Skip to main content

Optimize capacity by marginal cost-benefit

Short answer

Add capacity as long as marginal benefit exceeds marginal cost. Annual cost per kW is about $99, and the step from 604 to 805 kW gives MB < MC, so optimum installed capacity is 604 kW.

A RoR hydropower plant is proposed in a river. Using the marginal cost and benefit method, optimize the installed capacity with the following data: interest rate = 12%; energy price = $0.08/kWh; fixed cost = $60 × 10⁶; variable cost (electro-mechanical) = $650/kW; annual O&M = 3% of variable cost; project life = 35 years.

% Time8.3316.6725.033.3341.6750.058.3366.6775.083.3391.67100
Power (kW)80560456440730016713011596897465

Capacity should be increased as long as the marginal benefit (MB) of the added capacity is at least its marginal cost (MC). The fixed cost ($60 × 10⁶) does not depend on the capacity, so it does not enter the marginal comparison.

Data

  • Interest i=12%i=12\%, life n=35n=35 years: CRF=i(1+i)n(1+i)n−1=0.12232CRF=\dfrac{i(1+i)^n}{(1+i)^n-1}=0.12232
  • Annual cost of 1 kW of electro-mechanical equipment c=650 (CRF+0.03)=650×(0.12232+0.03)=99.01c = 650\,(CRF+0.03) = 650\times(0.12232+0.03) = 99.01 USD per kW per year
  • Energy price = $0.08/kWh

Method

The power duration table gives the percentage of time each power level is equalled or exceeded. Raising the capacity from the next lower power level to the level PkP_k adds ΔP\Delta P kW, which can be used only for the percentage of time tkt_k for which that power is available:

ΔE=ΔP×tk100×8760,MB=0.08 ΔE,MC=c ΔP\Delta E = \Delta P \times \frac{t_k}{100} \times 8760,\quad MB = 0.08\,\Delta E,\quad MC = c\,\Delta P
Capacity step (kW)ΔP (kW)Time used (%)ΔE (kWh)MB ($)MC ($)MB/MC
604 → 8052018.33146,67111,73419,9000.59
564 → 6044016.6758,4124,6733,9601.18
407 → 56415725.0343,83027,50615,5441.77
300 → 40710733.33312,40924,99310,5942.36
167 → 30013341.67485,48938,83913,1682.95
130 → 1673750.0162,06012,9653,6633.54
115 → 1301558.3376,6466,1321,4854.13
96 → 1151966.67110,9668,8771,8814.72
89 → 96775.045,9903,6796935.31
74 → 891583.33109,4968,7601,4855.90
65 → 74991.6772,2735,7828916.49
0 → 6565100569,40045,5526,4357.08

Decision

The ratio MB/MC is below 1 for the step 604 → 805 kW (MB = $11,734 < MC = $19,900), so this extra capacity is not worth building. The step 564 → 604 kW has MB/MC = 1.18 (more than 1), so it is justified, and all the lower steps are also justified.

Answer: the optimum installed capacity is 604 kW (the capacity exceeded 16.67% of the time).

(If the curve is interpolated linearly between the 8.33% and 16.67% points, break-even occurs where 0.08×8760×t=99.010.08\times8760\times t = 99.01, i.e. at about 14.1% of the time, which corresponds to about 665 kW; with the tabulated power levels, 604 kW is the answer.)

✓ Answer checked by Claude Opus 5.5 (high effort)