Performance reporting process
Short answer
Performance reporting collects and distributes performance information, including status and forecasts, to stakeholders. Steps: collect work data, analyse with variance and earned value, prepare reports per communication plan, distribute, and use feedback for corrective actions. Outputs include performance reports and change requests.
What is the performance reporting process?
Performance reporting is the process of collecting and distributing performance information, including status reports, progress measurements and forecasts, to stakeholders. It tells how resources are being used to achieve the project objectives. In PMBOK it was a process of Communications Management (now part of Monitor and Control Project Work / Manage Communications).
Steps in the process
- Collect work performance data: actual start/finish dates, hours, costs, percent complete, defects.
- Analyse the data: compare with the baseline (variance analysis), trend analysis, earned value (CPI, SPI), forecasts (EAC, completion date).
- Prepare reports in the format required by the communication plan.
- Distribute to stakeholders by the planned medium and frequency.
- Receive feedback and decide on corrective actions.
- Update plans, change requests and records.
Work data -> Analysis -> Report -> Stakeholders
^ |
+------ corrective action <------+
Types of reports
| Report | Content |
|---|---|
| Status report | Where the project stands now |
| Progress report | Work done in the period |
| Forecast report | Expected cost and completion |
| Variance report | Difference from baseline, causes |
| Earned value report | PV, EV, AC, CPI, SPI |
| Issue/risk report | Open issues and risks |
| Trend report | Pattern over time |
Contents of a good report
Accomplishments, planned next steps, schedule and cost status, risks and issues, change requests, and decisions needed.
Tools and techniques
Variance analysis, performance review meetings, earned value, forecasting, reporting systems, dashboards (red/amber/green).
Outputs
Performance reports, forecasts, change requests, updates to OPA.
Importance
Keeps stakeholders informed, supports early corrective action, and builds confidence.
Example: A weekly dashboard shows SPI 0.9 and CPI 1.0, and lists a risk from vendor delay, so the sponsor approves overtime to recover the schedule.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- EVA graphically; BCWS 9,50,000, BCWP 8,00,000 · Project Engineering, chapter 4
- Compare DSB-AM, DSB-SC, SSB, VSB; SSB by phase discrimination · Communication Systems, chapter 2