- 2082 Baisakh · 8 marks
Channel earthwork, chainage 0+500 to 1+500
Short answer
Using ground vs bed level comparison, partial cutting/banking and full banking sections are identified. Volumes: cutting = 2,047.50 m³, banking = 35,930.00 m³, total = 37,977.50 m³.
Calculate the quantities of earthwork from the following data for channel section from chainage 0+500 to 1+500 m. Bed width = 5 m, side slope in cutting 1H:1V, side slope in banking 1.5H:1V, top width of both banks = 2.5 m, full supply depth = 1.5 m and free board = 0.5 m.
| Chainage | RL of Bed (m) | RL of ground (m) |
|---|---|---|
| 0+500 | 1000.50 | 1001.80 |
| 0+1000 | 1000.00 | 999.50 |
| 0+1500 | 999.50 | 997.50 |
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of each bank m.
- Side slope in cutting ; side slope of banks (inner and outer) (H:V).
- Chainages 0+500, 1+000 and 1+500 are 500 m apart.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 0+500 | 1,001.800 | 1,000.500 | 1.300 | part cutting, part banking | 8.190 | 4.970 |
| 1+000 | 999.500 | 1,000.000 | -0.500 | full banking | 0.000 | 33.375 |
| 1+500 | 997.500 | 999.500 | -2.000 | full banking | 0.000 | 72.000 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 0+500 – 1+000 | 500.0 | 2,047.50 | 9,586.25 |
| 1+000 – 1+500 | 500.0 | 0.00 | 26,343.75 |
| Total | 2,047.50 | 35,930.00 |
Answer: Earthwork in cutting = 2,047.50 m³; earthwork in banking = 35,930.00 m³; total = 37,977.50 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Channel fully in banking, 0.5-1.5 km · Estimating and Costing, chapter 6
- Channel earthwork with drop at 0+090 · Estimating and Costing, chapter 6
- Hill road earthwork, cutting 4 m / banking 6 m · Estimating and Costing, chapter 6
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Balancing depth: bed width 25 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Balancing depth with service bank and free board · Irrigation and Drainage Engineering, chapter 3
- Efficient rectangular section and triangular channel depth · Hydro Power, chapter 1 · asked 2×