Project risk
Short answer
Project risk is uncertainty from within the project or its environment that can affect objectives. Sources include unclear requirements, estimation errors, new technology, resource shortages, and external factors. Risk is highest early, measured by probability and impact, and managed through identification, analysis, response planning and monitoring.
What do you mean by project risk?
Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective, such as scope, schedule, cost or quality. Project risk arises from uncertainty in any phase of the project and from the project's environment.
Sources of project risk
- Unclear or changing requirements and scope.
- Estimation errors for time and cost.
- Immature or new technology.
- Resource problems: lack of skilled people, turnover.
- Poor planning and weak management or communication.
- Dependence on suppliers and third parties.
- Organisational support, funding and politics.
- External factors: law, economy, weather, security.
Characteristics
- Uncertainty: not certain to occur.
- Has a cause and an effect.
- Level of risk is highest early in the project and decreases as it progresses.
- Can be positive (opportunity) or negative (threat).
- Measured by probability and impact.
Classification
| Category | Meaning | Example |
|---|---|---|
| Known risks | Identified, can be planned | Vendor delay |
| Unknown risks | Not identified | Unexpected regulation |
| Business risk | Chance of profit or loss | Product fails in market |
| Pure risk | Only loss | Fire, data loss |
Project risk management steps
- Plan risk management.
- Identify risks.
- Qualitative analysis (probability-impact matrix).
- Quantitative analysis (EMV, simulation).
- Plan responses.
- Monitor and control.
Probability
High | M | H | H
Med | L | M | H
Low | L | L | M
Low Med High Impact
Importance
Managing project risk improves the chance of delivering on time and within budget and increases opportunities.
Example: In a software project, the risk of "requirements change after design approval" has medium probability and high impact, so a change control process and prototype reviews are planned.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Risk · ICT Project Management, chapter 12
- Risk management plan · ICT Project Management, chapter 12
- Resolution of risk · ICT Project Management, chapter 12
- Risk audits · ICT Project Management, chapter 12
- Importance of risk response planning · ICT Project Management, chapter 12
- Risk identification techniques · ICT Project Management, chapter 12
- Define risk; types of project risk · Project Engineering, chapter 5 · asked 2×
- Gumbel flood at given risk, 50-year project life · Engineering Hydrology, chapter 6
- Sources of project risk · Project Engineering, chapter 5
- Internal risk of Nepalese construction project · Project Engineering, chapter 5