Layout planning of surface drainage system

Short answer

Field drains collect from bunded fields, discharging into collector drains that feed a main drain to a natural stream. Drains follow lowest ground; canals run on ridges, drains in valleys, and water levels are kept at least 0.3 m below outlets.

Discuss with sketch the layout planning of the various components of surface drainage system.

The layout of a surface drainage system is planned so that every field outlet discharges by gravity into a drain, and the water moves from small drains to larger ones until it reaches the natural outlet.

Components

  1. Field drains (laterals): shallow drains at the lower side of the fields, which receive water from the bunded fields' outlets.
  2. Collector drains: receive water from several field drains; run across or along the ground slope.
  3. Main (outfall) drain: receives the flow of the collectors and delivers it to a natural drain/river.
  4. Outlet: structure at the junction with the river with a flap gate or sill to prevent backflow.
  5. Structures: culverts at crossings of roads/canals, drops where the slope is steep.
        irrigation canal ======================
        | field | field | field |  <- bunded fields
  ------+-------+-------+-------+----- field drains
        |       |       |       |
        v       v       v       v
  ===========================>  collector drain
                |
                v  main drain
              ~~~~~~~~~~~~~~~~~~~ natural river

Planning principles

  • Drains follow the lowest lines of the land (natural depressions), and are kept parallel to the contours for the field drains and along the slope for collectors.
  • The irrigation canal runs on the ridge, the drains in the valleys; drain and canal do not run side by side.
  • The spacing of the field drains depends on the size of fields and the land slope (typically 100–300 m).
  • Water level in each drain is at least 0.3 m below the outlets it receives.
  • Minimum number of crossings and a short route to the outfall; the layout should avoid cutting through villages and roads.