- 2079 Chaitra · 8 marks
Transition curve and shift for 250 m radius
Short answer
From equilibrium e=0.065, design speed is 60 km/h. Transition length Ls=40 m (govered by empirical formula 2.7V²/R). Shift s=0.27 m.
A horizontal curve of radius 250 m in a two-lane highway passing through rolling terrain in heavy rainfall area is designed with an equilibrium superelevation of 0.065. Design the length of a transition curve and the shift required to connect this curve to the straight section of the highway. Assume rate of introduction of superelevation of 1 in 150.
Assumptions
- In the IRC method the design superelevation fully balances the centrifugal force at 75% of the design speed, so it is the equilibrium superelevation for mixed traffic. With : km/h, so the design speed = 60 km/h.
- Two-lane carriageway m, pavement rotated about the centre line, rate of introduction 1 in .
- Extra widening for 2 lanes ( m): mechanical m, psychological m, so m.
Length of transition curve (largest of three criteria)
- Rate of change of centrifugal acceleration (IRC): m/s³
- Rate of introduction of superelevation (rotation about the centre line):
- IRC empirical (plain/rolling): m.
Adopt = 40 m.
Shift
Answer: transition length m; shift m.
Note: if 0.065 is taken as the equilibrium superelevation at the full design speed (), then km/h. The three criteria then give 12.1 m, 36.3 m and 22.3 m, so the superelevation criterion governs and m and m are unchanged.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Transition curve and edge elevations, hilly terrain · Transportation Engineering I, chapter 3
- Transition curve for NH, 200 m radius · Transportation Engineering I, chapter 3
- Transition curve length and shift, 7.2 m pavement · Transportation Engineering I, chapter 3
- Transition curve for 310 m radius · Transportation Engineering I, chapter 3
- Transition curve 400 m radius, 85 kmph · Transportation Engineering I, chapter 3 · asked 2×
- Setback on six lane highway, 450 m curve · Transportation Engineering I, chapter 3
- Highway curve through M 16 m from IP · Surveying II, chapter 6
- Transition curve R=300 m, deflection 40° · Surveying II, chapter 6
- Transition curve road 8 m, R=300 m, IP 3605 · Surveying II, chapter 6 · asked 3×