Reconnaissance survey information
Short answer
Reconnaissance collects field data on terrain, stream crossings and flood levels, soil type and geology, drainage, land use, construction material sources, climate, land cost, existing infrastructure, and social impacts, using simple instruments like abney level, compass, and GPS.
Describe the information to be collected during reconnaissance survey.
Reconnaissance is a rapid field study of the alternative routes that were picked in the map study. The following information is collected.
- Topography: general terrain, ridges, valleys, cross-slopes, possible gradients, mountain passes.
- Streams and rivers: number and size of stream crossings, high flood level, river course, bed material, suitable bridge sites.
- Soil: type of soil (clay, silt, sand, rock), suitability as subgrade, swamp or black cotton soil.
- Geology: rock type, landslide zones, faults, unstable slopes.
- Drainage conditions: water table, flooding, seasonal streams.
- Land use: forests, farms, settlements, graveyards, religious sites, protected areas.
- Construction materials: quarries, sand and aggregate sources, water and the lead distance.
- Climate: rainfall, snow, fog, wind, temperature.
- Existing roads and bridges, their conditions and possible use.
- Cost of land and property, utilities (electric, telephone, pipes) to be shifted.
- Labour and equipment availability, and accessibility to the site.
- Social and environmental aspects, e.g. effect on local people.
Instruments used: Abney level, compass, tape, pocket altimeter, GPS and camera. The final output is a comparison of the routes with rough lengths and cost, from which 1-3 are selected for the preliminary survey.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Why reconnaissance survey is conducted · Transportation Engineering I, chapter 2
- Updating information across survey stages · Transportation Engineering I, chapter 2 · asked 3×
- Final location and detailed survey · Transportation Engineering I, chapter 2 · asked 3×
- Studies in reconnaissance, pre-feasibility, feasibility · Hydropower Engineering, chapter 2 · asked 3×
- Average demand, village survey 2013, design 25 years · Water Supply Engineering, chapter 3 · asked 2×
- Total demand, village survey 2013, design 15 years · Water Supply Engineering, chapter 3 · asked 2×
- Ethnographic survey and its methods · Technology, Environment and Society, chapter 2