- 2072 Chaitra · 2+4 marks
Project proposal; cost benefit analysis for road
Short answer
A project proposal presents the idea, objectives, plan, cost, and benefits to secure approval. CBA for a road compares discounted present values of costs (construction, maintenance) and benefits (VOC savings, time savings, accident reduction). With capital NRs500M, annual benefits NRs90M, maintenance NRs10M, 20-year life, 10% discount rate, NPV is NRs181.08 million and B/C=1.31, making the road economically justified.
Define project proposal. Discuss cost benefit analysis for a road project.
A project proposal is a written document that presents the idea, objectives, plan, cost and expected benefits of a proposed project to convince the client, funder or approving authority to accept and finance it.
Cost benefit analysis for a road project
Cost benefit analysis (CBA) compares the money value of all costs and benefits of the road, discounted to present value, to decide whether the road is worth building.
Costs: construction (earthwork, pavement, structures), land acquisition and compensation, utility shifting, supervision, environmental mitigation, and periodic and routine maintenance.
Benefits:
- Saving in vehicle operating cost (fuel, tyres, repair).
- Saving in travel time of passengers and goods.
- Reduction in accidents.
- Benefit to induced and generated traffic.
- Wider benefits: access to markets, schools and health services, rise in land value, employment.
Steps: (1) forecast traffic with and without the road; (2) find unit costs and benefits; (3) work out yearly costs and benefits over the design life (say 20 years); (4) discount at the opportunity cost of capital; (5) compute NPV, B/C and EIRR; (6) carry out sensitivity analysis.
Illustrative calculation
Capital cost NRs 500 million (year 0); maintenance NRs 10 million per year; benefits NRs 90 million per year for 20 years; discount rate 10%.
Answer: and NRs 181.08 million, so the road is economically justified. The IRR on the net benefit of NRs 80 million per year is about 15.03%, above 10%.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Socio-economic survey and social cost benefit analysis · Project Engineering, chapter 2 · asked 3×
- Short note: Cost-benefit analysis · Project Engineering, chapter 2
- Proposal; feasibility study of a road project · Project Engineering, chapter 2
- Appraisal, proposal contents, input analysis · Project Engineering, chapter 2
- Procedure for developing a project proposal · Project Engineering, chapter 2 · asked 4×
- Contents of a good project proposal · Project Engineering, chapter 2 · asked 3×
- Optimize capacity by marginal cost-benefit · Hydropower Engineering, chapter 3
- Safety risk-benefit analysis; dispute resolution · Engineering Professional Practice, chapter 6
- Proposal for computer lab: title, technical, cost · Communication English, chapter 6 · asked 2×
- Proposal for computer lab: background, technical, cost · Communication English, chapter 6 · asked 2×