Using ground vs bed level comparison, partial cutting/banking and full banking sections are identified. Volumes: cutting = 2,047.50 m³, banking = 35,930.00 m³, total = 37,977.50 m³.

Calculate the quantities of earthwork from the following data for channel section from chainage 0+500 to 1+500 m. Bed width = 5 m, side slope in cutting 1H:1V, side slope in banking 1.5H:1V, top width of both banks = 2.5 m, full supply depth = 1.5 m and free board = 0.5 m.

ChainageRL of Bed (m)RL of ground (m)
0+5001000.501001.80
0+10001000.00999.50
0+1500999.50997.50

Given data and assumptions

  • Bed width 55 m; FSD 1.51.5 m; free board 0.50.5 m, so D=2.0D = 2.0 m; top width of each bank 2.52.5 m.
  • Side slope in cutting 1:11:1; side slope of banks (inner and outer) 1.5:11.5:1 (H:V).
  • Chainages 0+500, 1+000 and 1+500 are 500 m apart.

Method

Total depth of canal section D=FSD+free board=1.50+0.50=2.00D = \text{FSD} + \text{free board} = 1.50 + 0.50 = 2.00 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
0+5001,001.8001,000.5001.300part cutting, part banking8.1904.970
1+000999.5001,000.000-0.500full banking0.00033.375
1+500997.500999.500-2.000full banking0.00072.000

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
0+500 – 1+000500.02,047.509,586.25
1+000 – 1+500500.00.0026,343.75
Total2,047.5035,930.00

Answer: Earthwork in cutting = 2,047.50 m³; earthwork in banking = 35,930.00 m³; total = 37,977.50 m³.