- 2065 Kartik (old course) · 5 marks
Canal outlet and module performance criteria
Short answer
A canal outlet diverts water from a distributary to a water course. Performance is judged by flexibility (ratio of relative discharge change to relative distributary discharge change), proportionality, sensitivity, setting, minimum modular head, silt-drawing capacity, and tamper-resistance.
Define canal outlet. What are the criteria for judging the performance of modules?
A canal outlet (module) is a small structure that diverts water from a distributary or minor to a water course and fixes the discharge supplied to the command area of the chak.
Criteria for judging the performance of a module
- Flexibility : shows how the outlet discharge responds to changes in the distributary discharge. is proportional, hyper-proportional and sub-proportional.
- Proportionality: the outlet should draw its share in proportion to the supply (equitable distribution).
- Sensitivity (with the distributary gauge reading and its depth): the outlet should be insensitive to small level changes; a low sensitivity gives a stable discharge. It is related to flexibility by .
- Setting: the ratio of the depth of the outlet's sill below FSL to the distributary depth; it controls the flexibility and the silt drawn.
- Minimum modular head: the least head loss needed for the outlet to work as designed. It should be small so that command is not lost.
- Silt-drawing capacity: the outlet should draw silt in proportion to the water, so that the distributary does not silt up.
- Tamper-resistance and cost: simple, cheap and not easily altered by farmers.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Non-modular, semi-modular outlet; module requirements · Irrigation and Drainage Engineering, chapter 7
- Interval and outlet discharge, 11 hour canal · Irrigation and Drainage Engineering, chapter 2
- Adjustable orifice semi-module design · Irrigation and Drainage Engineering, chapter 7
- Storage capacity, depth and water at outlet · Irrigation and Drainage Engineering, chapter 2
- CAD software modules: part, assembly, drafting · Computer Aided Design, chapter 1
- EVA; 450 cum brickwork canal · Project Engineering, chapter 4
- CPU criteria; RR Gantt and times · Operating System, chapter 2
All Irrigation and Drainage Engineering chapter 7 questions →