following data: Bed width = 4 m; Free board = 45 cm; Side slope in cutting = 1:1; Side slope in banking = 1.5:1; Full supply depth = 1 m; Top width of bank = 3 m left and 1.5 m right.
| Chainage | 90 | 120 | 150 | 180 | 210 | 220 |
|---|---|---|---|---|---|---|
| RL Ground | 109.8 | 109.7 | 109.55 | 109.30 | 109.15 | 109.10 |
| RL Bed | 109.52 | Bed slope 1:300 rising |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of bank m (left) and m (right).
- Side slope in cutting , in banking (inner and outer faces of banks).
- Bed level 109.52 m at chainage 90, rising at 1 in 300 with chainage (assumed direction): 109.52, 109.62, 109.72, 109.82, 109.92, 109.953 m.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0+090 | 109.800 | 109.520 | 0.280 | part cutting, part banking | 1.198 | 9.372 |
| 0+120 | 109.700 | 109.620 | 0.080 | part cutting, part banking | 0.326 | 11.796 |
| 0+150 | 109.550 | 109.720 | -0.170 | full banking | 0.000 | 15.800 |
| 0+180 | 109.300 | 109.820 | -0.520 | full banking | 0.000 | 22.182 |
| 0+210 | 109.150 | 109.920 | -0.770 | full banking | 0.000 | 26.966 |
| 0+220 | 109.100 | 109.953 | -0.853 | full banking | 0.000 | 28.602 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0+090 – 0+120 | 30.0 | 22.87 | 317.51 |
| 0+120 – 0+150 | 30.0 | 4.90 | 413.93 |
| 0+150 – 0+180 | 30.0 | 0.00 | 569.73 |
| 0+180 – 0+210 | 30.0 | 0.00 | 737.22 |
| 0+210 – 0+220 | 10.0 | 0.00 | 277.84 |
| Total | 27.77 | 2,316.23 |
Permanent land
Width of land at a section = distance between the outer toes of the banks (banking) or canal top width plus the two bank/berm widths (cutting).
| Station | Land width (m) |
|---|---|
| 0+090 | 16.080 |
| 0+120 | 16.880 |
| 0+150 | 17.710 |
| 0+180 | 18.760 |
| 0+210 | 19.510 |
| 0+220 | 19.760 |
Area of land mean width × length, summed over the reaches m² ha.
Answer: Earthwork in cutting = 27.77 m³; earthwork in banking = 2,316.23 m³; total = 2,344.00 m³. Permanent land = 2,330.70 m².
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Channel earthwork and land area, 50 cm fall · Estimating and Costing, chapter 6 · asked 2×
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Channel earthwork with drop at 0+090 · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Channel fully in banking, 0.5-1.5 km · Estimating and Costing, chapter 6
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3