Channel fully in banking, 0.5-1.5 km

Short answer

Total section depth is 2.0 m. All stations lie fully in banking, so cutting area is zero. Using mean area method over 500 m intervals, earthwork in cutting = 0.00 m³, banking = 50,364.69 m³.

Workout the quantity of a portion of channel fully in banking with the following data:

DistanceR.L. of Ground levelProposed bed level
5001314.751316.00
10001314.90
15001314.20

The bed width of channel is 4.50 m. The bed slope is 1 in 5000. The full supply depth is 1.50 m and free board is 0.50 m. The top width of both side banks is 2.50 m in each bank. The side slope of banks is (1.5:1).

Given data and assumptions

  • Bed width 4.54.5 m; FSD 1.51.5 m; free board 0.50.5 m, so D=2.0D = 2.0 m; top width of each bank 2.52.5 m; side slope of banks 1.5:11.5:1 (inner and outer).
  • Bed falls 1 in 5000: 0.10 m per 500 m, so bed = 1316.00, 1315.90, 1315.80 m at 500, 1000, 1500 m. The canal is wholly in banking.

Method

Total depth of canal section D=FSD+free board=1.50+0.50=2.00D = \text{FSD} + \text{free board} = 1.50 + 0.50 = 2.00 m. At each station the bed level is compared with the ground level; e=e = GL − bed level.

  • If e≥De \ge D: full cutting, area Ac=(b+sce) eA_c = (b + s_c e)\,e (no banks needed).
  • If 0<e<D0 < e < D: part cutting, part banking. Cutting area Ac=(b+sce)eA_c = (b + s_c e)e; each bank stands hb=D−eh_b = D - e above ground, so bank area (both banks) Ab=(tL+tR)hb+(si+so)hb2A_b = (t_L + t_R)h_b + (s_i + s_o)h_b^2 with si,sos_i, s_o the inner and outer bank slopes.
  • If e≤0e \le 0: full banking, bed above ground. Bank top is H=D−eH = D - e above ground. Gross embankment =(T+soH)H= (T + s_o H)H with T=tL+tR+b+2siDT = t_L + t_R + b + 2 s_i D, and the canal space (b+siD)D(b + s_i D)D is deducted.

Volume between stations = mean area × distance (separately for cutting and banking).

Sectional areas

StationGL (m)Bed RL (m)ee (m)ConditionCutting area (m²)Bank area (m²)
5001,314.7501,316.000-1.250full banking0.00051.219
10001,314.9001,315.900-1.000full banking0.00045.000
15001,314.2001,315.800-1.600full banking0.00060.240

Volumes

BetweenDistance (m)Cutting (m³)Banking (m³)
500 – 1000500.00.0024,054.69
1000 – 1500500.00.0026,310.00
Total0.0050,364.69

Answer: Earthwork in cutting = 0.00 m³; earthwork in banking = 50,364.69 m³; total = 50,364.69 m³.

✓ Answer checked by Claude Opus 5.5 (high effort)