Spillway purposes and ogee advantages

Short answer

A spillway safely passes floods, controls reservoir level, and dissipates energy. An ogee crest provides the highest discharge efficiency (C≈2.2), maintains near-atmospheric pressure at design head, ensures smooth flow, and integrates well with concrete dams.

What are the purposes of a spillway? What are the advantages of ogee shape spillway? Explain.

Purposes of a spillway

  • Safe passage of floods: it passes surplus flood water from the reservoir to the d/s river and so prevents overtopping of the dam (a major cause of failure, especially for earth dams).
  • Reservoir level control: keeps the reservoir below the maximum water level and protects the dam, intake and powerhouse.
  • Energy dissipation: together with a stilling basin or bucket, it reduces the energy of the falling water, preventing scour at the dam toe.
  • Flood routing and sluicing: gives a controlled release, helps pass debris, ice and silt, and allows lowering of the reservoir in an emergency.

Advantages of an ogee-shaped spillway

The ogee crest has an S-shaped profile; the upper curve follows the lower surface of a free-falling nappe over a sharp-crested weir, and the lower curve is tangent to the downstream face.

        ~~~~~~~~ H
   ___  ~~~~~   .
  /   \ ~  nappe ' .
 |  crest \          '.
 |      ogee curve      '.   d/s face 1:0.8
 |                          '.
  • Highest discharge efficiency: Q=C L H3/2Q=C\,L\,H^{3/2} with C≈2.2C\approx2.2 (Cd≈0.74C_d\approx0.74), larger than for broad-crested or round-crested weirs, so a shorter crest can pass the same flood.
  • Pressure at crest close to atmospheric at design head, so there is no cavitation or vibration; cost of the spillway is low.
  • Smooth, stable flow with little energy loss and no separation; the nappe is supported by the crest.
  • It fits well as the overflow section of a concrete dam, can be fitted with gates, and links smoothly to a stilling basin, bucket or ski-jump.
  • Ability to pass debris and ice over the crest without clogging.