Risk

Short answer

A risk is an uncertain event or condition with a positive or negative effect on project objectives. It has probability and impact; risk exposure equals probability times impact. It differs from an issue (already occurred). Example: 20% chance of server failure causing Rs 5,00,000 loss yields EMV Rs 1,00,000.

What do you mean by risk?

A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives such as scope, schedule, cost and quality (PMBOK). Schwalbe: risk is the possibility of loss or injury; project risk includes both negative (threats) and positive (opportunities) risks.

Key points

  • Uncertainty: it may or may not happen.
  • Cause and effect: has a cause (condition) and, if it occurs, an impact.
  • Probability and impact: Risk exposure = probability × impact.
  • Negative risk (threat) and positive risk (opportunity).
  • Risk differs from an issue, which has already occurred.

Types of risk

TypeExamples
TechnicalNew technology failure, performance shortfall
ManagementPoor planning, communication
OrganisationalFunding cut, priorities change
ExternalLaw change, supplier failure, disaster
MarketCompetitors, demand
FinancialCost overrun, exchange rate

Risk attributes

  • Event, probability (0-1 or low/medium/high), impact, timing, and risk owner.

Risk exposure example

Probability of server failure 20%, loss Rs 5,00,000. Expected monetary value = 0.2 × 5,00,000 = Rs 1,00,000.

Risk management process

Plan -> Identify -> Qualitative -> Quantitative
     -> Plan responses -> Monitor and control

Risk tolerance

Different stakeholders have different attitudes: risk-averse, risk-neutral and risk-seeking.

Example: In a mobile banking project, a risk is "payment gateway API changes during development", which could delay the schedule by a month.