- 2073 Shrawan · 5 marks
Short note: Cost-benefit analysis
Short answer
Cost-benefit analysis (CBA) compares total discounted expected benefits and costs to judge project worth. It calculates NPV, B/C ratio, and IRR; a project is acceptable if NPV>0, B/C>1, IRR>required rate. Shadow prices and social discount rate are used in social CBA to account for externalities and market imperfections.
Write a short note on cost-benefit analysis.
Cost-benefit analysis (CBA) compares the total expected benefits of a project with its total costs, both expressed in money and discounted to present value, to judge whether the project is worthwhile.
Steps: identify all costs and benefits; assign money values (using shadow prices if market prices are distorted); choose a discount rate and project life; discount; calculate indicators.
Indicators:
A project is accepted if , and required rate.
Ordinary (private/financial) CBA counts only the cash costs and benefits to the owner at market prices. Social CBA (SCBA) counts all costs and benefits to society, including externalities and non-market effects, using shadow prices and a social discount rate.
Drawbacks: hard to give money value to intangible items (environment, human life, time); choice of discount rate affects results; forecasts are uncertain; ignores distribution of benefits among groups; externalities can be missed; costs may be underestimated and benefits overstated; not suitable alone for decisions with large social or ecological effects.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Socio-economic survey and social cost benefit analysis · Project Engineering, chapter 2 · asked 3×
- Project proposal; cost benefit analysis for road · Project Engineering, chapter 2
- Optimize capacity by marginal cost-benefit · Hydropower Engineering, chapter 3
- Safety risk-benefit analysis; dispute resolution · Engineering Professional Practice, chapter 6
- Cost variance analysis from standard and actual · Engineering Economics, chapter 1
- IRR with varying benefit and O&M; unrecovered balance · Engineering Economics, chapter 3