Qualitative versus quantitative risk analysis

Short answer

Qualitative analysis subjectively prioritizes risks using a probability-impact matrix, quick and done on all projects. Quantitative analysis uses numerical techniques like EMV, decision trees, and Monte Carlo to estimate objective probabilities and cost/time reserves, applied to top risks after qualitative analysis and requiring reliable data.

Differentiate qualitative and quantitative risk analysis process.

Qualitative risk analysis prioritises risks for further analysis or action by assessing and combining their probability of occurrence and impact, using subjective ratings. Quantitative risk analysis numerically analyses the effect of identified risks on the overall project objectives using numbers (money, time).

BasisQualitative analysisQuantitative analysis
NatureSubjective, descriptiveObjective, numerical
OutputPriority ranking (high, medium, low)Probability of meeting cost/time goals, expected values
Data neededExpert opinion, little dataReliable data, estimates, models
Time and costFast and cheapSlower, costly
DoneAlways, for every projectWhen needed: large or high-risk projects
SequenceFirstAfter qualitative
ScaleVery low to very highRs, days, percentage
ToolsProbability-impact matrix, risk categorisation, risk urgency assessment, expert judgmentSensitivity analysis, expected monetary value (EMV), decision tree, Monte Carlo simulation
Output example"Vendor delay: high priority""EMV of vendor delay = Rs 2 lakh; 70% chance to finish within 12 months"

Probability-impact matrix (qualitative)

Prob.
High | M | H | H
Med  | L | M | H
Low  | L | L | M
     Low Med High  Impact

EMV example (quantitative)

Risk: server failure with probability 0.2 and cost Rs 5,00,000. EMV = 0.2 × 5,00,000 = Rs 1,00,000.

Relation

Qualitative analysis filters the many risks into a short list; quantitative analysis is applied on top-priority risks to estimate contingency reserves and decide responses.

Example: In an ERP project, qualitative rating marks "data migration errors" as high; quantitative analysis estimates the expected delay at 3 weeks and cost at Rs 4 lakh to set the reserve.