- 2071 Magh · 4 marks
Evapo-transpiration mound
Short answer
An ET mound disposes effluent where groundwater is high or soil impermeable. A 0.5–1 m high sand mound with perforated pipes in gravel, 0.3 m topsoil and plants loses water by evapotranspiration; area sized from flow rate divided by infiltration plus evapotranspiration rate.
Describe the purpose and construction of an evapo-transpiration mound.
Purpose
An evapo-transpiration (ET) mound is an above-ground sand-fill bed for disposing of septic tank effluent where the soil is shallow, the ground-water table is high, the ground is rocky, or the infiltration rate is very slow, so that a soak pit or trench cannot work. The effluent is spread through the mound and is lost mainly by evaporation from the surface and transpiration by the plants growing on it; the rest percolates into the soil below.
Construction
- The site is ploughed, and a fill of clean coarse sand (and gravel) is built up to form a mound about 0.5-1.0 m high, with side slopes of 1 V : 3 H or flatter. The sand bed is placed on the loosened natural ground.
- Septic tank effluent is fed through a distribution box into perforated distribution pipes (75-100 mm dia) laid in a gravel bed (15-20 cm thick) inside the sand.
- The gravel is covered with a layer of geotextile or straw, then 0.3 m of topsoil, and the surface is grassed or planted with high-transpiring plants (banana, bamboo, canna, etc.).
- The area is sized from the effluent flow and the local evaporation: plan area .
- Surface runoff is kept off with a diversion drain, and the mound is fenced.
plants / grass
__________________
/ topsoil 0.3 m \
/--------------------\
/ gravel + distr.pipe \
/ coarse sand fill \
=========================== natural ground
(poor or rocky soil)
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Grit chamber: purpose, construction, design · Sanitary Engineering, chapter 7 · asked 4×
- Skimming tank: purpose and construction · Sanitary Engineering, chapter 7
- Pit privy: purpose and construction · Sanitary Engineering, chapter 9
- Drop manhole: need and construction · Sanitary Engineering, chapter 4 · asked 4×
- Service reservoirs: purpose and construction · Water Supply Engineering, chapter 7 · asked 2×
- Purpose and importance of specification · Construction Management, chapter 12 · asked 9×
- Estimating, purpose and data required · Estimating and Costing, chapter 1 · asked 6×