Short note: Testing of sewers

Short answer

Sewers are tested after laying to ensure watertightness, alignment, and freedom from obstruction. Key tests are water (hydrostatic) test with 1.5 m head, air test (100 mm water gauge, 5 min), smoke test, mirror-lamp test, ball test, and infiltration test for groundwater entry. Leakage must meet specifications.

Write a short note on testing of sewers.

Testing of sewers is done after laying and jointing, before backfilling, to check that the sewer is watertight, straight, true to gradient and free from obstruction. A defective sewer causes exfiltration (pollution of groundwater) or infiltration (extra flow).

Tests

  1. Water (hydrostatic) test: the length between two manholes is plugged at the lower end and filled with water to give a head of about 1.5 m above the crown at the upper end. After the pipe has absorbed water, the fall of level in a standpipe over a set time (often 30 min) is noted. Leakage must be within the specified limit.
  2. Air test: the sealed pipe is pressurised with air to about 100 mm of water gauge; the drop of pressure over 5 minutes should not exceed about 25 mm. It is quick and does not require water.
  3. Smoke test: smoke is forced into the sewer; escape at any point shows a leak (mostly for house drains and old sewers).
  4. Mirror and lamp test (alignment test): a mirror at one manhole reflects light from a lamp at the next manhole. A full bright circle shows that the sewer is straight and clear.
  5. Ball (obstruction) test: a ball slightly smaller than the pipe is rolled along; obstructions or projecting joint material stop it.
  6. Infiltration test: in a sewer below the water table, the flow entering is measured at the lower manhole.

Defects found are repaired and the test is repeated until the line is accepted.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Sanitary Engineering chapter 3 questions →