Good detailing and bar bending schedule

Short answer

Good detailing follows codes (IS 456, SP 34, IS 13920), provides proper anchorage, uses simple standard shapes, avoids congestion, ensures specified cover, places steel correctly, gives clear drawings with bar marks, and allows construction sequence. Bar bending schedule (BBS) lists each bar's mark, diameter, shape, number, length, total length, and weight for ordering, cutting, bending, and cost estimation.

Discuss about requirements for good detailing. Also describe bar bending schedule.

Requirements for good detailing

Reinforcement detailing means the exact arrangement of bars shown on the drawings. Good detailing should:

  1. Follow the code (IS 456, SP 34, and IS 13920 in seismic regions) for cover, spacing, anchorage, laps and curtailment.
  2. Provide proper anchorage and development length for every bar, with hooks or bends where space is limited.
  3. Keep reinforcement simple: use few bar diameters, standard shapes and regular spacing, so that it is easy to fabricate and place.
  4. Avoid congestion, especially at beam-column joints, so that concrete can flow and be compacted; keep the minimum clear spacing between bars.
  5. Give the specified cover (with spacers or cover blocks) for durability and fire resistance.
  6. Place bars where the stresses are: tension steel on the tension face, curtailed at the correct points, with stirrups closely spaced near the supports.
  7. Provide clear drawings: plan, elevation and sections with bar marks, diameters, spacing, lap positions and notes.
  8. Allow for construction: bars must be capable of being placed in the sequence of erection, and lap positions and construction joints must be shown.

Bar bending schedule (BBS)

A bar bending schedule is a table prepared from the structural drawings that lists every bar of a member with its mark, diameter, shape, number, length of each bar, total length and weight. It is used for ordering, cutting, bending, fixing and checking the steel, and for estimating the quantity (and cost).

Steps:

  1. Give each different bar a number (bar mark) on the drawing.
  2. Find the cutting length of each bar = straight length + hook allowances - bend deductions. In usual site practice, a 45° bend deducts 1ϕ1\phi, a 90° bend 2ϕ2\phi and a 135° bend 3ϕ3\phi, and a standard semicircular hook adds about 9ϕ9\phi (IS 2502 practice).
  3. Total length = number × length of each bar; weight = total length × unit weight, where unit weight =ϕ2162= \dfrac{\phi^2}{162} kg/m (ϕ\phi in mm).
Bar | Dia | Shape    | No. | Length | Total | Weight
mark| mm  |          |     | (m)    | L (m) | (kg)
----+-----+----------+-----+--------+-------+-------
 A  | 16  | straight |  3  | 4.20   | 12.60 | 19.9
 B  | 12  | cranked  |  2  | 4.40   |  8.80 |  7.8
 C  |  8  | stirrup  | 20  | 1.10   | 22.00 |  8.7

The schedule is checked against the drawings before the steel is cut.