- 2076 Chaitra · 10 marks
Channel fully in banking, 0.5-1.5 km
Short answer
Total section depth is 2.0 m. All stations lie fully in banking, so cutting area is zero. Using mean area method over 500 m intervals, earthwork in cutting = 0.00 m³, banking = 50,364.69 m³.
Workout the quantity of a portion of channel fully in banking with the following data:
| Distance | R.L. of Ground level | Proposed bed level |
|---|---|---|
| 500 | 1314.75 | 1316.00 |
| 1000 | 1314.90 | |
| 1500 | 1314.20 |
The bed width of channel is 4.50 m. The bed slope is 1 in 5000. The full supply depth is 1.50 m and free board is 0.50 m. The top width of both side banks is 2.50 m in each bank. The side slope of banks is (1.5:1).
Given data and assumptions
- Bed width m; FSD m; free board m, so m; top width of each bank m; side slope of banks (inner and outer).
- Bed falls 1 in 5000: 0.10 m per 500 m, so bed = 1316.00, 1315.90, 1315.80 m at 500, 1000, 1500 m. The canal is wholly in banking.
Method
Total depth of canal section m. At each station the bed level is compared with the ground level; GL − bed level.
- If : full cutting, area (no banks needed).
- If : part cutting, part banking. Cutting area ; each bank stands above ground, so bank area (both banks) with the inner and outer bank slopes.
- If : full banking, bed above ground. Bank top is above ground. Gross embankment with , and the canal space is deducted.
Volume between stations = mean area × distance (separately for cutting and banking).
Sectional areas
| Station | GL (m) | Bed RL (m) | (m) | Condition | Cutting area (m²) | Bank area (m²) |
|---|---|---|---|---|---|---|
| 500 | 1,314.750 | 1,316.000 | -1.250 | full banking | 0.000 | 51.219 |
| 1000 | 1,314.900 | 1,315.900 | -1.000 | full banking | 0.000 | 45.000 |
| 1500 | 1,314.200 | 1,315.800 | -1.600 | full banking | 0.000 | 60.240 |
Volumes
| Between | Distance (m) | Cutting (m³) | Banking (m³) |
|---|---|---|---|
| 500 – 1000 | 500.0 | 0.00 | 24,054.69 |
| 1000 – 1500 | 500.0 | 0.00 | 26,310.00 |
| Total | 0.00 | 50,364.69 |
Answer: Earthwork in cutting = 0.00 m³; earthwork in banking = 50,364.69 m³; total = 50,364.69 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Hill road earthwork, km 8.50 to km 9.00 · Estimating and Costing, chapter 6
- Irrigation channel earthwork, bed 5 m, 1 in 3000 · Estimating and Costing, chapter 6
- Channel earthwork, chainage 0+500 to 1+500 · Estimating and Costing, chapter 6
- Canal earthwork, bed 3 m, free board 0.44 m · Estimating and Costing, chapter 6
- Channel earthwork and land area, bed 4 m · Estimating and Costing, chapter 6 · asked 2×
- Channel earthwork and land area, 50 cm fall · Estimating and Costing, chapter 6 · asked 2×
- Balancing depth: bed width 20 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Porosity at 50%, 75%, 90% hydration · Concrete Technology and Masonry Structure, chapter 4
- Balancing depth: bed width 25 m · Irrigation and Drainage Engineering, chapter 3 · asked 3×
- Cutting volume, 60 m, formation level 279.00 · Surveying I, chapter 9 · asked 7×