- 2073 Shrawan · 5 marks
Risk identification and analysis, rural road
Short answer
Identify risks by reviewing documents, site visits, checklists, brainstorming, interviews, and SWOT. Analyse qualitatively by rating probability and impact (score = P x I), then quantitatively by EMV for top risks, e.g. landslide P=0.3 and Rs 20 lakh gives EMV Rs 6 lakh. Rank risks and plan responses.
How can risk be identified and analysed for a rural road project? Explain the procedure.
Risk identification for a rural road project
- Review documents: DPR, survey, drawings, geotechnical report, estimate.
- Site visit and checklist: use a checklist from past rural road projects.
- Brainstorming and interviews with the local people, user committee, engineers and contractors.
- SWOT and assumption analysis.
Typical risks found: landslide and slope failure, monsoon damage and washout, land and right-of-way dispute, local opposition, material shortage and price rise, contractor with low capacity, late budget release, poor quality of earthwork and drainage, and lack of maintenance.
Risk analysis procedure
- Prepare a risk register with description, cause and effect.
- Qualitative: rate probability and impact (1 to 5) and score = P x I.
Impact -> Low Medium High
Prob.
High Medium High High
Medium Low Medium High
Low Low Low Medium
- Quantitative: for top risks, calculate EMV, e.g. landslide with P = 0.3 and cost Rs 20 lakh gives EMV = Rs 6 lakh.
- Rank the risks and give priority to high-score risks.
- Plan responses (retaining wall and drainage, early land agreement, community participation, inspection), assign owners, and monitor.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Tools and techniques for risk identification · Project Engineering, chapter 5 · asked 2×
- Project proposal; cost benefit analysis for road · Project Engineering, chapter 2
- Risk analysis with hydropower example · Project Engineering, chapter 5
- Qualitative and quantitative risk analysis methods · Project Engineering, chapter 5
- Why risk analysis is important in planning · Project Engineering, chapter 5
- Define risk; types of project risk · Project Engineering, chapter 5 · asked 2×
- Risk identification techniques · ICT Project Management, chapter 12
- Qualitative versus quantitative risk analysis · ICT Project Management, chapter 12
- Short note: construction procedure of gravel road · Transportation Engineering II, chapter 3 · asked 2×
- Road construction equipment and DBSD procedure · Transportation Engineering II, chapter 3