- Asked 4/25
- 2082 Baisakh · 3 marks
- 2080 Bhadra · 2 marks
- 2075 Chaitra · 6 marks
- 2072 Kartik · 6 marks
Ductility requirements of RC beam with sketch
Short answer
Beam: b>=200 mm, b/D>=0.3, D<=L/4, two continuous bars, steel ratio 0.24sqrt(fck)/fy to 2.5%, bottom steel >=50% of top at joints. Closed stirrups with 135-degree hooks: min(d/4,8phi,100 mm) over 2d from supports, else d/2; splices only in middle half with hoops at 150 mm.
Explain the ductility requirements/ductile detailing for the reinforced concrete beam with neat sketches (requirements on reinforcement detailing in beams to ensure sufficient ductility).
Ductility is the ability of a member to undergo large inelastic deformation without significant loss of strength. In a beam it is obtained by making the tension steel yield before the concrete crushes and by preventing early shear failure. IS 13920 gives the following detailing rules.
Geometry
- Width mm and .
- Depth of clear span.
Longitudinal steel
- At least two bars (12 mm or more) continuous at top and at bottom.
- and on any face.
- Positive steel at a joint face is not less than 50% of the negative steel there.
- Along the span, neither positive nor negative capacity is less than 25% of the maximum capacity at either joint face.
- Lap splices only in the middle half of the span, never within the joint or within of a joint face. Not more than 50% of bars are spliced at one section and the splice is enclosed by closely spaced hoops (spacing mm).
Transverse steel (stirrups)
- Closed hoops with hooks and a tail of (not less than 75 mm) so that they stay effective after the cover spalls.
- Diameter mm (8 mm if clear span exceeds 5 m).
- Over a length from each joint face the spacing is the least of , and 100 mm, with the first hoop at 50 mm. Elsewhere the spacing is .
- Stirrups are designed for the shear that develops when plastic hinges form at both ends (capacity design).
Column |<-- 2d -->|<------ L/2 ------>|<- 2d ->| Column
-------+-+-+-+-+-+---------------------+-+-+-+-+-------
| | | | | | hoops at d/2 | | | | | |
| | | | | | | | | | | |
-------+-+-+-+-+-+---------------------+-+-+-+-+-------
50 mm, then s <= min(d/4, 8phi, 100) lap splice only
in middle half
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Importance of ductile detailing, sketches · Design of RCC Structure, chapter 12
- Ductile detailing of beams and columns · Design of RCC Structure, chapter 12 · asked 2×
- Column 350x350, 1440 kN, ductile detailing · Design of RCC Structure, chapter 10 · asked 2×
- Define ductility, joint detailing sketch · Design of RCC Structure, chapter 12 · asked 2×
- Ductile detailing of columns, confining steel · Design of RCC Structure, chapter 12 · asked 4×
- Ductile design per IS 13920, beam and column · Design of RCC Structure, chapter 12
- Ductile behaviour of reinforced and unreinforced masonry · Design of Timber and Masonry Structures, chapter 6
- Reinforced concrete column stresses in steel and concrete · Strength of Materials, chapter 3
- Pipe requirements; concrete, CI, PPR pipes · Water Supply Engineering, chapter 8