Chapter 3 · 4 hours
Design and Construction of Sewers
IOE past exam questions
Past questions and answers
20 questions set from this chapter, 2 of them more than once. Most repeated first.
- Asked 2 times
- 2079 Chaitra · 8 marks
- 2075 Baisakh · 8 marks
Determine the size of combined circular sewer for a discharge of 1.5 m³/s running half full. Assume a gradient of 1 in 2000 and Manning's rugosity coefficient N = 0.013 (constant for all flows). In the dry season if the flow drops to 0.5 m³/sec, does the flow maintain desired self-cleaning velocity of 0.60 m/sec?
Answer
Part 1: Size of the sewer
At half depth () the area and hydraulic radius are half and equal to the full values, respectively: , , so and, with constant, .
Full-pipe Manning's formula: with , .
Adopt a standard size m. Check: m/s (this is also the velocity at half depth), m³/s, so half-full capacity m³/s, greater than 1.5 m³/s. Velocity at design flow is above 0.6 m/s.
Part 2: Dry-season flow of 0.5 m³/s
Using the adopted m, m³/s and m/s:
For circular sections with constant , this ratio corresponds to (solving ). Then and
Since 0.77 m/s is greater than 0.60 m/s, the flow does maintain the self-cleansing velocity in the dry season.
Answer: m (computed 1.907 m). In the dry season the velocity is about 0.77 m/s, so the self-cleansing velocity is maintained.
- Asked 2 times
- 2080 Chaitra · 8 marks
- 2075 Bhadra · 8 marks
A sewer carries a runoff water to its 0.6 depth at maximum flow which is entering from the catchment area of 200 hectare having overall coefficient of runoff as 0.45 and time of concentration of 55 minutes. The velocity in the sewer is to be maintained as 1.5 m/s at peak flow. Determine the diameter and slope of the cement concrete sewer with the Manning's coefficient as 0.013.
Answer
Step 1: Peak runoff (rational method)
min. No rainfall formula is given, so mm/hr is assumed:
Step 2: Hydraulic elements at
For : , , , so and (n taken constant).
Step 3: Diameter
Here the velocity at peak flow is fixed ( m/s), so the flow area is
Adopt m.
Step 4: Slope
m. From Manning's formula :
(For the adopted m, the slope needed for the same 1.5 m/s is in 1281.)
Answer: Diameter about 1.990 m (adopt 2.10 m), slope about 1 in 1192 (0.6 depth, v = 1.5 m/s, Q = 2.923 m³/s).
- 2081 Chaitra · 8 marks
Design a sewer running 0.6 times full at maximum discharge for a town provided with the separate system serving a population of 250,000 persons. Water is from the water-work at a rate of 200 lpcd. Take a constant value of n = 0.013 at all depths of flow. The permissible slope is 1 in 600. Take peak factor of 2.25.
Similar questions: Separate sewer, 0.70 full, 100000 persons (2069 Bhadra)
Answer
Design flow
Assume 80% of the water supplied reaches the sewer. Peak factor = 2.25.
Data: , (constant), depth ratio .
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 1200 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.51 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Answer: Provide a circular sewer of D = 1200 mm at slope 1 in 600; it runs 0.6 full with v = 1.51 m/s at Q = 1.0417 m³/s (computed diameter 1.188 m). Such a large flow may also be carried by two parallel sewers.
- 2069 Bhadra · 8 marks
Design a circular sewer running 0.70 full at maximum discharge for a town provided with the separate system serving a population of 100000 persons. Water is supplied from the water works at a rate of 200 liters per capita per day. Take a constant value of n = 0.013 at all depths of flow. The permissible slope is 1 in 600. Take a peak factor of 2.25.
Similar questions: Separate sewer, 0.6 full, 250000 persons (2081 Chaitra)
Answer
Design flow
Assume 80% of the water supplied reaches the sewer. Peak factor = 2.25.
Data: , (constant at all depths), depth ratio .
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 900 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.30 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Answer: Provide a circular sewer of D = 900 mm at slope 1 in 600; it runs 0.7 full with v = 1.30 m/s at Q = 0.4167 m³/s (computed diameter 0.776 m).
- 2068 Magh (old course) · 10 marks
Design a sewer for separate system to carry a maximum flow of 0.5 m³/s at a slope of 1 in 1000 (10 in 10000). Sewer should run 0.7 times depth at maximum flow. Assume n = 0.012.
Answer
Given
Maximum flow m³/s, slope , , depth of flow at maximum flow.
Hydraulic elements
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 900 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.09 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Answer: Provide a circular sewer of diameter 900 mm at slope 1 in 1000; it runs 0.7 full with velocity 1.09 m/s at 0.5 m³/s.
- 2072 Magh · 8 marks
Design a sewer for separate system to carry peak flow 0.5 m³/sec at a slope 10 in 10000. Sewer should run 0.7 times depth at peak flow. The value of n in Manning's formula is 0.012. Will the self cleansing velocity be maintained in the sewer during dry weather flow? Take peak factor = 3.
Answer
Given
Peak flow m³/s, , , at peak flow, peak factor = 3.
Design for peak flow
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 900 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.09 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Check in dry weather flow
Average (dry weather) flow m³/s. For the adopted pipe ( m, m³/s, m/s):
At the minimum flow (about one-third of average, m³/s), and m/s.
Since the self-cleansing velocity is 0.6 m/s (0.75 m/s is preferred for sewage), the velocity at average dry weather flow, 0.83 m/s, is above 0.6 m/s; at minimum flow the velocity is above 0.6 m/s.
Answer: Provide 900 mm sewer at 1 in 1000. Velocity at peak flow = 1.09 m/s; at dry weather (average) flow = 0.83 m/s, so self-cleansing velocity is maintained at average flow.
- 2078 Chaitra · 8 marks
Calculate the diameter of a circular sewer laying at a slope of 1:150 when it is running just full with a discharge of 1.6 m³/sec and Manning's coefficient 0.013. Also, determine the discharge capacity if it is permitted to flow half full with the same gradients.
Answer
Part 1: Diameter when running just full
For a circular pipe flowing full, , with and :
Full velocity: m/s (check: m/s).
Adopt a standard diameter of 1.05 m (the calculated size 0.927 m is the minimum required).
Part 2: Discharge when half full
At : and , so and with constant,
(for the calculated diameter; for the adopted m the half-full capacity is m³/s).
Answer: D = 0.927 m (adopt 1.05 m); half-full discharge = 0.80 m³/s with the same velocity 2.37 m/s.
- 2076 Bhadra · 8 marks
Calculate the velocity and discharge in a sewer of circular section having diameter of 1.8 m laid at a gradient of 1 in 600. The sewer runs partially full at 0.75 depth. Use Manning's formula taking n = 0.013.
Answer
Given
m, , , depth of flow .
Full-flow values
Proportionate values at
For : , , , so and (n taken constant).
Answer: Velocity = 2.09 m/s; discharge = 4.28 m³/s.
- 2073 Bhadra · 8 marks
What will be the diameter of a circular concrete sewer carrying 2/3rd depth at the peak discharge of 0.70 m³/s laid in a gradient of 1 in 1000? Also check whether it is safe for non-scouring velocity or not. Assume Manning's 'n' as 0.012.
Answer
Given
Peak discharge m³/s, , , depth of flow .
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 1050 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.20 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
For non-scouring, the velocity must not exceed the maximum permissible value (about 3 m/s for concrete sewers), and for self-cleansing it should be at least 0.6 m/s. The velocity is 1.20 m/s at peak flow, which is within 0.6-3.0 m/s, so the sewer is safe against scouring and also self-cleansing at peak flow. (At lower flows the velocity falls, so flows below about 0.058 m³/s give less than 0.6 m/s, and the minimum flow should be checked separately.)
Answer: D = 1050 mm (computed 1.032 m); v = 1.20 m/s < 3 m/s, so safe.
- 2068 Bhadra (old course) · 10 marks
Calculate the diameter and velocity of a circular sewer at a slope of 1 in 400 when it is running just full at a discharge of 1 m³/sec. The value of n in Manning's formula is 0.012. Will the self cleansing velocity be maintained in the sewer when flow drops to 0.6 m³/s?
Answer
Part 1: Diameter and velocity (just full)
, , m³/s. For a full circular pipe:
Adopt m. For it: m³/s and m/s.
Part 2: Check at 0.6 m³/s
From the proportionate-flow relations of a circular section (constant ), this gives and , so
Since 1.62 m/s is greater than the self-cleansing velocity of 0.6 m/s, the sewer does maintain self-cleansing velocity when the flow drops to 0.6 m³/s.
Answer: D = 0.907 m (adopt 1.05 m), full velocity = 1.55 m/s; at 0.6 m³/s the velocity is 1.62 m/s, so self-cleansing is maintained.
- 2076 Baisakh · 8 marks
Calculate the diameter of a sewer to serve an area of 2.5 sq. km. with a population density of 400 persons per hectare. The average rate of water supply is 110 lpcd. The coefficient of runoff for 50% area is 0.5 and the remaining area is 0.6. The time taken to reach by the storm water at the considered point of sewer from the farthest point of the catchment area is 18 minute. Consider the storm duration of 21 minutes, values of Manning's n = 0.013 at all the depths of flow. The permissible slope is 1 in 500. Consider peak factor of 2.7. The sewer should run half full.
Answer
The sewer is taken as a combined sewer (sewage + storm water), running half full at maximum flow.
Step 1: Sanitary sewage
Area = 2.5 km² = 250 ha, so population . Assume 80% of the supply becomes sewage; peak factor = 2.7.
Step 2: Storm water
Weighted coefficient: . No intensity formula is given, so mm/hr is assumed for the given storm duration of 21 min (the time of concentration is 18 min, so a 21 min storm covers the whole catchment).
Step 3: Total design discharge
Step 4: Sewer design (half full, , )
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 3000 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 2.84 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Answer: Diameter required = 2.955 m; provide 3000 mm circular sewer (running half full, v = 2.84 m/s).
- 2073 Magh · 8 marks
Calculate the diameter of a sewer to serve an area of 12 sq.km with a population density of 250 persons per hectare. The average rate of sewage flow is 235 lpcd. The coefficient of runoff for 50% farthest area is 0.3 and rest of the area is 0.75. Time taken to reach storm water inlet from the farthest point of the catchment is 25 min. Assume storm duration = 20 min and n = 0.013.
Answer
The sewer is taken as a combined sewer. Missing data are assumed: slope 1 in 500, peak factor 3, sewage = 80% of the 235 lpcd given, sewer running half full.
Step 1: Sewage flow
Area = 12 km² = 1200 ha, population .
Step 2: Storm water
. Time of concentration = 25 min; storm duration = 20 min. The intensity for the given 20 min storm is taken from the assumed formula mm/hr:
(Because the storm of 20 min is shorter than = 25 min, the farthest part of the area has not yet contributed. Using the full area is on the safe side.)
Step 3: Total discharge
Step 4: Sewer design (, , half full)
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 5400 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 4.20 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is NOT within limits.
Answer: Diameter = 5.322 m; provide about 5400 mm (for such a large flow two or more sewers in parallel or a box/arch section may be used).
- 2074 Bhadra · 8 marks
What would be your preferable combined sewer section for an 85-hectare residential area having average runoff coefficient of 0.45 for serving altogether 1500 population? Average rainfall duration is 26 min. Self-cleansing velocity is 0.98 m/sec. Residential area have average elevation difference of 22 m in horizontal 5 km longitudinal distance. Assume any other appropriate data if required.
Answer
Assumptions
Sewage 135 lpcd of which 80% reaches the sewer, peak factor 3, for concrete, circular section running full at peak flow, intensity from the assumed formula mm/hr with storm duration 26 min.
Step 1: Discharge
Step 2: Slope
Step 3: Size
Adopt m. Then m/s and m³/s.
Step 4: Check
The full-flow velocity 2.29 m/s is greater than the required self-cleansing velocity 0.98 m/s and below the maximum of 3 m/s, so the section is satisfactory. At the very small dry weather flow (about 0.0056 m³/s) the velocity in this big pipe will be lower, so a small low-flow channel (cunette) in the invert or an egg-shaped section is advisable.
Answer: A circular combined sewer of about 1.200 mm diameter at slope 22/5000 (1 in 227), carrying 2.249 m³/s at velocity 2.29 m/s.
- 2070 Bhadra · 8 marks
The population of a town is 80,000 persons with a water supply rate of 145 lpcd. Assuming 80% of water supply contributes for sewage flow, taking Manning's N as 0.013, average slope as 1:400 and peak factor as 3, determine the minimum diameter of sewer required to carry the maximum discharge if it runs at 0.75 depths?
Answer
Design flow
Data: , (constant), depth ratio .
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 675 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.33 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Answer: Minimum diameter required = 0.632 m; provide 675 mm.
- 2071 Bhadra · 2+6 marks
Design a circular section of combined sewer from the following data:
Area to be served = 60 ha
Population = 65,000
Maximum permissible velocity = 3.2 m/sec
Time of entry = 5 minutes
Time of flow = 18 minutes
Rate of water supply = 235 lpcd
Overall runoff coefficient = 0.55
Assume suitably any other data required.
Answer
Part 1: Dry weather flow (sewage) [2 marks]
Assume 80% of 235 lpcd becomes sewage and the peak factor is 3.
Part 2: Design of the combined sewer [6 marks]
Storm water. min. With the assumed formula mm/hr:
Size. The sewer is designed to run full at peak flow. Take a design velocity of 3.0 m/s (below the maximum permissible 3.2 m/s):
Adopt m. Then m/s (less than 3.2 m/s).
Slope. From Manning's formula with m, :
Check at average dry weather flow m³/s: , , m/s. This is greater than 0.6 m/s, so the self-cleansing condition is satisfied.
Answer: Circular combined sewer, D = 1.05 m, slope about 1 in 116, carrying 2.535 m³/s at 2.93 m/s (running full).
- 2070 Magh · 8 marks
Calculate the diameter of combined circular sewer with following data: water supply rate = 100 lpcd, population density = 100 persons/hec, peak factor = 2.7, area = 35 hectares, rainfall intensity = 15 mm/hr, slope = 1/750, Manning's coefficient of rugosity = 0.011. The coefficient of run-off = 0.4. The sewer should run 0.6 depth full during peak flow.
Answer
Step 1: Sewage flow
Population . Assume 80% of the supply becomes sewage.
Step 2: Storm water
Step 3: Combined design discharge
Step 4: Diameter (, , )
For : , , , so and (n taken constant).
Size of the sewer
Discharge when running full:
Manning's formula for a full circular pipe, , with and :
Adopt the next standard size, D = 1050 mm.
Check of velocity and capacity
For the adopted pipe: m/s and m³/s.
The velocity at maximum flow, 1.46 m/s, lies between the minimum (0.6 m/s) and the maximum non-scouring limit (3.0 m/s), so it is satisfactory.
Answer: Diameter of the combined circular sewer = 0.942 m; provide 1050 mm.
- 2072 Asoj · 8 marks
List the various types of pipe materials used in sewer line. Describe them with merits and demerits.
Answer
Sewers are made of materials that must be strong, smooth, watertight, durable against sewage gases and acids, and economical. The common materials are given below.
1. Asbestos cement (AC) pipes
- Merits: light, easy to cut and lay, smooth inside (low friction), available in long lengths with few joints, resistant to corrosion.
- Demerits: weak against impact and heavy loads; attacked by acids and sulphates; health concern about asbestos fibres, so use is declining.
2. Cast iron (CI) pipes
- Merits: strong, durable, withstand high internal and external pressure and heavy traffic; long lengths; good for river crossings, inverted siphons, pumping mains.
- Demerits: costly, heavy; corrodes with sewage and acids unless lined; rough surface after rusting.
3. Concrete pipes (plain and reinforced, PCC and RCC)
- Merits: cheap, can be made at site in large sizes (up to 3 m), strong when reinforced, easy to repair, and widely available in Nepal.
- Demerits: attacked by acid wastes and hydrogen sulphide (crown corrosion), porous, heavy to transport, many joints in small lengths.
4. Vitrified clay / stoneware pipes
- Merits: resistant to acids and corrosion, smooth, impervious, durable, cheap in small sizes.
- Demerits: brittle and weak in tension, break in handling; available only in small sizes (up to 600 mm) and short lengths, so many joints.
5. Plastic pipes (PVC, HDPE, UPVC)
- Merits: very light, smooth (lower slope needed), corrosion free, flexible joints, long lengths, easy installation; popular for house connections and small sewers.
- Demerits: low strength under heavy loads and shallow cover; damaged by heat and sunlight; costly in large sizes.
6. Brick and stone masonry sewers
- Merits: can be built in any shape and large size at site using local material.
- Demerits: joints leak, rough surface, attacked by sewage, slow to construct, so used only for large old sewers with lining.
7. Steel pipes
- Merits: strong, light compared to CI, can have long lengths, welded watertight joints; used for pressure mains and siphons.
- Demerits: corrode easily (need lining and coating), costly.
For a modern urban sewer in Nepal, RCC pipes are used for large diameters, and HDPE/UPVC or stoneware for small ones.
- 2071 Magh · 8 marks
With the help of neat sketches, describe in detail the various steps of sewer construction.
Answer
Sewers are constructed in the following steps (for pipe sewers in an urban area).
Ground level
|<---- trench width ---->|
| \ / | Sheeting & strutting
| \ backfill / |
| \______________/ |
| | bedding | |
| | ( O pipe )| |
| |____________| |
gravel / concrete bed
1. Survey, setting out and alignment
The centre line and the levels (invert levels) of the sewer are marked on the ground from the design drawings with a theodolite and levelling instrument. Manhole locations are fixed. Sight rails (boning rods) are set up at intervals to control the gradient.
2. Excavation of trench
- The trench is excavated by hand or machine (excavator) to the required depth and width. Width = pipe diameter + 0.3-0.6 m working space on each side.
- The excavated soil is placed on one side of the trench at least 0.6 m from the edge, and the other side is left free for pipes.
- The depth must give a minimum cover of about 1 m to 1.2 m over the pipe (to protect from traffic).
3. Timbering (sheeting and shoring)
In loose soil or deep trenches (more than 1.5 m), the sides are supported by timber planks and struts or steel trench boxes to prevent collapse and accidents.
4. Dewatering
Water in the trench is removed by sump and pump, or well points, so that the pipe can be laid in dry condition.
5. Preparation of bed (bedding)
A bed of sand, gravel or 10-15 cm of concrete (1:3:6) is laid and levelled exactly to the slope. Holes are dug for the socket of the pipes. Rock is removed so the pipe rests uniformly.
6. Handling and laying of pipes
- Pipes are inspected for cracks and lowered into the trench by ropes, a chain pulley or crane.
- Laying starts from the downstream end, with the socket facing upstream, and each length is checked for level and line with a boning rod, so that the gradient is exact.
7. Jointing
- Spigot and socket joints: the annular gap is filled with tarred gasket (yarn), then cement mortar 1:1 or lead. A fillet is formed at the mouth.
- For concrete and PVC: collar joints, rubber ring joints or solvent joints. Joints must be watertight.
8. Testing of the sewer
Pipe lines are tested (see testing) before backfilling.
9. Backfilling
Selected soil, free from stones, is filled around and 30 cm above the pipe by hand, and compacted in layers (15-20 cm), then the rest of the trench is filled and road restored.
10. Manholes and house connections
Manholes are built at specified points, and the house connections are made with Y-junctions.
- 2070 Magh · 4 marks
State the steps involved in construction of sewers in urban area. Briefly describe the testing of sewer line.
Answer
Steps in construction of sewers in an urban area
- Setting out: survey; mark the centre line and levels of the sewer and manhole positions from the drawings. Place sight rails over the line.
- Excavation: dig the trench by machine or hand, wide enough for pipes (diameter + 0.6 to 1.0 m) and deep enough for the invert level, with a minimum cover of about 1 m. Keep excavated soil away from the edge.
- Timbering and dewatering: support trench sides with sheeting and struts, and remove water by pumping.
- Bedding: lay a bed of sand, gravel or concrete, levelled to the design gradient.
- Laying of pipes: lower the pipes carefully and lay from downstream to upstream, with sockets facing upstream, checking the line and level with boning rods.
- Jointing: make water-tight joints with cement mortar, tarred yarn, rubber rings or solvent cement.
- Testing: test the joints before backfilling.
- Backfilling and compaction in layers, then restoration of the road surface.
- Construction of manholes and house connections.
Testing of sewer line
Sewers are tested to ensure they are watertight and straight.
- Water (hydrostatic) test: a length of sewer between two manholes is plugged at the lower end, and filled with water to a head of about 1.5 m above the crown at the upper end. After allowing absorption, the drop in water level in a standpipe is measured over 30 min. The loss of water (leakage) must not exceed the limit given in the specification; otherwise the joints are repaired and the test repeated.
- Air test: the pipe is sealed and air at a pressure of about 100 mm of water is pumped in; the pressure should not fall by more than 25 mm in 5 minutes.
- Smoke test: smoke is blown in and any leak shows as smoke coming out (used for house drains).
- Mirror and lamp test: a mirror is held at one manhole and a lamp at the next; the circle of light shows the line and the clear bore of the pipe is checked for obstruction or sagging.
- Ball test: a ball of diameter about 13 mm less than the pipe is rolled through to check that there is no obstruction or projecting joint material.
- 2068 Magh (old course) · 4 marks
Write a short note on testing of sewers.
Answer
Testing of sewers is done after laying and jointing, before backfilling, to check that the sewer is watertight, straight, true to gradient and free from obstruction. A defective sewer causes exfiltration (pollution of groundwater) or infiltration (extra flow).
Tests
- Water (hydrostatic) test: the length between two manholes is plugged at the lower end and filled with water to give a head of about 1.5 m above the crown at the upper end. After the pipe has absorbed water, the fall of level in a standpipe over a set time (often 30 min) is noted. Leakage must be within the specified limit.
- Air test: the sealed pipe is pressurised with air to about 100 mm of water gauge; the drop of pressure over 5 minutes should not exceed about 25 mm. It is quick and does not require water.
- Smoke test: smoke is forced into the sewer; escape at any point shows a leak (mostly for house drains and old sewers).
- Mirror and lamp test (alignment test): a mirror at one manhole reflects light from a lamp at the next manhole. A full bright circle shows that the sewer is straight and clear.
- Ball (obstruction) test: a ball slightly smaller than the pipe is rolled along; obstructions or projecting joint material stop it.
- Infiltration test: in a sewer below the water table, the flow entering is measured at the lower manhole.
Defects found are repaired and the test is repeated until the line is accepted.
Questions from Old Question Collection (CE 656) (IOE BCE exam papers (CE 656) from 2068 to 2081, 21 papers). Answers are written for this site; check them against your class notes.
Chapter titles and hours from the IOE syllabus ↗