Procurement management process flow

Short answer

Procurement flow: Plan (make-or-buy, SOW, contract type), Conduct (solicit, select seller, award contract), Control (monitor performance, handle changes, payments), and Close (verify delivery, settle claims, archive). It ensures needed external resources are acquired and managed efficiently.

Sketch and explain the procurement management process flow.

Procurement management follows a sequence of four processes. The flow with inputs and outputs is shown below.

Sketch

 +------------------+   Procurement mgmt plan, SOW,
 | 1. PLAN          |   bid documents, criteria
 | PROCUREMENT      |-----------------+
 +------------------+                 v
 +------------------+   Selected sellers, contract
 | 2. CONDUCT       |-----------------+
 | PROCUREMENTS     |                 v
 +------------------+   Performance info, changes,
 | 3. CONTROL       |   payments
 | PROCUREMENTS     |-----------------+
 +------------------+                 v
 +------------------+   Closed contracts, archive
 | 4. CLOSE         |
 | PROCUREMENTS     |
 +------------------+

Explanation

  1. Plan procurement management
    • Identify needs not met by the team; make-or-buy analysis; market research.
    • Choose contract type (fixed price, cost-plus, time and materials).
    • Prepare procurement SOW, procurement documents (RFP, RFQ, IFB) and source selection criteria.
    • Output: procurement management plan, SOW, make-or-buy decisions.
  2. Conduct procurements
    • Advertise, hold bidder conferences, receive proposals.
    • Evaluate using criteria (price, technical approach, experience); negotiate.
    • Select seller and award the contract.
    • Output: selected sellers, agreements, resource calendars.
  3. Control procurements
    • Administer contract: monitor seller performance, inspections and audits, process payments and changes, resolve claims.
    • Output: performance information, change requests, updates.
  4. Close procurements
    • Verify all work done and accepted, finalise claims, settle payments, archive documents, collect lessons learned.
    • Output: closed procurements, updated OPA.

Summary table

ProcessGroupKey output
PlanPlanningProcurement plan
ConductExecutingContract
ControlM&CManaged contract
CloseClosingClosed contract

Processes overlap with other knowledge areas such as scope, cost and risk.