- 2079 Bhadra · 6 marks
Qualitative and quantitative risk analysis methods
Short answer
Qualitative methods: probability-impact assessment, probability-impact matrix, risk categorization, urgency assessment, expert judgement. Quantitative methods: expected monetary value (EMV), decision tree analysis, sensitivity analysis (tornado diagram), Monte Carlo simulation, and PERT three-point estimate.
Explain the different methods of qualitative and quantitative analysis of risk.
Qualitative risk analysis methods
Qualitative analysis ranks risks by probability and impact using ordinal scales (low, medium, high).
- Probability and impact assessment: each risk is given a rating for both.
- Probability-impact matrix: combines the two ratings to give the priority.
Impact -> Low Medium High
Prob.
High Medium High High
Medium Low Medium High
Low Low Low Medium
- Risk categorisation: risks are grouped by source (technical, financial, etc.) to find the problem areas.
- Risk urgency assessment: risks that need an early response are dealt with first.
- Expert judgement and interviews.
Quantitative risk analysis methods
Quantitative analysis puts numbers on the effect of the risks.
- Expected monetary value (EMV): EMV = P x I. Example: P = 20% and loss = Rs 10 lakh give EMV = Rs 2 lakh.
- Decision tree analysis: branches show decisions and chance outcomes; the branch with the best expected value is chosen.
- Sensitivity analysis: one variable is changed at a time; a tornado diagram shows the most sensitive one.
- Simulation (Monte Carlo): many random runs of the cost or schedule model give a distribution and the probability of meeting the target.
- PERT three-point estimate: and variance .
- Interviewing and probability distributions obtained from experts.
Qualitative analysis is quick and used for all risks; quantitative analysis is slower and used for the high-priority risks.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Risk management; qualitative, quantitative; steps · Project Engineering, chapter 5
- Manage risk; qualitative and quantitative system · Project Engineering, chapter 5
- Why risk analysis is important in planning · Project Engineering, chapter 5
- Risk analysis with hydropower example · Project Engineering, chapter 5
- Risk identification and analysis, rural road · Project Engineering, chapter 5
- Qualitative versus quantitative risk analysis · ICT Project Management, chapter 12