Risk analysis with hydropower example

Short answer

Risk is an uncertain event affecting project objectives, measured as probability times impact. Analysis is qualitative (rating probability and impact on a matrix) then quantitative (EMV = probability x impact, sensitivity, simulation). For a 20 MW hydropower project, total EMV of five risks is Rs 114 million, used as contingency reserve.

Define project risk. How can risk be analysed? Explain with an example of a hydropower project.

Project risk

Risk is an uncertain event or condition which, if it occurs, has a positive or negative effect on the project objectives (scope, time, cost, quality). It is measured by the probability of the event and the size of its impact: Risk = Probability x Impact.

How risk is analysed

Risk analysis is done in two stages after identification.

  1. Qualitative analysis: give each risk a probability and an impact rating and place it on the matrix.
 Impact ->   Low      Medium     High
 Prob.
 High       Medium     High      High
 Medium      Low      Medium     High
 Low         Low       Low      Medium
  1. Quantitative analysis: for high-priority risks calculate EMV = probability x impact, and use sensitivity analysis or simulation for the cost and schedule effect.

Example: a 20 MW run-of-river hydropower project (assumed)

RiskProbabilityImpact (Rs million)EMV (Rs million)Priority
Flood damage to headworks0.215030High
Poor rock in tunnel0.410040High
Delay in land and compensation0.54020Medium
Price rise of cement and steel0.3309Medium
Transmission line delay0.35015Medium

The total EMV is 30 + 40 + 20 + 9 + 15 = Rs 114 million, which is used to set the contingency reserve. Rock condition and flood are first priority, so they get detailed responses (more drilling, insurance and flood-resistant design).