- 2081 Bhadra · 4 marks
Return period for bridge design at 5% risk
Short answer
Risk 0.05 over 25 years yields (1-1/T)^25=0.95, so 1-1/T=0.99795, giving T=488 years.
What return period will you adopt in the design of a bridge on a river if you are allowed to accept only 5% risk of flooding in the 25 years of expected life of the bridge?
The probability that a flood of return period T occurs at least once in n years of the structure's life is the risk
Given and years:
Answer: adopt a return period of about 488 years (design for the ≈ 500-year flood).
✓ Answer checked by Claude Sonnet 5.5
Related questions
- Gumbel design flood for highway bridge, 4% risk · Engineering Hydrology, chapter 6
- Define return period, frequency and risk · Engineering Hydrology, chapter 6
- Gumbel design flood, 21 years data, 40-year life · Engineering Hydrology, chapter 6 · asked 3×
- Return period of 350 m3/s design flood by Gumbel · Engineering Hydrology, chapter 6 · asked 2×
- Gumbel flood at given risk, 50-year project life · Engineering Hydrology, chapter 6
- Gumbel design flood, factor of safety 1.3, 45-year life · Engineering Hydrology, chapter 6
- Average demand, village survey 2013, design 25 years · Water Supply Engineering, chapter 3 · asked 2×
- PW sensitivity to investment, income, life by ±25% · Engineering Economics, chapter 6
- Bheri river suspension bridge collapse · Engineering Professional Practice, chapter 7
- Demand of rural municipality, base period 3 years · Water Supply Engineering, chapter 3