In detailed design, very detailed surveys, geotechnical investigation with boreholes and tests, hydrology update, hydraulic model tests, structural and hydraulic design, electro-mechanical and hydro-mechanical design, environmental management plan, and preparation of drawings, quantities, specifications, tender documents, cost estimate and schedule are carried out.

Discuss the hydropower development cycle with a flow chart. Explain the type of studies done in the detailed engineering design stage of a hydropower project.

Hydropower development cycle

 Master plan / Reconnaissance
            |
     Pre-feasibility study  --> drop? (stop)
            |
      Feasibility study     --> drop? (stop)
            |
   Detailed engineering design
            |
   Tender, contract, financing
            |
   Construction, commissioning
            |
   Operation and maintenance

Each stage is a decision gate: the project goes ahead only when the results are favourable, and the cost accuracy improves from about ±30% to ±5-10%.

Studies in the detailed engineering design stage

  • Surveys: Very detailed topographic survey (1:200-1:500) of all structure sites, and alignment survey of access roads and transmission line.
  • Geotechnical investigation: Additional boreholes and test adits at dam/weir, tunnel, powerhouse and slopes; in-situ and laboratory tests (rock mechanics, soil properties); construction material survey (borrow, quarry).
  • Hydrology update: Final flood, sediment and low-flow analysis; check of design discharge and installed capacity.
  • Hydraulic model tests: Physical or numerical model of the spillway, intake, desander, and energy dissipator.
  • Structural and hydraulic design: Final design of weir, intake, tunnel, penstock, surge tank, powerhouse and tailrace; stability and stress analysis; support and lining design.
  • Electro-mechanical and hydro-mechanical design: Turbine and generator selection, transformers, gates, governor and control, and transmission line.
  • Environmental management plan and resettlement plan.
  • Quantities, drawings, specification, tender documents and final cost estimate and construction schedule.